Award of Contract- The Laurels- Temporary Accommodation
DecidedExecutive1 paper
AI summaryMid Devon Cabinet awards contract for The Laurels temporary accommodation scheme, with two abstentions and one vote against, citing health and safety duty.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedTwo councillors abstained, one voted against
MoneyNot disclosed in public papersAnnex A is marked Part II confidential
What happens nextNot specified in public papersContractor performance to be monitored frequently
Who it affectsPeople presenting as homelessHouseholds placed in Mid Devon temporary accommodation
What was decided
Cabinet awarded the contract to deliver accommodation units at The Laurels, enabling compliance with health and safety and other statutory duties for temporary accommodation. Report P2
Two members, Councillors N Bradshaw and J Wright, abstained and Councillor G DuChesne voted against the award.
Why
The Council has a legal duty to maintain the health and safety of its employees and people placed in its temporary accommodation, and the contract provides a framework to meet that duty. Report P2, P3
Failing to award risks uncontrolled costs, loss of LAHF3 funding and continued reliance on more expensive nightly paid accommodation to discharge temporary accommodation duties. Report P1
The purchase of The Laurels for temporary accommodation was previously agreed by Cabinet on 1 April 2025, and the contract is needed to deliver the scheme. Report P19, P20
What happens next
Contract performance will be monitored frequently, with corrective action if it falls below agreed parameters. Report P5
The contract has been reviewed and approved with the Council's legal services team ahead of award. Report P3
Implications
Financial: Risk of uncontrolled costs, loss of LAHF3 funding and continued nightly paid accommodation costs if the contract is not in place; PC sums may prove inadequate. Report P1, P5
Legal: A standard contract framework manages the contractor to meet the Council's legal obligations, including health and safety of staff and residents. Report P2, P3
Risk: Principal risk is failure to limit costs from additional works and programme delays, alongside normal large construction project risks. Report P5
Climate: Renovation includes works to improve the building's energy performance, though any improvement is not directly comparable to its previous commercial use; environmental impact was part of the contractor evaluation. Report P7
Staffing: The contract supports the Council's legal duty towards employees working on or supporting the temporary accommodation service. Report P2
Other: Project supports the Homes theme of the 2024-2028 Corporate Plan, specifically Objective 3.5 on responding to homelessness. Report P11
Who and where
Households placed in Mid Devon temporary accommodation Report P2, P11
Council employees involved in delivering and supporting temporary accommodation Report P2
People presenting as homeless in Mid Devon Report P11
Timeline
1 April 2025: Cabinet agreed to purchase The Laurels for temporary accommodation (Item 173). Report P19
24.03.2026: Statutory sign-offs by Section 151, Monitoring Officer, Chief Executive and Corporate Performance and Improvement Manager. Report P13, P14, P15
2026-04-07: Cabinet considered the contract award report.
Plain English for the jargon
LAHF3: Local Authority Housing Fund, round 3, a government grant stream for temporary accommodation.
PC sums: Prime Cost sums in a construction contract, allowances for items not yet selected or specified.
TA: Temporary Accommodation provided by the Council to discharge its homelessness duties.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item148
Resolved
The Council had a legal duty to maintain the health and safety of its employees and those that occupy temporary accommodation provided by the Council. The Contract would enable accommodation units to be delivered in compliance with relevant requirements and other statutory obligations. Note ( i )*Report previously circulated. (ii) Councillors: N Bradshaw and J Wright ABSTAINED from voting and G DuChesne voted AGAINST .
Word for word from the decision Mid Devon published for this meeting.Source: democracy.middevon.gov.uk
Subject: AWARD OF CONTRACT – THE LAURELS TEMPORARY ACCOMMODATION PROJECT
Cabinet Member: Cllr Jane Lock - Cabinet Member for Housing, Assets and Property Services
Responsible Officer: Simon Newcombe - Head of Housing and Health
Exempt: Annex A – PART II report
Information that links named contractors to their specific bid values is exempt under paragraph 3, Part 1 of Schedule 12A to the Local Government Act 1972 (as amended) as it contains information relating to the financial or business affairs of any particular person (including the authority holding that information).
Wards Affected: Lowman
Enclosures: Annex A – PART II report.
Section 1 – Summary and Recommendations
This report is to advise Members on the results for the tendering of the conversion and renovation of The Laurels, Station Road, Tiverton, EX16 4LF (formerly Vale Vets) for the purposes of providing temporary homelessness accommodation and agree the award of the contract.
Recommendation(s):
1. It is recommended that the award of The Laurels - Temporary Accommodation Project Contract to be awarded to Contractor 6.
2. Delegated authority is granted to the S151 Officer (in consultation with the Cabinet Member for Housing, Assets and Property Services) to complete the associated The Laurels Temporary Accommodation Project Contract (the Contract). Section 2 – Report (PART I)
1 Introduction
1.1The Laurels, Station Road, Tiverton EX16 4LF was purchased on 14th October 2025 following Cabinet approval granted on 1 April 2025, and an allocation of funding under the Local Authority Housing Fund Round 3 (LAHF3) (Local Authority Housing Fund: Round 3 prospectus and guidance - GOV.UK.)
1.2The LAHF3 funding provides the Council with a grant of around 50% towards the build/acquisition and refurbishment of property for use as dedicated, high-quality temporary homelessness accommodation (TA). This builds on the Council’s successful draw down of funds from the Ministry of Housing, Communities and Local Government (MHCLG) under the first LAHF round.
1.3The self-contained flats will be used by the Housing Options Service to provide those presenting as homeless with more appropriate temporary accommodation options and further reduce the use of hotels for this purpose.
1.4This contract (reference MDDC202504-004) covers the conversion of the main building from a former vets practice and two veterinary nurse flats into six self‑contained flats, including two level‑access units, along with all associated works. Planning permission for this project was granted on 3 December 2025 under planning reference 25/01453/FULL.
1.5Under the contract requirements the project is due for completion by 31 March 2027 with occupation shortly afterwards.
1.6Due to the nature and value of this procurement, the appropriate procedure was an open procurement process. This means that anyone who expressed an interest in the contract would be invited to tender.
1.7To ensure quality of contractors, several minimum requirements were set out within the Invitation to Tender (ITT).
2 Procurement Process
2.1A Tender Notice under Open Tender was published on 5th February 2026. A Tender advertisement was also placed in Find a Tender and Contracts Finder. The Invitation to Tender was issued via ProContract on 5 February 2026 and documents made available online via www.advantageswtenders.co.uk.
2.2The Invitation to Tender (ITT) requested interested parties to arrange viewings of the site and buildings on either 16 or 17 February 2026. Nine contractors attended viewings over the two days. 2.3 The tender pack included annotated site plans, annotated layout plans, various reports and surveys, and an itemised schedule of work for bidders to price against.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
2027/28 Draft Budget Update (00:04:00)RESOLVED that: 1. The proposed approach to balancing the 2027/28 General Fund and Housing Revenue Account budget gaps...
Minutes of the Previous MeetingThe minutes of the previous meeting held on 07 July 2026 were APPROVED as a correct record and SIGNED by the Leader. ...
2026/27 Budget Monitoring- Quarter 1The Cabinet had before it a report * from the Deputy Chief Executive (S151) on the 2025/26 Budgeting Monitoring quart...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.