Resolved
That Cabinet members approve the strategic risk assessment shown at appendix 2 as a realistic and evidenced appraisal of the strategic risks facing the authority over the next three years.
Cabinet approved this item on Wednesday 14 April 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
That Cabinet members approve the strategic risk assessment shown at appendix 2 as a realistic and evidenced appraisal of the strategic risks facing the authority over the next three years.
2.1That Cabinet members approve the strategic risk assessment shown at appendix 2 as a realistic and evidenced appraisal of the strategic risks facing the authority over the next three years.
3. KEY ISSUES:
3.1The strategic risk assessment ensures that: • Strategic risks are identified and monitored by the authority • Risk controls are appropriate and proportionate • Senior managers and elected members systematically review the strategic risks facing the authority
3.2The strategic risk assessment is updated based on the latest evidence available in line with the Council’s strategic risk management policy; a summary is provided in appendix 3. The risk assessment has continued to be updated with the council’s ongoing activity during the Coronavirus pandemic. Through the pandemic, the council continues to operate in a dynamic environment. Controls are in place to manage and mitigate, as far as possible, a variety of risks to service delivery and to the well-being of our staff and residents, of which the strategic risk assessment is one important mechanism.
3.3Due to its purpose, the strategic risk assessment is a detailed document; appendix 1 provides Cabinet with an overview of the strategic risks on the register. Appendix 2 provides the full strategic risk assessment. There have been a number of amendments to ensure it accurately manages the current strategic risks facing the Council, including the removal of two risks. Where a risk has been removed and there remains a level of risk, these risks will continue to be monitored and action undertaken through the relevant service plan.
3.4Updates have been made, where required, to the existing risks, including to the reason why the risk has been identified, the assessed risk level, mitigating actions being undertaken and the progress on these. Some of the more significant recent changes are:
• Updates on financial risks, in relation to the budget for 2021/22, the MTFP, funding associated with the pandemic, and the potential impact on services into the future • Updates on the risk to service delivery and safeguarding arrangements for vulnerable children and adults during the pandemic • The latest on education related risks in light of changes and risks associated with the pandemic • Updated assessment of risk as a result of the United Kingdom leaving the European Union • The latest updates on the risks and mitigations related to COVID-19, which forms part of many risks, in line with changing government guidelines, legislation, local circumstances and evidence-bases • Removal of the risk of declining recycling rates affecting our ability to achieve the Welsh Government target of 70% recycling rates throughout Wales. This risk still needs to be managed at a service level. • Removal of the risk that the authority cannot deliver its services due to potential internal/external factors resulting in service disruption due to lack of Business Continuity planning 1 3.5 The risk assessment only covers high and medium level strategic risks. Lower level, or operational risks, are not registered unless they are projected to escalate within the three years covered. These are managed and monitored through other arrangements, including through team service plans. The strategic risk assessment should continue to focus on medium term risks to service delivery.
3.6The strategic risk assessment was presented to Audit Committee in March 2021 to fulfil its role in providing assurance of the adequacy of the Council’s risk management framework.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
WHOLE AUTHORITY STRATEGIC RISK ASSESSMENTReport | 1.2 MB | DownloadRead as text |
Follow Cabinet at Monmouthshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Nov 2026 | Local Growth Fund Year 2 and 3 2027- 2029That the Cabinet considered the draft Local Growth Fund proposals for Years 2 and 3. That Cabinet approves the portfo... | Approved | Open |
| 11 Nov 2026 | Future of Former Tudor Street Day Centre, AbergavennyTo terminate the existing Tenancy at Will agreement with The Gathering Community CIO. To Approve the commencement of ... | Agreed | Open |
| 11 Nov 2026 | Medium Term Financial Plan Update - October 2026That Cabinet notes the refreshed MTFP update at Appendix 1, including the current scenario based planning range for 2... | Decided | Open |
| 14 Oct 2026 | Performance and Overview Scrutiny Committee - Feedback to Cabinet of Meeting held on 29th September 2026Noted. | Noted | Open |
| 14 Oct 2026 | Place Committee - Feedback to Cabinet of Meeting held on 1st October 2026Noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.