Cabinet, Wednesday 4 May 2016 at 2.00pm

Gilwern S106 funding

Approved Executive 1 paper

Cabinet approved this item on Wednesday 4 May 2016. Below is the council's own wording, with the papers it was decided on.

Item2

Resolved

We resolved that the projects set out below be approved, with the schemes not emboldened being carried out when the remaining funding is received: Project Amount Gilwern S106 Funding £ 03 Upgrading of canal towpath in Gilwern 18,000.00 04 Extension/improvement of Gilwern Scooter Park 21,555.00 05 Install fitness equipment at Gilwern Playing Field 7,065.00 06 Construct petanque terrain in Gilwern 3,960.00 07 New central heating system – Gilwern Community Centre 11,475.00 08 Heaven Scent Garden/Learning Zone, Ty Mawr 12,000.00 09 Clydach Playing Field Spectator Barrier 5,940.00 10 Gilwern OEC – toilets/kitchen/glazing 56,802.00 11 Upgrade Gilwern bowling green/pavilion 26,751.00 12 Gilwern Playing Field Improvements 34,391.00 13 Clydach – additional junior playing pitches 53,000.00 14 Incredible Edibles Llanelly Hill food project 1,215.00 15 Llanelly Hill Welfare Hall car park 22,441.00 Unallocated Balance 33,398.00 Total 307,993.00 Grant offers to be made to each of the successful applicants subject to the standard terms and conditions of grant set out in Appendix A to the report and subject to each applicant providing evidence of their security of tenure for an unexpired period of at least ten years, prior to the payment of any grant monies.
Word for word from the decision Monmouthshire published for this meeting. Source: democracy.monmouthshire.gov.uk

Follow this further

Built from Monmouthshire's papers

What the report saysPro

Report to Cabinet

SUBJECT: GILWERN SECTION 106 FUNDING

MEETING: CABINET DATE: 4th May 2016 DIVISION/WARDS AFFECTED: LLANELLY HILL

1. PURPOSE: 1.1 To decide on the allocation of grants to specific projects from the Section 106 funding available in Gilwern in 2016/17.

2. RECOMMENDATIONS that 2.1 the projects set out below be approved, with the schemes not emboldened being carried out when the remaining funding is received: Project Amount Gilwern S106 Funding £ 03 Upgrading of canal towpath in Gilwern 18,000.00 04 Extension/improvement of Gilwern Scooter Park 21,555.00 05 Install fitness equipment at Gilwern Playing Field 7,065.00 06 Construct petanque terrain in Gilwern 3,960.00 07 New central heating system – Gilwern Community Centre 11,475.00 08 Heaven Scent Garden/Learning Zone, Ty Mawr 12,000.00 09 Clydach Playing Field Spectator Barrier 5,940.00 10 Gilwern OEC – toilets/kitchen/glazing 56,802.00 11 Upgrade Gilwern bowling green/pavilion 26,751.00 12 Gilwern Playing Field Improvements 34,391.00 13 Clydach – additional junior playing pitches 53,000.00 14 Incredible Edibles Llanelly Hill food project 1,215.00 15 Llanelly Hill Welfare Hall car park 22,441.00 Unallocated Balance 33,398.00 Total 307,993.00

2.2Grant offers be made to each of the successful applicants subject to the standard terms and conditions of grant set out in APPENDIX A to this report and subject to each applicant providing evidence of their security of tenure for an unexpired period of at least ten years, prior to the payment of any grant monies.

3. KEY ISSUES: 3.1 On 3rd February this year Cabinet considered a report on the Section 106 funding arising from housing developments in Gilwern and Little Mill. At that meeting it was agreed to create the capital budgets necessary to bring all the proposals forward and it was also agreed to allocate grants to specific projects in Little Mill.

3.2At the same meeting, Cabinet also agreed to ask the Section 106 Assessment Panel to reconvene as a matter of urgency to reconsider the proposed grant allocations for Gilwern and to confirm, at a later meeting, whether or not it was still minded to stay with its original recommendations or to amend them.

3.3The panel reconvened on Friday 12th February, a week after the Cabinet meeting, and went through each application again to make sure that the panel was confident about the consistency and clarity of its recommendations. Arising from this process, there were a number of issues that required further information and/or clarification from the applicants, hence the short delay in this report coming back to Cabinet.

3.4On balance, after receiving further clarification from the applicants concerned, the panel is still minded to propose awarding grants towards the twelve projects originally recommended, plus a grant towards the project for installing an updated central heating system in the Gilwern Community Centre. It is clear that this building currently supports a number of recreational activities (something that was not clear from the original application), and the building will also support the use of the adjoining petanque terrain once that project has been completed.

3.5One of the issues that arose at the reconvened panel meeting was the security of tenure held by the various grant applicants – in some cases the applicant is the landowner so in those cases that is not an issue. However, a number of the applications received relate to land in the ownership of a third party and, in those cases, the panel felt it reasonable to ensure that there was a reasonable unexpired term of security of tenure held by the applicants so that the investments made will have a reasonable beneficial period for the local community.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Gilwern S106 fundingReport 126 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

21 of 33 attended
CC
County Councillor Geoff BurrowsCommittee Member, present
CC
County Councillor Peter FoxCommittee Member, present
CC
County Councillor Bob GreenlandCommittee Member, present
CC
County Councillor Liz Hacket PainCommittee Member, present
CC
County Councillor Phyl HobsonCommittee Member, present
CC
County Councillor Bryan JonesCommittee Member, present
CC
County Councillor Phil MurphyCommittee Member, present
CC
County Councillor Dimitri BatrouniCommittee Member, present
CC
County Councillor Tony EassonCommittee Member, present
BB
Bridgit BarnettOfficer, expected
AB
Alan BurkittOfficer, expected
PD
Peter DaviesOfficer, expected

All 33 on the meeting page

On this subject at Monmouthshire

Search all
  1. Gilwern S106 fundingThis decision
  2. Gilwern Section 106 FundingAgreed

More from Monmouthshire Cabinet

All decisions
MeetingDecisionOutcome
11 Nov 2026 Local Growth Fund Year 2 and 3 2027- 2029That the Cabinet considered the draft Local Growth Fund proposals for Years 2 and 3. That Cabinet approves the portfo... Approved Open
11 Nov 2026 Future of Former Tudor Street Day Centre, AbergavennyTo terminate the existing Tenancy at Will agreement with The Gathering Community CIO. To Approve the commencement of ... Agreed Open
11 Nov 2026 Medium Term Financial Plan Update - October 2026That Cabinet notes the refreshed MTFP update at Appendix 1, including the current scenario based planning range for 2... Decided Open
14 Oct 2026 Performance and Overview Scrutiny Committee - Feedback to Cabinet of Meeting held on 29th September 2026Noted. Noted Open
14 Oct 2026 Place Committee - Feedback to Cabinet of Meeting held on 1st October 2026Noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies