SUBJECT: INTERNAL AUDIT SECTION OPERATIONAL PLAN, 2017/18 DRAFT
DIRECTORATE: Chief Executive MEETING: Audit Committee DATE: 16th March 2017 DIVISION/WARDS AFFECTED: All
1. PURPOSE
To receive and consider the early draft Internal Audit Operational Audit Plan for 2017/18.
2. RECOMMENDATION(S)
That the Audit Committee reviews, comments on and shapes the early Draft Audit Plan with a view to receiving a more detailed plan by the end of the 1st quarter for approval.
3. KEY ISSUES
3.1A comprehensive risk matrix was developed for the 2011/12 planning process which gave an outline programme of work that would enable the Internal Audit Section to cover all material audit risks across all services of the Council.
3.2This report explains how the 2017/18 Operational Audit Plan has been prepared and how the plan will be put together in future years. The risk matrix enables all possible systems, processes, sections and establishments that could possibly be audited within Monmouthshire to be risk assessed and ranked in a high to low risk priority. Size, Control and Detection were the overarching categories which risk was assessed against, each broken down to 4 sub categories. Each area was individually scored against each criteria with an overall score being determined by the risk matrix, where 5 was considered to be the highest risk and 1 the lowest.
3.3Over 300 possible areas to audit across all services provided by Monmouthshire were risk assessed in this way and then sorted in risk order from high, then medium and low. The audit team staff resources would then be allocated to cover the higher ranked risks as a priority. That said, inevitably there will be reviews which the audit team have to undertake annually such as performance indicators, annual governance statement, mandatory grant claim audits and audit advice, which have also been incorporated into the plan, along with follow up reviews, finalisation work and planned work from previous year not undertaken. 3.4 An allocation of time will be included in the plan for special investigations where the team might receive allegations of fraud, theft, non compliance. The plan also needs to be flexible enough to respond to changes to risk profiles and other developments in year; the audit management team will continually monitor this situation.
3.5For 2017/18, total available audit resources amounts to 886 days, which will be allocated across service directorates on a risk basis. This includes 116 days for special investigations and unplanned work. The work will be undertaken by 5.4 FTE audit staff. The available resource is based on all staff being in place for the whole of the year.
3.6Although the time allocated to special investigations is usually a pressure point the 2017/18 allocation of days has been maintained to ensure appropriate coverage is given across service areas.
3.7The detail of the plan is still to be finalised following completion of the ongoing consultation exercise with Heads of Service. The first quarter will include finalisation of 2016/17 work which was at draft report stage at year end, work planned for 2016/17 but not completed, corporate performance indicators along with the collation of the Annual Governance Statement.
3.8This plan may change as the year progresses if the risk profile of audit work changes. Any significant change will be brought back to the Audit Committee for approval. The Audit Committee will be kept updated with the progress against the agreed plan via quarterly reports. The intention is to bring an updated plan back to Audit Committee for formal approval by the end of the 1st quarter.
3.9The team comprises of one Audit Manager supported by one Principal Auditor, two Senior Auditors and one Auditor with the Chief Internal Auditor having overall responsibility for the team; he operates on a shared services arrangement with Newport City Council.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Draft Internal Audit Operation Plan 2017 18Appendix 1 | 164 KB | Download |
PDF |
Internal Audit 2017/18 Plan: draftReport | 99 KB | DownloadRead as text |
Follow Governance and Audit Committee at Monmouthshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Nov 2026 | To note the Action List from the previous meeting.Resolved that Action 1 be closed and progress against Action 2 be noted. | Noted | Open |
| 19 Nov 2026 | 26/27 Q2 Treasury reportResolved that the report be noted. Officers to review arrangements for providing members with access to relevant exem... | Noted | Open |
| 19 Nov 2026 | Whole Authority Annual Complaints ReportResolved that the report be noted. | Noted | Open |
| 19 Nov 2026 | The Ombudsmans's Annual LetterResolved that the report be noted. Officers to consider providing further assurance regarding how complaint informati... | Noted | Open |
| 19 Nov 2026 | Annual Audit Plan Welsh Church FundsResolved that the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.