That a capital budget of £35,000 be created in 2018/19 to carry out upgrading and improvement works to play areas in Llanfoist and Abergavenny and that this is funded from a corresponding contribution from the Section 106 balances held by the County Council in respect of the Gavenny Gate development (Finance Code N581).
Word for word from the decision Monmouthshire published for this meeting.Source: democracy.monmouthshire.gov.uk
SUBJECT: SECTION 106 OFFSITE PLAY CONTRIBUTIONS Funding of Play Area Improvement Works MEETING: CABINET DATE TO BE CONSIDERED: 6th JUNE 2018 DIVISION/WARDS AFFECTED: LLANFOIST AND ABERGAVENNY
1. PURPOSE To seek member approval to utilise Section 106 off-site monies allocated for off-site play area improvements in the Abergavenny area. 2. RECOMMENDATION That a capital budget of £35,000 be created in 2018/19 to carry out upgrading and improvement works to play areas in Llanfoist and Abergavenny and that this is funded from a corresponding contribution from the Section 106 balances held by the County Council in respect of the Gavenny Gate development (Finance Code N581). 3. KEY ISSUES 3.1 Following inspections of some of the play areas in the Llanfoist and Abergavenny area, it has been established that a number of these areas are in need of significant improvement and upgrading to ensure that they continue to offer a safe play environment for local children. 3.2 Works are required to the following play areas and approval of the funding is required so that the works can be implemented in the current financial year. School Lane (off Gypsy Lane), Llanfoist Union Road, Abergavenny Bailey Park, Abergavenny
3.3If works to the above sites are not addressed quickly then the condition of the play equipment and the general safety environment will get worse and will involve greater expense to the Authority in the longer term. 3.4 With regard to safety surfacing on play areas, artificial turf is now the standard surfacing material used by the Council at its sites. This is also now specified as the standard for developers when they provide play areas as part of new housing developments in the county. 3.4 Many of the older play areas in the county were developed with the use of wet pour (rubberised tarmac) surfacing, which at the time was considered to be acceptable. However, experience over the years has shown that wet pour safety surfacing is adversely affected by weather, is more susceptible to vandalism and it deteriorates more quickly than artificial turf so this creates trip points and an uneven surface. 3.5 In terms of funding, the Council has received an off-site play contribution of £35,000 from the Gavenny Gate development and it is proposed to utilise this funding to carry out the works to the play areas concerned.
4. OPTIONS APPRAISAL Unless these play areas are improved and maintained to an acceptable standard, then their condition will deteriorate and there is no alternative funding available in existing budgets to carry out works of this nature.
5. EVALUATION CRITERIA Please see evaluation criteria set out in Appendix A. . 6. REASONS To ensure that the play areas in question are improved and then maintained to a good standard by utilising some contributions received by the Council from developers via this Section 106 Agreement. This will provide much needed play participation opportunities for local young children.
7. RESOURCE IMPLICATIONS The S106 capital funding identified in this report has been received to improve play facilities in the local area, so the works proposed will not impact on existing capital or revenue budgets.
8. WELL BEING OF FUTURE GENERATIONS IMPLICATIONS (INCORPORATING EQUALITIES, SUSTAINABILITY, SAFEGUARDING & CORPORATE PARENTING) See attached at Appendix D
9. CONSULTEES Cabinet Members Section 106 Working Group Local Members Leadership Team 10. BACKGROUND PAPERS: Section 106 Agreement with Johnsey Estates dated 23rd May 2013 Deed of Variation with Barratt Homes dated 28th March 2014
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.