Resolved

That Cabinet agree the rationale for selecting the three schools in the Abergavenny cluster to be the focus for change and development in Band B of the Welsh Government’s 21st Century Schools’ Programme. That Cabinet agree to the Chepstow cluster being redeveloped in Band C of the 21 st Century Schools Programme. That Cabinet agree to the submission of the proposal as set out in Appendix 1 to Welsh Government for consideration in the first stage of the Band B process.
Word for word from the decision Monmouthshire published for this meeting. Source: democracy.monmouthshire.gov.uk

Follow this further

Built from Monmouthshire's papers

What the report saysPro

Report to Cabinet

Recommendations

It is recommended that Cabinet Members:

2.1Agree the rationale for selecting the three schools in the Abergavenny cluster to be the focus for change and development in Band B of the Welsh Government’s 21st Century Schools’ Programme.

2.2Agree to the Chepstow cluster being redeveloped in Band C of the 21 st Century Schools Programme.

2.3Agree to the submission of the proposal as set out in Appendix 1 to Welsh Government for consideration in the first stage of the Band B process.

3. KEY ISSUES

3.1Members will be aware that Band A of our 21st Century Programme is well underway. Caldicot Schools opened in September 2017 and Monmouth Comprehensive School is on schedule to open September 2018. Working with Welsh Government the Local Authority is looking to develop Band B of the programme. The first stage is the review and resubmission of the Strategic Outline Programme. Working within Welsh Government timescales, a draft Strategic Outline Programme has been submitted, and is attached at Appendix 1.

3.2The key factors to be considered are that the proposal seeks to address the condition of our school buildings and sufficiency, ensuring that the schools are of an appropriate size and design to meet the needs of 21st Century learning. The Welsh Government has issued guidance to all local authorities and further education institutions setting out the investment priorities:

Investment Objective One –  To provide efficient and effective educational infrastructure that will meet current and future demand for places by 2024.  Backlog maintenance costs for the schools and colleges selected for Band B are reduced by at least 50% (based on the assumption that approximately 50% of the projects in the Programme will be replacements for existing assets).  No category D buildings in the estate.  C. 25% of Category C condition buildings are improved to Category A or B.  Provide the right number of places for the delivery of: ◦ Welsh medium education; and ◦ English medium education addressing sufficiency issues where relevant.

Investment Objective Two –  Optimise the use of infrastructure and resources, to deliver public services for our communities by 2024. This will include flexibility of our assets so that space and facilities available for our stakeholders are maximised.  Our aspiration is for all facilities that receive investment commit to making assets available for community use if local demand exists.  10% of schools / colleges that receive funding from the Programme have co-located public services on site if local demand exists.

3.3The original Monmouthshire Strategic Outline Programme (2010) held a much wider remit. This included the development of the whole education estate, however as a result of significant cost pressures identified during the development of Band A, a greater focus has been applied to the revised Strategic Outline Programme for Band B. Section 5 of this report considers the extent of the cost pressures in Band A and the impact this has had on the likely development of Band B.

The Needs of Chepstow and Abergavenny

3.4The consideration for the development of Band B has been focused on meeting the needs of the learners in these two areas (equivalent to their primary cluster). There is a specific focus on the secondary estate but the primary settings have also been considered.

3.5Given the known costs of secondary school developments it is the working premise of Monmouthshire’s Band B considerations that only one area of redevelopment would be affordable.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
21st Century Schools Programme: Strategic Outline Programme (SOP) Band B UpdateReport 392 KB DownloadRead as text
PDF
4ca Appendix 1 Monmouthshire Strategic Outline ProgrammeAppendix 387 KB Download
PDF
4cb Appendix 2: 6794065_Chepstow Comprehensive_Report_ISSUEAppendix 2.6 MB Download
PDF
4cc Appendix 3: 6794064_King Henry VIII Comprehensive School_Report_ISSUEAppendix 4.6 MB Download
PDF
4cd Appendix 4: WESPS 2017: Monmouthshire (E)Appendix 301 KB Download
PDF
4ce Appendix 5: Future Generations EvaluationAppendix 362 KB Download

At this meeting

Whole meeting

Who was there

20 of 36 attended
CC
County Councillor Peter FoxCommittee Member, present
CC
County Councillor Bob GreenlandCommittee Member, present
CC
County Councillor Richard JohnCommittee Member, present
CC
County Councillor Bryan JonesCommittee Member, present
CC
County Councillor Penny JonesCommittee Member, present
CC
County Councillor Sara JonesCommittee Member, present
CC
County Councillor Paul JordanCommittee Member, present
CC
County Councillor Phil MurphyCommittee Member, present
BB
Bridgit BarnettOfficer, expected
KB
Kellie BeirneOfficer, present
AB
Alan BurkittOfficer, expected
PD
Peter DaviesOfficer, present

All 36 on the meeting page

On this subject at Monmouthshire

Search all
  1. 21st Century Schools Programme - Strategic Outline Programme (SOP) Band B UpdateThis decision
  2. Monmouthshire county council's 21st century schools programme - outcome of statutory objection period to establish an all-through school (3-19) in abergavennyAgreed
  3. Monmouthshire county council's 21st century schools programme - outcome of statutory consultation to establish an all-through school (4-19) in abergavennyAgreed
  4. 21st century schools -statutory consultation to establish an all-through school (4-19) in abergavennyAgreed

More from Monmouthshire Cabinet

All decisions
MeetingDecisionOutcome
11 Nov 2026 Local Growth Fund Year 2 and 3 2027- 2029That the Cabinet considered the draft Local Growth Fund proposals for Years 2 and 3. That Cabinet approves the portfo... Approved Open
11 Nov 2026 Future of Former Tudor Street Day Centre, AbergavennyTo terminate the existing Tenancy at Will agreement with The Gathering Community CIO. To Approve the commencement of ... Agreed Open
11 Nov 2026 Medium Term Financial Plan Update - October 2026That Cabinet notes the refreshed MTFP update at Appendix 1, including the current scenario based planning range for 2... Decided Open
14 Oct 2026 Performance and Overview Scrutiny Committee - Feedback to Cabinet of Meeting held on 29th September 2026Noted. Noted Open
14 Oct 2026 Place Committee - Feedback to Cabinet of Meeting held on 1st October 2026Noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies