Monmouthshire County Council
Cabinet, Wednesday 2 March 2022 at 3.00pm

ABERGAVENNY VELO PARK

Agreed Executive 1 paper

Cabinet agreed this item on Wednesday 2 March 2022. Below is the council's own wording, with the papers it was decided on.

Item3k

Resolved

That a capital budget of £492,000 be created in the 2021/22 financial year to fund the construction of the first phase of the Abergavenny velo park and that this is funded by: a) Contributions from balances held by the council from the S106 Agreements relating to the Westgate (£168,160 – Finance Code N560) and Gavenny Gate (£231,840 – Finance Code N581) developments in Llanfoist. b) A further S106 contribution of £92,000 be added to the above budget, when received, from the residential development site at Grove Farm, Llanfoist. That the Council continues to work with other partner agencies to support a community group to form and subsequently source and apply for further capital funding from external sources that contribute to the development costs of the second and third phases of the Abergavenny Velo Park project. That commitment of any expenditure from the above sums is subject to the submission and approval of a satisfactory management agreement with a supporting business plan for the proposed new velo park; such approval being delegated to the Cabinet Member for Resources, in consultation with the council’s S151 Officer.
Word for word from the decision Monmouthshire published for this meeting. Source: democracy.monmouthshire.gov.uk

Follow this further

Built from Monmouthshire's papers

What the report saysPro

Report to Cabinet

Recommendations

2.1That a capital budget of £492,000 be created in the 2021/22 financial year to fund the construction of the first phase of the Abergavenny velo park and that this is funded by:

a) Contributions from balances held by the council from the S106 Agreements relating to the Westgate (£168,160 – Finance Code N560) and Gavenny Gate (£231,840 – Finance Code N581) developments in Llanfoist.

b) A further S106 contribution of £92,000 be added to the above budget, when received, from the residential development site at Grove Farm, Llanfoist.

2.2That the Council continues to work with other partner agencies to support a community group to form and subsequently source and apply for further capital funding from external sources that contribute to the development costs of the second and third phases of the Abergavenny Velo Park project.

2.3That commitment of any expenditure from the above sums is subject to the submission and approval of a satisfactory management agreement with a supporting business plan for the proposed new velo park; such approval being delegated to the Cabinet Member for Resources, in consultation with the council’s S151 Officer.

3. KEY ISSUES

3.1In 2020 the council was awarded a grant from the Welsh Government, via Sport Wales, to develop a project for the construction of a velo park (to include a purpose-built closed road circuit (CRC) and some recreational trails) on part of the council’s landholding at Racecourse Farm, Llanfoist. A copy of the site masterplan is attached at APPENDIX A.

3.2The project has been developed in consultation with a number of stakeholders including Sport Wales, British Cycling, the national governing body and two local cycling clubs. The provision of a velo park in this location is a key component of the council’s emerging cycling strategy and is intended to form part of a network of regional facilities promoted by Welsh Cycling, the governing body of the sport in Wales.

3.3This has been a complex project to develop, mainly because of the site’s topography, biodiversity and ecology, with a number of protected species identified on or immediately adjacent to the site. The land is also currently occupied under a farm business tenancy. The tenancy is holding over, pending a decision on whether or not to proceed with the velo park project.

3.4A formal planning application was made in early 2021, with 34 documents submitted in support, including a Site User and draft Management Plan with an outline programme of use. These documents and the site masterplan have been updated as part of the planning proposals in the light of comments received from consultees, in particular the detailed comments submitted by Natural Resources Wales (NRW).

3.5The velo park planning application is included on the agenda for the Planning Committee meeting on 1st March, with a recommendation for approval.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
ABERGAVENNY VELO PARKReport 1 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

28 of 50 attended
CC
County Councillor Richard JohnCommittee Member, present
CC
County Councillor Robert GreenlandCommittee Member, apologies
CC
County Councillor Phil MurphyCommittee Member, present
CC
County Councillor Penny JonesCommittee Member, present
CC
County Councillor Sara JonesCommittee Member, present
CC
County Councillor Jane PrattCommittee Member, present
CC
County Councillor Paul PaviaCommittee Member, present
CC
County Councillor Lisa DymockCommittee Member, present
CC
County Councillor Jo WatkinsCo-Optee, present
CC
County Councillor Simon HowarthCo-Optee, present
PM
Paul MatthewsOfficer, present
PD
Peter DaviesOfficer, present

All 50 on the meeting page

More from Monmouthshire Cabinet

All decisions
MeetingDecisionOutcome
11 Nov 2026 Local Growth Fund Year 2 and 3 2027- 2029That the Cabinet considered the draft Local Growth Fund proposals for Years 2 and 3. That Cabinet approves the portfo... Approved Open
11 Nov 2026 Future of Former Tudor Street Day Centre, AbergavennyTo terminate the existing Tenancy at Will agreement with The Gathering Community CIO. To Approve the commencement of ... Agreed Open
11 Nov 2026 Medium Term Financial Plan Update - October 2026That Cabinet notes the refreshed MTFP update at Appendix 1, including the current scenario based planning range for 2... Decided Open
14 Oct 2026 Performance and Overview Scrutiny Committee - Feedback to Cabinet of Meeting held on 29th September 2026Noted. Noted Open
14 Oct 2026 Place Committee - Feedback to Cabinet of Meeting held on 1st October 2026Noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies