That a capital budget of £492,000 be created in the 2021/22 financial year to fund the construction of the first phase of the Abergavenny velo park and that this is funded by: a) Contributions from balances held by the council from the S106 Agreements relating to the Westgate (£168,160 – Finance Code N560) and Gavenny Gate (£231,840 – Finance Code N581) developments in Llanfoist. b) A further S106 contribution of £92,000 be added to the above budget, when received, from the residential development site at Grove Farm, Llanfoist. That the Council continues to work with other partner agencies to support a community group to form and subsequently source and apply for further capital funding from external sources that contribute to the development costs of the second and third phases of the Abergavenny Velo Park project. That commitment of any expenditure from the above sums is subject to the submission and approval of a satisfactory management agreement with a supporting business plan for the proposed new velo park; such approval being delegated to the Cabinet Member for Resources, in consultation with the council’s S151 Officer.
Word for word from the decision Monmouthshire published for this meeting.Source: democracy.monmouthshire.gov.uk
2.1That a capital budget of £492,000 be created in the 2021/22 financial year to fund the construction of the first phase of the Abergavenny velo park and that this is funded by:
a) Contributions from balances held by the council from the S106 Agreements relating to the Westgate (£168,160 – Finance Code N560) and Gavenny Gate (£231,840 – Finance Code N581) developments in Llanfoist.
b) A further S106 contribution of £92,000 be added to the above budget, when received, from the residential development site at Grove Farm, Llanfoist.
2.2That the Council continues to work with other partner agencies to support a community group to form and subsequently source and apply for further capital funding from external sources that contribute to the development costs of the second and third phases of the Abergavenny Velo Park project.
2.3That commitment of any expenditure from the above sums is subject to the submission and approval of a satisfactory management agreement with a supporting business plan for the proposed new velo park; such approval being delegated to the Cabinet Member for Resources, in consultation with the council’s S151 Officer.
3. KEY ISSUES
3.1In 2020 the council was awarded a grant from the Welsh Government, via Sport Wales, to develop a project for the construction of a velo park (to include a purpose-built closed road circuit (CRC) and some recreational trails) on part of the council’s landholding at Racecourse Farm, Llanfoist. A copy of the site masterplan is attached at APPENDIX A.
3.2The project has been developed in consultation with a number of stakeholders including Sport Wales, British Cycling, the national governing body and two local cycling clubs. The provision of a velo park in this location is a key component of the council’s emerging cycling strategy and is intended to form part of a network of regional facilities promoted by Welsh Cycling, the governing body of the sport in Wales.
3.3This has been a complex project to develop, mainly because of the site’s topography, biodiversity and ecology, with a number of protected species identified on or immediately adjacent to the site. The land is also currently occupied under a farm business tenancy. The tenancy is holding over, pending a decision on whether or not to proceed with the velo park project.
3.4A formal planning application was made in early 2021, with 34 documents submitted in support, including a Site User and draft Management Plan with an outline programme of use. These documents and the site masterplan have been updated as part of the planning proposals in the light of comments received from consultees, in particular the detailed comments submitted by Natural Resources Wales (NRW).
3.5The velo park planning application is included on the agenda for the Planning Committee meeting on 1st March, with a recommendation for approval.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.