Strategic Plan 2021-24 - Progress at Year-End 2021/22

Agreed Scrutiny 4 papers

Overview and Scrutiny Board agreed this item on Wednesday 22 June 2022. Below is the council's own wording, with the papers it was decided on.

Item20/104

Resolved

AGREED that the information provided be noted.
Word for word from the decision Middlesbrough published for this meeting. Source: moderngov.middlesbrough.gov.uk

Follow this further

Built from Middlesbrough's papers

What the report saysPro

Report to Overview and Scrutiny Board

MIDDLESBROUGH COUNCIL

Report of: The Mayor Chief Executive

Submitted to: OSB

Date: 22 June 2022

Title: Corporate Performance Update: 2021/22 Year End Results

Report for: Discussion

Status: Public

Strategic priority: All

Key decision: No Why: Not applicable

Urgent: No Why:

Executive summary This report advises the OSB of progress against corporate performance at Year-End 2021/22, providing the necessary information to enable the OSB to discharge its performance management responsibilities. This report also asks that the OSB:  notes the proposed amendments to Executive actions outlined at Appendix 1  notes achievement in implementation of the Strategic Plan 2021-24 at 2021/22 Year- End, detailed in Appendix 2  notes the Council’s updated position in relation to Strategic Risk  notes 2021/22 Year-End achievement in delivery of the 2021/22 Directorate Priorities, detailed in Appendix 3

1 Purpose

1. This report advises the OSB of corporate performance at Year-End 2021/22.

Background and relevant information

2. The Council’s Scheme of Delegation gives the OSB collective responsibility for monitoring corporate strategic performance, together with associated action.

3. This report provides the necessary information to enable the OSB to discharge its performance management responsibilities, setting out progress against Executive action, the Strategic Plan and other key associated items, together with actions to be taken to address any issues identified.

4. The projected Year-End 2021/22 financial outturns are presented separately and so not repeated here. Where performance has had a significant impact on finances this is highlighted within the body of the report.

5. As part of continuous improvement in performance and risk management, the Council’s Leadership Management Team (LMT) has implemented monthly reviews of corporate performance utilising a Directorate Performance dashboard, drawing data from a range of performance systems.

6. The output from these sessions is reflected through quarterly updates to the Executive and Overview and Scrutiny Board and covering in addition, progress in delivering actions agreed by the Executive, key Directorate performance issues and other performance-related matters.

Overall progress at Year-End

7. The Council’s performance overall at Year-End saw a slight improvement in performance from the Quarter Three reported position, with progress towards expected performance standards as set out in the Council’s risk appetite, achieved in three out of seven areas.

Progress in delivering Executive actions

8. Actions agreed by the Executive to deliver approved decisions are tracked by LMT on a monthly basis. If, subsequent to the Executive’s approval, any action is found to be no longer feasible or appropriate, or cannot be delivered within the approved timescales, the Executive is advised of this an approval sought of alternative actions or amended timescales.

9. At Year-End, 39 of 51 live actions (76.5%) were reported as on target to be delivered by the agreed timescales, improved from the 72% reported at Quarter Three and slightly below the 90% standard of achievement of actions, with 7 amendments sought for Executive approval set out at Appendix 1. All remaining Executive actions are expected to be achieved within their approved timescales.

10. The amendments relate to:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Corporate Performance Results: Appendix 1 /104Appendix 190 KB Download
PDF
Corporate Performance Results: Appendix 2 /104Appendix 315 KB Download
PDF
Corporate Performance Results: Appendix 3 /104Appendix 7 pages Download
PDF
Strategic Plan 2021-24: Progress at Year-End 2021/22Report 404 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Middlesbrough

Search all
  1. Strategic Plan 2021-24 - Progress at Year-End 2021/22This decision
  2. Strategic Plan 2021-2024 – Progress at Quarter One 2021/2022Agreed
  3. Strategic Plan 2020-23 - Progress at Year-End 2020/21Agreed

More from Middlesbrough Overview and Scrutiny Board

All decisions
MeetingDecisionOutcome
7 Jul 2026 Revised Terms of Reference - Council Engagement with Faith and Belief GroupsAGREED that the revised Terms of Reference for the Board’s short review into Council engagement with Faith and Belief... Agreed Open
7 Jul 2026 2025/26 Revenue & Capital Year End OutturnIt was agreed that the Director of Finance would bring the Treasury Management report to the next meeting of OSB to p... Agreed Open
15 Apr 2026 Scrutiny Chairs UpdateAGREED that the information presented be noted. Agreed Open
15 Apr 2026 Executive Forward Work ProgrammeIt was agreed the service area would be approached for further information on this matter. A Member queried if, in re... Agreed Open
15 Apr 2026 Forward Plan Actions ProgressAGREED that the information presented be noted . Agreed Open