Agreed that the Section 24 Action plan was formally closed. 2. Approved the change control outlined in the report at paragraph 6.1 to close CT5.07 in the Corporate Governance Improvement Plan: Monitoring of Appraisal completions - 95% of staff in work to have had an appraisal. 3. Noted the progress against the Corporate Governance Improvement Plan. 4. Noted that the Corporate Peer Challenge was currently underway and would inform the Council’s future continuous improvement activity.
Word for word from the decision Middlesbrough published for this meeting.Source: moderngov.middlesbrough.gov.uk
AGREES that the Section 24 Action plan is formally closed. AGREES the change controls outlined in the report at 6.1 to close CT5.07 in the Corporate Governance Improvement Plan, Monitoring of Appraisal completions - 95% of staff in work to have had an appraisal. NOTES the progress against the Corporate Governance Improvement Plan NOTES the Corporate Peer Challenge which is currently underway and will inform the Council’s future continuous improvement activity.
3 Rationale for the recommended decision(s)
3.1The report demonstrates that the Council has responded effectively and at pace to deliver the improvements set out in both the Corporate Governance Improvement Plan and the Section 24 report.
4 Background and relevant information
4.1On 18 September 2023, Council received a report that set out the activities of Phase Three of the proposed Corporate Governance Improvement Plan, alongside the associated governance arrangements providing oversight of delivery. It also received a report from the Council’s External Auditors which made statutory recommendations in relation to the Council’s governance. This report set out that all activity in that plan is now complete, as well as an update on delivery against the Corporate Governance Improvement Plan.
4.2The activities in the improvement plan comprise ten workstreams, each with a milestone delivery plan which is monitored and reported monthly to the Leadership Team, the Independent Improvement Advisory Board and at each full Council.
4.3This report is being considered by Council on 15 January 2025. During this week the Council is taking part in an independent Corporate Peer Challenge, led by the Local 2 This document was classified as: OFFICIAL
Government Association. The outcome of this process will be presented to Council in due course and inform future continuous improvement activity. It is expected that an update will be provided to Council at the March meeting.
5. Performance management methodology
5.1The Council’s and Programme and Project Management policy set out the methodology used to assess and report on progress against delivery, which is applied across the Corporate Governance Improvement and Section 24 delivery plans.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.