Boho X - draft findings and proposed management response
AgreedFinance1 paper
Corporate Affairs and Audit Committee agreed this item on Wednesday 6 April 2022. Below is the council's own wording, with the papers it was decided on.
It was agreed by the Executive in March 2020 that Boho X would be a 20 storey office development with 100,000 square feet of floor space (plan A). In August 2020 the design of Boho X was reviewed and the downsizing of the building to six storey, 60,000 square feet development was subsequently initiated (plan B). The project was the responsibility of the Regeneration and Culture Directorate. The original sponsor was the then Executive Director of Growth and Place, moving to the Head of Economic Growth on the former’s compulsory redundancy. The Council expected to let Boho X in its entirety for ten years in the near future. The purpose of the audit was to provide assurance to management that procedures and controls within the system ensured that: · The project had used and met the requirements of the established Project Management Framework in operation at the Council. · Meetings and communications directing the design and development of the project were carried out in line with proper procedures and fully recorded. · Decisions relating to the project had been taken, recorded, published and communicated in line with the Council’s Constitution (including the Scheme of Delegation). · Key information relating to the project was available and had been retained to support decisions. · There were appropriate project governance arrangements in place including processes for managing project risk. The auditor’s key ... view the full minutes text for item 21/54
Word for word from the decision Middlesbrough published for this meeting.Source: moderngov.middlesbrough.gov.uk
notes the findings of the draft internal audit report on the project management of Boho X and the proposed management responses; and considers whether it wishes to make further comment on the issues raised by the audit and the proposed actions.
Report for: Key decision: Confidential: Is the report urgent? Information Not applicable No Not applicable
Contribution to delivery of the 2021-24 Strategic Plan People Place Business The report sets out proposed actions to improve programme and project governance across the Council in the light of the findings of this audit, subject to further comment from the Committee.
Ward(s) affected There is no direct impact on any ward from the recommendations of this report.
1 What is the purpose of this report?
1. Following discussions with the Chair and Vice Chair of Corporate Affairs and Audit Committee, and direction from the Committee at its meeting on 15 October 2020, the Director of Finance and Director of Legal and Governance Services commissioned an internal audit review of project management of the Boho X project. Group leaders were also consulted on the scope of the audit.
Why does this report require a Member decision?
2. As the internal audit was requested by members of Corporate Affairs and Audit Committee, it is appropriate for members to consider the summary draft findings and proposed management responses before finalisation of the audit report.
Report Background
Boho X
3. To be delivered by the end of 2022, Boho X will be specialist digital office space over two separate sites (Boho 8 and Boho 10) at St. Hilda’s Enterprise Zone in the Middlehaven regeneration area of Middlesbrough, which has been designated by the Council as a focal point for the growth of digital and creative businesses in the town.
4. Boho X is jointly funded by the Tees Valley Combined Authority (TVCA) and this Council and at a revised estimated final cost of £21m, is the biggest single project within the Council’s portfolio at the present time.
5. The plan for the building has seen one significant change since the start of the project. It was agreed by the Executive in March 2020 that Boho X would be a 20 storey office development with 100,000 square feet of floor space (plan A). In August 2020 the design of Boho X was reviewed and the downsizing of the building to six storey, 60,000 square feet development was subsequently initiated (plan B).
6. The project is the responsibility of the Regeneration and Culture Directorate. The original sponsor was the then Executive Director of Growth and Place, moving to the Head of Economic Growth on the former’s compulsory redundancy.
7. The Council expects to let Boho X in its entirety for ten years in the near future.
Council policies on the planning and delivery of programmes and projects
8. All of the Council’s activity must be delivered in line with the law and the rules established by its Constitution, including the member / officer protocol, delegated authorities, decision making procedures and standing orders. Where relevant, it must also comply with the conditions of external funding agreements.
9. In addition, the Council has a specific policy in respect of programme and project management, which is approved by the Executive and supported by a detailed programme and project management framework (PPMF) for officers working on such activities within the Council.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Corporate Affairs and Audit Committee at Middlesbrough and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.