REVENUE & CAPITAL BUDGET MONITORING 2022/23 - MONTH 9 FORECAST

Noted Executive 5 papers

Cabinet noted this item on Wednesday 1 March 2023. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

That Cabinet recognises a net improvement of £1.62m since the previous revenue budget forecast that results in a forecast over spend at month 9 of £7.53m. That Cabinet note that this is driven primarily by incorporating the budget recovery plan into forecasts at month 9, along with substantial unbudgeted grant funding notified in respect of Children’s services that is significantly offset by further costs within the service. That Cabinet note that the overall revenue budget outturn as currently forecast would need to be subsidised by £3.4m of capital receipts which are being used to fund identified eligible expenditure under the flexible use of capital receipts directive. That Cabinet notes the update to the budget recovery plan as outlined in table 3. This projects that a draw on revenue reserves of £6.06m will now be required to ensure a balanced outturn position is achieved; representing an increase of £1.06m in the contribution anticipated to support the budget recovery plan from month 6. That Cabinet recognise: · the implication of drawing on the level of useable revenue reserves to this degree in 2022/23, · the usage also being proposed to assist the 2023/24 budget, · the trend of budgetary over-spends in high cost service areas, and wider economic uncertainty. That Cabinet note the financial risk represented by the current volatile environment in Adult’s and Children’s services and require the respective Chief Officers and the Responsible Financial Officer to continue to closely monitor and manage operational and financial performance to ensure that all possible remedial action is taken to constrain cost and that this is reported to the Cabinet Portfolio Holder regularly That Cabinet require the Responsible Financial Officer to make consideration of strengthening the reporting of budget forecasts and savings progress during 2023/24. Cabinet considers the forecast capital outturn spend of £61.8m as outlined in appendix 1 that currently indicates a forecast over spend of £183k, noting the continuing difficulty in delivering capital projects to their allocated budget in the current challenging economic environment. That Cabinet note the forecast 100% delivery of the budgeted mandated savings as detailed in appendix 2 and as approved as part of the budget set by full Council. Cabinet notes the extent of forecast movements in Schools reserve usage contained in table 6, and appendices 1 & 3 which highlight the possibility of a further nine schools entering a deficit reserve position by the end of the financial year.
Word for word from the decision Monmouthshire published for this meeting. Source: democracy.monmouthshire.gov.uk

Follow this further

Built from Monmouthshire's papers

What the report saysPro

Report to Cabinet

Recommendations

2.1That Cabinet recognises a net improvement of £1.62m since the previous revenue budget forecast that results in a forecast over spend at month 9 of £7.53m.

2.2That Cabinet note that this is driven primarily by incorporating the budget recovery plan into forecasts at month 9, along with substantial unbudgeted grant funding notified in respect of Children’s services that is significantly offset by further costs within the service.

2.3That Cabinet note that the overall revenue budget outturn as currently forecast would need to be subsidised by £3.4m of capital receipts which are being used to fund identified eligible expenditure under the flexible use of capital receipts directive.

2.4That Cabinet notes the update to the budget recovery plan as outlined in table 3. This projects that a draw on revenue reserves of £6.06m will now be required to ensure a balanced outturn position is achieved; representing an increase of £1.06m in the contribution anticipated to support the budget recovery plan from month 6.

2.5That Cabinet recognise:  the implication of drawing on the level of useable revenue reserves to this degree in 2022/23,  the usage also being proposed to assist the 2023/24 budget,  the trend of budgetary over spends in high cost service areas, and wider economic uncertainty.

2.6That Cabinet note the financial risk represented by the current volatile environment in Adult’s and Children’s services and require the respective Chief Officers and the Responsible Financial Officer to continue to closely monitor and manage operational and financial performance to ensure that all possible remedial action is taken to constrain cost and that this is reported to the Cabinet Portfolio Holder regularly. 2.7. That Cabinet require the Responsible Financial Officer to make consideration of strengthening the reporting of budget forecasts and savings progress during 2023/24.

2.8Cabinet considers the forecast capital outturn spend of £61.8m as outlined in appendix 1 that currently indicates a forecast over spend of £183k, noting the continuing difficulty in delivering capital projects to their allocated budget in the current challenging economic environment.

2.9That Cabinet note the forecast 100% delivery of the budgeted mandated savings as detailed in appendix 2 and as approved as part of the budget set by full Council.

2.10Cabinet notes the extent of forecast movements in Schools reserve usage contained in table 6, and appendices 1 & 3 which highlight the possibility of a further nine schools entering a deficit reserve position by the end of the financial year.

3. KEY ISSUES:

Context

3.1In setting the 2022/23 budget there was an expectation that the Council would see a gradual return to a more stable operating environment relative to the last two years, with the direct impacts of the pandemic potentially set to ease.

3.2There was a known and accepted risk that the Welsh Government Hardship fund would end and that the challenges experienced in achieving historic income levels would continue, and that the permanent change in national policy initiative around the needs of the homeless would not be adequately funded by Welsh Government.

3.3The budget round therefore saw £10.1m of budget pressures accommodated, notably around the expected levels of pay; Additional learning needs demands; increasing demand and complexity of Children’s care cases; increasing demands upon adult social services and; significant service pressures within the passenger transport unit and within recycling and waste.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
1a. 20230301 Cabinet: Revenue Capital budget forecast month 9: Appendix 1: Detailed outturn forecastsAppendix 880 KB Download
PDF
1b. 20230301 Cabinet: Revenue Capital budget forecast Month 9: Appendix 2: Progress against mandated savingsAppendix 146 KB Download
PDF
1c. 20230301 Cabinet: Revenue Capital budget forecast month 9: Appendix 3: Forecast school balancesAppendix 42 KB Download
PDF
1d. 20230301 Cabinet: Revenue Capital budget forecast month 9: Appendix 4: Progress against budget recoveryAppendix 278 KB Download
PDF
REVENUE & CAPITAL BUDGET MONITORING 2022/23: MONTH 9 FORECASTReport 840 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

19 of 32 attended
JD
Jonathan DaviesOfficer, present
CC
County Councillor Mary Ann BrocklesbyCommittee Member, present
CC
County Councillor Sara BurchCommittee Member, present
CC
County Councillor Catherine FookesCommittee Member, present
CC
County Councillor Rachel Catherine GarrickCommittee Member, present
CC
County Councillor Paul GriffithsCommittee Member, present
CC
County Councillor Martyn GroucuttCommittee Member, present
CC
County Councillor Catrin MabyCommittee Member, present
CC
County Councillor Tudor ThomasCommittee Member, present
RM
Robert McGowanOfficer, expected
MP
Matt PhillipsOfficer, present
PD
Peter DaviesOfficer, present

All 32 on the meeting page

On this subject at Monmouthshire

Search all
  1. REVENUE & CAPITAL BUDGET MONITORING 2022/23 - MONTH 9 FORECASTThis decision
  2. Revenue and capital budget 2026/27 - final proposals following scrutiny and public consultationApproved
  3. Draft revenue and capital budget proposals 2026/27Approved
  4. Final revenue and capital budget proposals 2025/26Approved
  5. 2023/24 revenue & capital budget - month 9 updateNoted
  6. REVENUE AND CAPITAL BUDGET 2024/25 - Final proposals following scrutiny and public consultationApproved

More from Monmouthshire Cabinet

All decisions
MeetingDecisionOutcome
11 Nov 2026 Local Growth Fund Year 2 and 3 2027- 2029That the Cabinet considered the draft Local Growth Fund proposals for Years 2 and 3. That Cabinet approves the portfo... Approved Open
11 Nov 2026 Future of Former Tudor Street Day Centre, AbergavennyTo terminate the existing Tenancy at Will agreement with The Gathering Community CIO. To Approve the commencement of ... Agreed Open
11 Nov 2026 Medium Term Financial Plan Update - October 2026That Cabinet notes the refreshed MTFP update at Appendix 1, including the current scenario based planning range for 2... Decided Open
14 Oct 2026 Performance and Overview Scrutiny Committee - Feedback to Cabinet of Meeting held on 29th September 2026Noted. Noted Open