Middlesbrough Borough Council
Executive, Wednesday 2 September 2026 at 5.00pm

Cremator Refurbishment Programme

Approved Executive 3 papers

AI summaryThe Executive approved adding Teesside Crematorium to the Council's Capital Programme and a refurbishment scheme to extend the cremator's life by at least ten years, cut nitrogen oxide emissions by about 65%, and meet DEFRA emissions guidance.

AI summaryIn plain English

Written from the decision wording; the report is not read yetPDF Pro
OutcomeApprovedInclusion in Capital Programme and refurbishment works
MoneyNo figure stated; funded from existing Council capital resources
What happens nextImplement worksCremator refurbishment, emissions and structural upgrades
Who it affectsTeesside CrematoriumService users and Council operations

What was decided

Approved adding Teesside Crematorium to the Council's Capital Programme and allocating capital funding from existing Council funded capital resources.

Approved the implementation of the proposed programme of works, covering cremator refurbishment, refractory replacement, bypass flues, NOx abatement, emissions monitoring upgrades, mechanical and electrical improvements, and structural alterations.

Noted the independent condition assessment and options appraisal, including the operational, environmental and compliance risks of maintaining existing infrastructure without investment.

Why

The investment would extend the operational life of the existing cremator plant by at least ten years and improve service resilience.

It would support compliance with DEFRA Process Guidance Note PG5/2(25) and reduce nitrogen oxide emissions by approximately 65%.

Officers had identified operational, environmental and compliance risks in continuing without investment.

What happens next

Proceed to deliver the approved programme of works at Teesside Crematorium using existing Council funded capital resources.

Implications

  • Environment: Nitrogen oxide emissions from the cremator would fall by approximately 65%.
  • Legal: The scheme supports compliance with DEFRA Process Guidance Note PG5/2(25).
  • Risk: The condition assessment set out operational, environmental and compliance risks of continuing without investment.
  • Financial: The project would be funded from the Council's existing capital resources, with no external sum stated.
  • Other: The investment would extend the operational life of the existing cremator plant by at least ten years.

Who and where

  • Users of Teesside Crematorium and their families
  • Middlesbrough Council, as operator and capital funder
  • Local air quality, through reduced nitrogen oxide emissions

Timeline

  • At least ten years after works: Extended operational life of the existing cremator plant.

Plain English for the jargon

  • NOx: Nitrogen oxides, a group of pollutant gases produced by combustion.
  • NOx abatement: Technology to reduce nitrogen oxide emissions.
  • Refractory: The heat resistant lining inside the cremator, which is being replaced.
  • Bypass flue: An alternative flue route allowing the cremator to operate during maintenance or in different modes.
  • DEFRA PG5/2(25): The Department for Environment, Food and Rural Affairs Process Guidance Note for crematoria emissions.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item26/44

Resolved

ORDERED that Executive: 1. Approve the inclusion of the Teesside Crematorium in the Council’s Capital Programme, and the allocation of capital funding from existing Council funded capital resources to deliver the project. 2. Approve the implementation of the proposed programme of works, including cremator refurbishment, refractory replacement, installation of operational bypass flues, NOx abatement technology, emissions monitoring upgrades, mechanical and electrical improvements, and associated structural alterations. AGREED that Executive: 3. Noted the findings of the independent condition assessment and options appraisal, including the operational, environmental and compliance risks associated with maintaining the existing infrastructure without investment. 4. Noted that the proposed investment would extend the operational life of the existing cremator plant by at least ten years, improve service resilience, support compliance with DEFRA Process Guidance Note PG5/2(25), and reduce nitrogen oxide (NOx) emissions by approximately 65%.
Word for word from the decision Middlesbrough published for this meeting. Source: moderngov.middlesbrough.gov.uk

Follow this further

Built from Middlesbrough's papers

What the report saysPro

Report to Executive
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Cremator Options Assessment Summary /44Appendix A 55 KB Copy on its way
PDF
Impact Assessment /44Appendix B 104 KB Copy on its way
PDF
Cremator Refurbishment ProgrammeReport 183 KB Copy on its way

At this meeting

Whole meeting

More from Middlesbrough Executive

All decisions
MeetingDecisionOutcome
2 Sep 2026 Final Report of the Overview and Scrutiny Board - The Council's Approach to PovertyORDERED that the Executive: 1. Note the report of the Overview and Scrutiny Board on The Council’s Approach to Povert... Noted Open
2 Sep 2026 Risk and Opportunity Management PolicyORDERED that Executive approve the 2026–2029. Approved Open
2 Sep 2026 Place Strategy to Investment ProspectusORDERED that Executive: 1. Note the work undertaken by the Place Leaders Partnership to develop a Place Strategy for ... Noted Open
2 Sep 2026 Stainton Way Highway ImprovementsORDERED that Executive approve the Stainton Way Highway improvements scheme, considering the issues raised and propos... Approved Open