CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Middlesbrough Borough Council
Overview and Scrutiny Board, Wednesday 18 March 2026 at 4.30pm

Final Report of Place Scrutiny Panel - Barriers to Regeneration

Agreed Scrutiny 1 paper

AI summaryMiddlesbrough's Overview and Scrutiny Board has backed a Place Scrutiny Panel report on barriers to regeneration and passed it to the Executive, with proposals covering the town centre, safety, transport, culture and green spaces.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreed
MoneyNot stated
What happens nextReferred to the ExecutiveThe Executive will consider the report and its recommendations.
Who it affectsMiddlesbrough town centre and residentsResidents, visitors, students, businesses and town centre users in Middlesbrough.

What was decided

The Board endorsed the final report of the Place Scrutiny Panel and its recommendations on barriers to regeneration. Report P1

The Board agreed to refer the report to the Executive for consideration.

Why

The Place Scrutiny Panel carried out a review into barriers to regeneration in Middlesbrough, hearing from council officers and partners across six meetings in 2025. Report P19, P20, P15

What happens next

The Executive will consider the report and decide how to act on the panel's eleven recommendations. Report P1

If agreed, the Council would carry out a survey of college and university students about how to improve the town. Report P2

If agreed, officers would apply for an extension to Cleveland Unit for Reducing Violence funding or seek alternative money for the Night-Time Economy Pilot Project, due to end in March 2026. Report P12

Options considered

  • Chosen: Endorse the report and refer it to the Executive. The Board agreed this was the appropriate route for the panel's recommendations.

Implications

  • Climate: The report recommends increasing green spaces and creating a new town centre attraction such as a winter garden, with claimed health, environmental, social and economic benefits. Report P8
  • Risk: The report recommends more Neighbourhood Safety Wardens and joint work with businesses on street drinking compliance to improve town centre safety. Report P6, P7
  • Other: The report recommends redeveloping Linthorpe Road to create a more compact retail centre and increase footfall. Report P5
  • Other: The report recommends working with Tees Valley Combined Authority on transport links, including a possible park and ride and improved bus services. Report P9
  • Financial: The report recommends seeking an extension to CURV funding or alternative funding for the Night-Time Economy Pilot Project, which is due to end in March 2026. Report P12

Who and where

  • Residents of Middlesbrough Report P3, P4, P6, P8
  • Town centre visitors and businesses Report P4, P5, P7, P8
  • College and university students in Middlesbrough Report P2
  • Users of Middlesbrough Town Hall and its box office Report P10
  • Middlesbrough Development Corporation as a partner Report P11

Timeline

  • 29 April 2025: Place Scrutiny Panel meeting held Report P20
  • 30 June 2025: Place Scrutiny Panel meeting held Report P20
  • 29 September 2025: Place Scrutiny Panel meeting held Report P20
  • 27 October 2025: Place Scrutiny Panel meeting held Report P20
  • 6 November 2025: Place Scrutiny Panel meeting held Report P20
  • 22 December 2025: Place Scrutiny Panel meeting held Report P20
  • March 2026: Night-Time Economy Pilot Project due to end Report P12

Plain English for the jargon

  • ABCs: Acceptable Behaviour Contracts
  • ASB: Anti-social Behaviour
  • CBO: Criminal Behaviour Orders
  • CPN: Community Protection Notice
  • CURV: Cleveland Unit for Reducing Violence
  • FPN: Fixed Penalty Notice
  • MDC: Middlesbrough Development Corporation
  • PSPO: Public Space Protection Order
  • SBC: Stockton on Tees Borough Council
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item25/74

Resolved

AGREED: 1. The final report and its recommendations be endorsed. 2. The report be referred to the Executive for consideration.
Word for word from the decision Middlesbrough published for this meeting. Source: moderngov.middlesbrough.gov.uk

Follow this further

Built from Middlesbrough's papers

What the report saysPro

Report to Overview and Scrutiny Board

MIDDLESBROUGH COUNCIL

Final Report of the Place Scrutiny Panel

BARRIERS TO REGENERATION

CONTENTS

THE AIM OF THE SCRUTINY REVIEW Page 2

TERMS OF REFERENCE Page 2

BACKGROUND INFORMATION Page 2

SUMMARY OF EVIDENCE:

Term of Reference A - To establish what the Barriers to Regeneration are in Page 3 Middlesbrough Term of Reference B – To identify good practice from other local authorities in Page 5 relation to attracting businesses to the area Term of Reference C – To investigate what measures are in place to make people Page 6 feel safer in our town centre and neighbourhoods Term of Reference D – To gain an understanding of current legislation available to Page 9 local authorities to tackle anti-social behaviour CONCLUSIONS Page 10

RECOMMENDATIONS Page 11

ACKNOWLEDGEMENTS Page 11

ACRONYMS Page 12

BACKGROUND PAPERS Page 12

1 THE AIM OF THE SCRUTINY REVIEW

1. The aim of the review was to identify the barriers to regeneration in Middlesbrough and investigate how more businesses can be attracted to the town.

TERMS OF REFERENCE

2. The terms of reference, for the scrutiny panel’s review, are as follows:

A) To establish what the Barriers to Regeneration are in Middlesbrough

B) To identify good practice from other local authorities in relation to attracting businesses to the area

C) To investigate what measures are in place to make people feel safer in our town centre and neighbourhoods

D) To gain an understanding of current legislation available to local authorities to tackle anti- social behaviour BACKGROUND INFORMATION

3. The mainstay of UK high streets for much of the 20th century, retail is now in structural decline. The growth of e-commerce means councils and communities are now nursing an increasing number of vacant shops in town centres.

4. Around one in seven shops and one in five shopping centres units are now empty. Some town centres are now caught in a vicious cycle of boarded-up shops, declining attractiveness and falling footfall.

5. Already under pressure from online sales, the pandemic triggered a wave of retailer insolvencies in 2020. Some retailers like M&S and Next decided to relocate to out-of-town retail parks. Rents and service charges on retail parks are generally lower than in town centres. Internal store layouts are typically more efficient, while easy car parking and often longer opening hours add to the retail park appeal for shoppers. Higher energy costs and interest rates are squeezing households and businesses alike.

6. Although all towns across the UK have been affected by the decline in high street shopping, poorer towns have generally been hit harder than more prosperous towns. While there are exceptions to the rule, in general more deprived towns have a higher proportion of empty shops than relatively prosperous towns. One obvious explanation for this relationship is that people in more affluent towns have more disposable income.

7. An economic assessment on Middlesbrough had been carried out in 2017/181 it was recognised in the assessment that Middlesbrough needed to shift its focus away from a ‘need based’ retail model toward a ‘want based’ experience economy.

8. The assessment identified that Middlesbrough should prioritise; leisure, culture, events and unique offerings that cannot be replicated online.

1 Middlesbrough Town Centre Economic Assessment 2017/18 – Report to Middlesbrough Council

2 9. Additional recommendations from the assessment included, increase use of transport links and improve signage, investment in public realm and safety and strategies to reduce vacancies through alternative uses.

10. A further economic assessment on Middlesbrough was carried out in 2025 which focused on Middlesbrough’s current position including emerging trends and how Middlesbrough was responding to those.

11. Key points summarised from the initial findings of the latest assessment included:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Final Report of Place Scrutiny Panel: Barriers to RegenerationReport 167 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Middlesbrough

Search all
  1. Final Report of Place Scrutiny Panel - Barriers to RegenerationThis decision
  2. Final report of the Adult Social Care and Health Scrutiny Panel - Healthy Placemaking with a focus on Childhood ObesityNoted
  3. Final report of the Place Scrutiny Panel - Barriers to RegenerationNoted
  4. Final Report of the Adult Social Care and Health Scrutiny Panel - Healthy Place MakingAgreed
  5. Draft Final Scrutiny Report - Healthy Placemaking with a Focus on Childhood ObesityAgreed
  6. Final Report of the Place Scrutiny Panel - Empty PropertiesApproved

More from Middlesbrough Overview and Scrutiny Board

All decisions
MeetingDecisionOutcome
7 Jul 2026 Revised Terms of Reference - Council Engagement with Faith and Belief GroupsAGREED that the revised Terms of Reference for the Board’s short review into Council engagement with Faith and Belief... Agreed Open
7 Jul 2026 2025/26 Revenue & Capital Year End OutturnIt was agreed that the Director of Finance would bring the Treasury Management report to the next meeting of OSB to p... Agreed Open
15 Apr 2026 Scrutiny Chairs UpdateAGREED that the information presented be noted. Agreed Open
15 Apr 2026 Executive Forward Work ProgrammeIt was agreed the service area would be approached for further information on this matter. A Member queried if, in re... Agreed Open
15 Apr 2026 Forward Plan Actions ProgressAGREED that the information presented be noted . Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies