RE:FIT PROGRAMME - UTILISATION OF LOCAL PARTNERSHIPS ENERGY FRAMEWORK
ApprovedExecutive1 paper
Individual Cabinet Member Decisions approved this item on Wednesday 13 June 2018. Below is the council's own wording, with the papers it was decided on.
To seek approval to enter into the Local Partnerships Access Arrangements To seek approval to enter into the Refit Cymru Client Support Agreement To delegate decision making and the management of this programme to the Chief Officer, Resources in consultation with the Cabinet Member Resources.
Word for word from the decision Monmouthshire published for this meeting.Source: democracy.monmouthshire.gov.uk
2.1To seek approval to enter into the Local Partnerships Access Arrangements 2.2 To seek approval to enter into the Refit Cymru Client Support Agreement 2.3 To delegate decision making and the management of this programme to the Chief Officer, Resources in consultation with the Cabinet Member Resources.
3. KEY ISSUES:
3.1Re:fit is a procurement project that is designed to support public bodies procuring energy efficiency and generation measures, to reduce energy costs and resulting carbon footprint.
3.2The concept is built around a procurement framework developed by the Greater London Authority in 2009 and works on the principle of loan funding for capital works which are paid back through guaranteed energy savings or generation over and agreed period of time.
3.3The Re:fit Cymru Programme Implementation Unit (PIU) support public sector organisations in Wales through the Re:fit process, from initial benchmarking to determine viability, through engagement, contract and tender preparation, through to project delivery and monitoring.
3.4Officers have been working with Local Partnerships to determine the viability of the proposition, opportunities and resources prior to implementing this approach. They have undertaken a benchmarking exercise which suggests that there is a potential aggregate value in excess of £1,000,000 with the cost of these works being met from resulting savings anticipated to be circa £150,000 (gross). The actual borrowing costs are yet to be determined.
3.5Should approval be granted to proceed with the scheme, Local Partnerships would work with Officers to develop a tender, undertake a mini-competition and award the works. The management of the resulting contract will be the responsibility of the Council. Local Partnerships require a £10,000 contribution to cover the costs incurred in supporting the Council and this will rise to £20,000 should the Council choose to withdraw from the scheme following the tender process. This however is not payable in advance and can be included within the capital scheme costs if we proceed. It will also place an additional burden on staff resources and it is anticipated that short term support will be needed for the initial phases.
3.6Funding for the capital works will be determined when the viability of the schemes have been determined, however it is anticipated that it will be a blend of loan and capital programme funding. Loan funding is available from Welsh Government with schemes such as Salix and the capital programme funding will be from the property maintenance capital programme or form part of any refurbishment programmes where appropriate. Where funding is outside the approved capital programme, separate approval will be sought through the normal member approval process.
3.7Work to date has focussed on the implementation of improvements to the energy infrastructure within Council owned properties, however the scheme also deals with energy generation via renewable technologies. This is an area that merits further work given the successful delivery of the solar farm at Oak Grove farm and will form phase 2 of this programme.
3.8The Chief Officer, Resources will have delegated authority to approve the award of contracts for both energy reduction and regeneration contracts, in consultation with the Resources Cabinet Member.
4 OPTIONS APPRAISAL
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Individual Cabinet Member Decisions at Monmouthshire and we tell you when its next papers are published, before the meeting rather than after it.
Annual health and safety report 2025/26That the Council’s Annual Health and Safety Report 2025/26 is approved, including the health and safety priorities fo...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.