Cabinet approved this item on Tuesday 7 July 2026. Below is the council's own wording, with the papers it was decided on.
Resolved
The minutes of the previous meeting held on 16 June 2026 were APPROVED as a correct record and SIGNED by the Leader.
Cabinet- Public Questions and Answers
Name of Questions person submitting Paul Paul Elstone Elstone In particular regarding the overspends on Modular Builds.
Despite routinely being disparaged for the questions I ask regarding the cost and quality of modular housing developments by this Council - I will continue to put the information (and this administration’s response) on public record.
This Capital Outturn provides further firm evidence that this administration is bank rolling the many different failings of the modular home developer.
As examples
Beech Road, Tiverton
The overspend on this Beech Road project Housing Revenue Accounts (HRA) 1014 to date is over £481,000.
Outrageously, this Council has paid storage payments to the developer who claimed some modules were delayed from being installed.
In September 2025 we were told the delay relates to:
1. The position of a 4-inch water main not being mapped by South West Water (SWW). Untrue. The position of the 4-inch main was fully mapped and as drawings on the planning portal showed. 2. Delays because Beech Road needed to be shut as it was an ambulance route also a school run. Untrue. Beech Road did not require closure and was never shut. 3. That delays were caused by South West Water not installing the 4-inch water main that needed diverting. Untrue. SWW were never contracted to do the 4-inch main diversion. However, SWW were legally required to do the final connection something they promptly did on being advised the developer that the diversion was complete. Somerlea Willand
The overspend so far on this project is over £429,000.
You are being told that some of this overspend was due to drainage requirements. What you are not being told is that the modular unit foundation plinth was installed around 30 centimetres too high resulting in major changes to the site including drainage falls.
Should you be in any doubt please visit the site and see the rear gardens - these should have been level but have had to be stepped.
School Close Bampton
The overspend to date on this project it seems is an incredible £1.4 million plus. Downstairs toilets were not included in the planning application approved by the Planning Committee - despite the building regulations dated 2016 saying they should have been.
The need to install downstairs WCs and drainage to nine of the dwellings would not have been included in the original cost provision – which will be a reason for some of this overspend.
Time prevents me from presenting other contractor failings related to Fir Close Willand and the Croft Estate Sandford. Something for another meeting.
Question 1: When will this Administration realise there are many and severe failings with the delivery of these modular home projects, both technical and high cost. Failings which require full investigation?
Response from the Cabinet Member for Housing, Assets and Property Services: You continue to raise and regularly re-raise similar points in relation to the Council’s social housing delivery programme. Numerous detailed responses have been provided that confirm we are content with all of the officer procurement due diligence and contractual management for these schemes, that have been delivered in full compliance with the required building standards. With regard to ensuring VFM, I would also refer you back to previous responses that in addition to our own internal programme control measures we also receive independent verification from external auditors and Homes England.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Minutes of the Previous MeetingMinutes | 202 KB | Download |
PDF |
Response to Public Question time: June 2026Report | 384 KB | DownloadRead as text |
Follow Cabinet at Mid Devon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Sep 2026 | 2027/28 Draft Budget Update (00:04:00)RESOLVED that: 1. The proposed approach to balancing the 2027/28 General Fund and Housing Revenue Account budget gaps... | Approved | Open |
| 4 Aug 2026 | Minutes of the Previous MeetingThe minutes of the previous meeting held on 07 July 2026 were APPROVED as a correct record and SIGNED by the Leader. ... | Approved | Open |
| 4 Aug 2026 | 2026/27 Budget Monitoring- Quarter 1The Cabinet had before it a report * from the Deputy Chief Executive (S151) on the 2025/26 Budgeting Monitoring quart... | Noted | Open |
| 4 Aug 2026 | Air Source Heat Pump (ASHP) Contract 2026-2030The Cabinet had before it a report * from Head of Housing and Health on the Air Source Heat Pump (ASHP) Contract 2026... | Decided | Open |
| 4 Aug 2026 | Notification of Key DecisionsThe Cabinet had before it, and NOTED , the notification of Key Decisions *. Note: * Key Decisions previously circulated. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.