DIGITAL INFRASTRUCTURE ACTION PLAN UPDATE

Approved Executive 2 papers

Cabinet approved this item on Wednesday 29 July 2020. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

Cabinet to receive the update and acknowledge the significant activity and progress that has been made in less than a year and to support the future plans for the deployment of broadband infrastructure across the County, to reduce the deficiencies in digital infrastructure that are seen across the County. Cabinet to approve Officers engagement in further dialogue with Welsh Government, to optimise the additional investment, in order to maximise the spread of connectivity across the County and alongside other digital infrastructure investment as outlined in the report.
Word for word from the decision Monmouthshire published for this meeting. Source: democracy.monmouthshire.gov.uk

Follow this further

Built from Monmouthshire's papers

What the report saysPro

Report to Cabinet

SUBJECT: DIGITAL INFRASTRUCTURE ACTION PLAN UPDATE MEETING: CABINET

DATE: 29TH JULY 2020 DIVISION/WARDS AFFECTED: ALL

1. PURPOSE: To provide an update on activity following approval of the Digital Infrastructure Action Plan (Appendix A) in September 2019. 2. RECOMMENDATIONS: 2.1 Cabinet to receive the update and acknowledge the significant activity and progress that has been made in less than a year and to support the future plans for the deployment of broadband infrastructure across the County, to reduce the deficiencies in digital infrastructure that are seen across the County. 2.2 Following the very recent announcement by Welsh Government of additional funding for Openreach via the Superfast programme. Cabinet to approve Officers engagement in further dialogue with Welsh Government, to optimise the additional investment, in order to maximise the spread of connectivity across the County and alongside other digital infrastructure investment as outlined in the report. 3. KEY ISSUES: 3.1 In September 2019 Cabinet approved the Digital Infrastructure Action Plan setting out how the Council wished to capitalise on the provision of a high speed, first class digital infrastructure, in order to deliver economic growth, wealth creation and increased productivity and GVA for the county and the country. 3.2 Less than 12 months later, the need for a robust digital infrastructure has become even more pronounced. As a result of the COVID-19 pandemic, the increase and impact of on-line, digital activity has been phenomenal from a wider societal and economic perspective, with the unprecedented increase in home working, acceleration of people doing on line shopping and wider digital social interactions with families and friends. All this has led to the amplified need for good quality digital infrastructure and connectivity, particularly for the Council, with many of the Council’s services moving to an on-line digital platform. 3.3 It is therefore pleasing to be in a position to report that although the digital deprivation rates remain the highest in the Cardiff Capital Region 12.5% (approximately 8,000 premises) in Monmouthshire, in comparison to 3-4% in other CCR local authority areas, things are set to change. 3.4 This report seeks to highlight the scale of planned investment in broadband connectivity in the County and the activity that is set to take place over the coming months by commercial Altnets (Altnets are Network Service Providers other than BT). In addition, on the 20th July, Welsh Government announced that they had increased their agreement with Openreach, to increase the number of properties that will benefit through the project from 26,000 to 39,000 in local authority areas with less than 90% superfast broadband coverage. Officers will analyse the list of additional properties that will benefit from this coverage and seek to engage with Welsh Government, to ensure investment is made in the right postcodes in order to maximise broadband connectivity in the County.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
5a. Appendix A Digital Infrastructure Action Plan Updated 200710Appendix 1.3 MB Download
PDF
DIGITAL INFRASTRUCTURE ACTION PLAN UPDATEReport 639 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

20 of 31 attended
RM
Robert McGowanCouncil Staff, expected
MP
Matt PhillipsOfficer, present
CC
County Councillor Peter FoxCommittee Member, present
CC
County Councillor Bob GreenlandCommittee Member, present
CC
County Councillor Richard JohnCommittee Member, present
CC
County Councillor Penny JonesCommittee Member, present
CC
County Councillor Sara JonesCommittee Member, present
CC
County Councillor Paul JordanCommittee Member, present
CC
County Councillor Phil MurphyCommittee Member, present
AB
Alan BurkittOfficer, expected
PD
Peter DaviesOfficer, present
TH
Tracey HarryOfficer, expected

All 31 on the meeting page

On this subject at Monmouthshire

Search all
  1. DIGITAL INFRASTRUCTURE ACTION PLAN UPDATEThis decision
  2. Digital Infrastructure Loan - Verbal UpdateAgreed
  3. Digital infrastructure proposal - commercial loanDeferred
  4. Digital infrastructure action planApproved

More from Monmouthshire Cabinet

All decisions
MeetingDecisionOutcome
11 Nov 2026 Local Growth Fund Year 2 and 3 2027- 2029That the Cabinet considered the draft Local Growth Fund proposals for Years 2 and 3. That Cabinet approves the portfo... Approved Open
11 Nov 2026 Future of Former Tudor Street Day Centre, AbergavennyTo terminate the existing Tenancy at Will agreement with The Gathering Community CIO. To Approve the commencement of ... Agreed Open
11 Nov 2026 Medium Term Financial Plan Update - October 2026That Cabinet notes the refreshed MTFP update at Appendix 1, including the current scenario based planning range for 2... Decided Open
14 Oct 2026 Performance and Overview Scrutiny Committee - Feedback to Cabinet of Meeting held on 29th September 2026Noted. Noted Open
14 Oct 2026 Place Committee - Feedback to Cabinet of Meeting held on 1st October 2026Noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies