That Cabinet agrees to the co-production of ‘Placemaking Plans’ for Monmouth, Magor and Abergavenny with the respective Town Councils. These documents will provide an overarching masterplan for each of the towns to support future grant funding bids. That Cabinet agrees the proposed indicative package of smaller Placemaking Grant projects (Appendix 2) for delivery in 2022/23 to 2024/25, and authorises the Chief Officer for Communities and Place to make adjustments to that package of projects as needed, in liaison with the Cabinet Member for Sustainable Economy, Deputy Leader . That Cabinet notes the schedule of potential Strategic Projects and the scale of funding required for delivery, and agrees to defer making a decision on strategic projects until the Autumn 2022, allowing for alignment with the emerging new Corporate Plan and in formed by the decision on our bids for Levelling Up Funds from the UK Government.
Word for word from the decision Monmouthshire published for this meeting.Source: democracy.monmouthshire.gov.uk
1. PURPOSE: 1.1 The Council’s ambition for regeneration activity, and the ambition of the communities it represents, far outstrips the resources and funding available to deliver everything, and therefore decisions on priorities and sequencing are required. The purpose of the report is to invite Cabinet to agree the indicative package of Placemaking Grant projects (which will form the bid for Welsh Government Transforming Towns grant for the next three years) and to agree to develop ‘Placemaking Plans’ for Monmouth, Magor and Abergavenny. It is proposed that a decision on strategic projects is deferred until the Autumn of 2022, by which time the Council should have received a decision on its bids for Levelling Up Funds.
2 RECOMMENDATIONS: 2.1 That Cabinet agrees to the co-production of ‘Placemaking Plans’ for Monmouth, Magor and Abergavenny with the respective Town Councils. These documents will provide an overarching masterplan for each of the towns to support future grant funding bids.
2.2That Cabinet agrees the proposed indicative package of smaller Placemaking Grant projects (Appendix 2) for delivery in 2022/23 to 2024/25, and authorises the Chief Officer for Communities and Place to make adjustments to that package of projects as needed, in liaison with the Cabinet Member for Economy and Sustainable Livelihoods.
2.3That Cabinet notes the schedule of potential Strategic Projects and the scale of funding required for delivery, and agrees to defer making a decision on strategic projects until the Autumn 2022, allowing for alignment with the emerging new Corporate Plan and informed by the decision on our bids for Levelling Up Funds from the UK Government.
3 KEY ISSUES: 3.1 Strategic context 3.1.1 Within the current Corporate Plan, the need to support local economies is highlighted as a priorities:
‘THE COUNCIL PROVIDES MORE OPPORTUNITIES FOR LOCAL LIVING, WORKING & LEISURE Engage with communities to create plans for the redevelopment of Usk and Caldicot town centres and begin discussions on plans for Monmouth and Chepstow’ 3.1.2 The new administration has embarked on a review of the Corporate Plan but it is anticipated that regeneration will remain a priority into the future (‘promoting town centres’ being identified as a manifesto priority).
3.1.3 Appendix 3 sets out a range of existing and proposed regeneration-related projects that report into the Communities and Place Project Board. This list has been informed by existing masterplans and strategies. It does not assess priorities, but illustrates the volume of projects to be funded and progressed going forward. As further town masterplans are prepared and other projects completed, the list will change.
3.1.4 The previous Cabinet considered a report in September 2021 and agreed funding priorities for 21/22 and an indicative programme for 22/23. This report seeks to build on that in the light of the new three-year funding arrangements.
3.2Placemaking Plans 3.2.1 Several towns in the county already benefit from local strategic documents (master plans, town plans etc.) that assess the key opportunities and challenges for that settlement, set high level objectives for regeneration, and set out the key projects through which those objectives can be met. The existing plans include:
• The Caldicot Town Centre Regeneration Strategy originally developed in 2018. A refresh of the strategy reflecting delivery since 2018 has been prepared to support the Round 2 Levelling Up Fund bid.
• The Usk Town Improvement Plan was jointly developed by MCC, Usk Town Council and Llanbadoc Community Council. It has been adopted by each body, being adopted by the County Council in December 2021. A Masterplan steering group has been established to oversee its delivery.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.