SECTION 106 AGREEMENT : FUNDING OF OPENS SPACE MAINTENANCE AND RELEVANT STRUCTURES
DecidedExecutive1 paper
Individual Cabinet Member Decisions decided this item on Wednesday 28 March 2018. Below is the council's own wording, with the papers it was decided on.
That £35,950 of the Section 106 balance is made available to fund the revenue works described below be made available for the financial year period 2018/19 Total amount of Section 106 Major Maintenance available for the Pen y Val Settlement equates to £134,798.00 of which £35,950 is required to carry out the necessary repairs to the footbridge. That £35,950 of the Section 106 balance is made available to fund the revenue works described below be made available for the financial year period 2018/19 Total amount of Section 106 Major Maintenance available for the Pen y Val Settlement equates to £134,798.00 of which £35,950 is required to carry out the necessary repairs to the footbridge.
Word for word from the decision Monmouthshire published for this meeting.Source: democracy.monmouthshire.gov.uk
2.1That £35,950 of the Section 106 balance is made available to fund the revenue works described below be made available for the financial year period 2018/19
2.2Total amount of Section 106 Major Maintenance available for the Pen y Val Settlement equates to £134,798.00 of which £35,950 is required to carry out the necessary repairs to the footbridge.
3. KEY ISSUES:
The bridge has been in-situ since 2000. Major maintenance works are required in order to bring the structure back in to good repair before the structure is deemed unsafe and unusable. The structure provides an important and safe link between the Pen-y-fal development and Ross Road and Abergavenny town.
The structure serves as a major pedestrian and cycling link for residents and it provides safe access for children that walk or cycle to local schools within Abergavenny.
MCC Structural Engineers have assessed the condition of the structure and have made account of repairs that are required. The anticipated time period required to undertake the required works would be in excess of six weeks. Both local Ward Members have been kept updated in relation to all issues.
4. OPTIONS APPRAISAL
Do Nothing – this is not an option as the structure will deteriorate further and will need to be closed
Replace bridge – a replacement bridge would exceed the allowable Section 106 budget allocation.
5. EVALUATION CRITERIA
Attached
6. REASONS:
Repairs to the bridge provide the most cost effective solution to maintaining this important cycling and pedestrian link.
7. RESOURCE IMPLICATIONS:
MCC Structural Engineers have assessed the condition of the structure and have made account of repairs that are required and have in addition obtained quotations to of which include: 18no hardwood Parapet posts to be replaced 90no hardwood Infill posts to be replaced 38no hardwood infill panels to be replaced All hardwood decking boards to be replaced with a non-slip type for the full span of the bridge.The whole structure is then to have a preservative treatment applied to it. There are no reserve implications arising from this report as the highlighted work costing a total of £35950.00 will be met from funds already received by the Council through s.106 for maintenance of the development and associated infrastructure.
8. WELLBEING OF FUTURE GENERATIONS IMPLICATIONS (INCORPORATING EQUALITIES, SUSTAINABILITY, SAFEGUARDING AND CORPORATE PARENTING):
9. CONSULTEES: Cabinet Members Section 106 Working Group Local Members Leadership Team Highways Structural Engineers
Evaluation Criteria – Cabinet, Individual Cabinet Member Decisions & Council Title of Report: Date decision was made: Report Author:
What will happen as a result of this decision being approved by Cabinet or Council? What is the desired outcome of the decision? Repairs to bridge completed What effect will the decision have on the public/officers? Continue to provide a safe route for pedestrians and cyclist over the River Gavenny at Pen-y-fal
12 month appraisal
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Individual Cabinet Member Decisions at Monmouthshire and we tell you when its next papers are published, before the meeting rather than after it.
Annual health and safety report 2025/26That the Council’s Annual Health and Safety Report 2025/26 is approved, including the health and safety priorities fo...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.