S106 CHURCH ROAD AND CRICK ROAD ALLOCATION OF S106 OFFSITE RECREATION FUNDING

Approved Executive 6 papers

AI summaryMonmouthshire Cabinet approves allocating £144,000 from the Church Road S106 and £167,000 from the Crick Road S106 to the Caldicot Greenway/Multi-User Route, closing most of the £310,000 funding gap for the £650,000 scheme.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedS106 recreation funds allocated to Caldicot Greenway/MUR project
Money£311,000 total£144,000 from Church Road, £167,000 from Crick Road
What happens nextNot stated
Who it affectsCaldicot, Portskewett, Severnside wardsResidents and visitors to the greenway route

What was decided

Cabinet approved allocating £144,000 from the Church Road S106 offsite recreation contribution to the Caldicot Greenway/MUR project. Report 2.1

Cabinet approved allocating £167,000 from the Crick Road S106 offsite recreation contribution to the Caldicot Greenway/MUR project, subject to receipt of funds. Report 2.2

Why

The Caldicot Greenway/MUR is named as a beneficiary in both the Church Road and Crick Road S106 agreements, so allocating to it complies with the legal terms. Report 3.1, 3.10, P10

Public consultation in August and September 2025 reached over 460 residents and businesses, with 65% supporting the project and 12% opposed. Report 3.5, P38, P39

Allocating the funds safeguards £190,000 of Active Travel core funding and £150,000 of Shared Prosperity Fund grants, both of which must be spent soon, and supports the council's Green Infrastructure Strategy and 20-minute neighbourhood ambition. Report 3.4, 3.9, 3.10

What happens next

Discussions with local Severnside members will continue to determine how the remaining £233,000 of Crick Road S106 funds is allocated, with possible options including Caldicot Town Centre regeneration, the Cornfield Project, skate park improvements, and Portskewett and Sudbrook Recreation Hall toilet block redevelopment. Report 3.11, 8.2

Monitoring, evaluation and a project programme for construction and delivery will be provided as part of grant requirements. Report 5.1, P26

No additional resource implications beyond officer time to oversee delivery, with risks around construction costs, weather and planning or SuDS Approval Body delays flagged. Report 7.1, P31, P25

The money

  • £144,000 Church Road S106 offsite recreation contribution allocated to Caldicot Greenway/MUR Report 2.1
  • £167,000 Crick Road S106 offsite recreation contribution allocated to Caldicot Greenway/MUR, subject to receipt of funds Report 2.2
  • £144,456 Remaining Church Road S106 offsite recreation balance reported before this decision Report P8, 3.8, 3.10
  • £170,336 Total off-site recreation funding received from the Church Road S106 agreement Report P7
  • £25,880 Earlier Church Road S106 allocation to upgrade the play area at Castroggi/Hall Park Open Space Report P8
  • £400,000 Adult Recreation Contribution payable to the council under the Crick Road S106 agreement Report 3.1
  • £233,000 Balance of Crick Road S106 offsite contribution remaining after the £167,000 allocation Report 3.11
  • £650,000 Estimated total cost of the Caldicot Greenway/MUR project Report 3.9
  • £190,000 Active Travel core funding already secured for the Caldicot Greenway/MUR Report 3.9
  • £150,000 Shared Prosperity Fund allocation already secured for the Caldicot Greenway/MUR Report 3.9
  • £310,000 Further funding reported as required to enable the Caldicot Greenway/MUR project to proceed Report 3.9

Options considered

  • Rejected: Do nothing. Not recommended: would leave only a small section deliverable, waste secured match funding, risk loss of public trust, and require reapplying for planning and SAB consent with higher costs. Report P24
  • Rejected: Allocate reduced funding (limited to delivering beyond the Green Route). Not recommended: incremental delivery beyond the Green Route would be difficult due to additional engineering and project management costs. Report P25
  • Chosen: Allocate full requested S106 funding to the Caldicot Greenway/MUR. Recommended: completes the publicly consulted scheme, retains match funding, gains public trust, supports equality and 20-minute neighbourhood aims, and caps costs by providing funding certainty. Report P25, 2.1, 2.2

Implications

  • Financial: Approving full S106 funding maximises use of currently secured grant allocations, with no additional resource implications beyond officer time to oversee delivery. Report 7.1, P31, 3.9
  • Equalities: An Integrated Impact Assessment found large positive effects on accessibility, health, social inclusion and the Welsh language, with no direct negative impacts identified for protected characteristics. Report 3.13, P24
  • Climate: The route supports active travel and the council's 20-minute neighbourhood ambition, helping reduce short car journeys under three miles and linking to the Gwent Levels and Wales Coast Path. Report 3.4, 6.1, 6.2
  • Risk: Risks include delays in decision making on remaining funding, higher construction costs from clause breaks, extreme weather, and planning or SAB delays. Report P25
  • Other: The scheme delivers on the Green Infrastructure Strategy adopted in 2024 and the Countryside Access Improvement Plan 2020-2030, and links to a development north of Crick Road proposed in the RLDP. Report 3.10, P20

Who and where

  • Residents of Caldicot, Portskewett and the wider Severnside area, including Caerwent, Crick and Sudbrook Report P3, 3.4
  • Walkers, cyclists, wheelchair and mobility scooter users, and other users of the greenway route Report 3.4, 3.5
  • Visitors to Caldicot Castle and Country Park, the Gwent Levels and the Wales Coast Path Report 3.4, 6.1
  • Caldicot Town Council and local Severnside county councillors, who will be consulted on remaining Crick Road allocations Report 3.11, 8.2

Timeline

  • 29 March 2019: Crick Road Section 106 agreement signed Report 3.1
  • 17 April 2019: Church Road Section 106 agreement signed Report 3.1
  • 5th May 2024: Earlier Cabinet decision allocating £25,880 to Castroggi/Hall Park play area upgrade and creating a £144,456 capital budget for the remaining Church Road S106 funds Report P8, 8.1
  • August/September 2025: Public consultation on the Caldicot Greenway/MUR scheme Report 3.5, P38
  • 8th December 2025: Severnside members workshop consulted on allocation of the remaining S106 Church Road and Crick Road funding Report 3.11, 8.2
  • 21 January 2026: Cabinet decision to allocate the S106 funds to the Caldicot Greenway/MUR project Report 2.1, 2.2

Plain English for the jargon

  • S106: Section 106 agreement, a legal planning agreement under which a developer contributes funds for local infrastructure, recreation or community facilities
  • MUR: Multi-User Route, a shared path designed for walkers, cyclists, mobility scooter users and other non-motorised users
  • Greenway: A dedicated traffic-free path, in this case the former munitions railway line repurposed for active travel between Portskewett and Caldicot
  • 20-minute neighbourhood: Planning concept where residents can reach most daily needs by walking, wheeling or cycling within about 20 minutes
  • AT: Active Travel, modes of travel such as walking and cycling
  • SPF: Shared Prosperity Fund, a UK Government funding programme
  • PROW: Public Rights of Way, legally protected paths the public can use
  • SAB: SuDS Approval Body, the body that approves Sustainable Drainage Systems for new developments
  • RLDP: Replacement Local Development Plan, the council's planning policy document for future development
  • NRW: Natural Resources Wales, the Welsh Government's environmental body
  • Cadw: The Welsh Government's historic environment service
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5

Resolved

That Cabinet approves the allocation of £144,000 from the Church Road S106 offsite recreation contribution to the Caldicot Greenway/Multi-User Route (MUR) project. That Cabinet approves the allocation of £167,000 from the Crick Road S106 offsite recreation contribution to the Caldicot Greenway/MUR project, subject to receipt of funds.
Word for word from the decision Monmouthshire published for this meeting. Source: democracy.monmouthshire.gov.uk

Follow this further

Built from Monmouthshire's papers

What the report saysPro

Report to Cabinet

Recommendations

2.1That Cabinet approves the allocation of £144,000 from the Church Road S106 offsite recreation contribution to the Caldicot Greenway/Multi-User Route (MUR) project.

2.2That Cabinet approves the allocation of £167,000 from the Crick Road S106 offsite recreation contribution to the Caldicot Greenway/MUR project, subject to receipt of funds.

3. KEY ISSUES:

S106 Background

3.1The Church Road and Crick Road residential developments in Caldicot and Portskewett have each been subject to Section 106 agreements, which set out the financial contributions to be made by the developers to support local infrastructure, recreation, and community facilities.

3.2The Section 106 agreement for Church Road (dated 17 April 2019 - see attached Appendix 1) required the developer to pay a range of contributions, including a specific off-site recreation facilities contribution. The agreement states the funding should be used for one or a combination of four named beneficiary projects which includes: 1) Caldicot Greenway Scheme, 2) Caldicot Castle Country Park, 3) Hall Park Open Space, 4) Caldicot Town Centre Regeneration Project.

The total off-site recreation contribution was calculated based on the final number of market dwellings delivered, with payments made in two instalments: one prior to occupation of 50% of the market dwellings, and the second prior to occupation of 80% of the market dwellings. The total off-site recreation funding received from Church Road was £170,336. At its meeting on 5th May 2024 (see attached Appendix 3) Cabinet decided:

a) To allocate £25,880 towards the cost of upgrading the play area at Castroggi (also known as the Hall Park Open Space), b) To create a capital budget of £144,456 in 2024/25 (the remaining balance of the S106 offsite recreation contribution from Church Road) to fund works at one or more of three beneficiary sites, namely:  the Caldicot Greenway Scheme  Caldicot Castle Country Park  the Caldicot Town Centre Regeneration Scheme c) To delegate to the Chief Officer for Customer, Culture and Wellbeing in consultation with the Cabinet Member for Equalities and Engagement, a decision on how the remaining funding of £144,456 should be spent, to be taken following consultation with the local Caldicot county council members and Caldicot Town Council.

3.1The Section 106 agreement for Crick Road (dated 29 March 2019 – see attached Appendix 2) required the developer to pay an “Adult Recreation Contribution” of £400,000 to Monmouthshire County Council. The agreement states the funding should be used for one or a combination of four named beneficiary projects which includes:

1) Developing the former MOD railway as a footway/cycle path (creating links from the property to Caldicot Country Park and the Cornfield Project), 2) improvements to Caldicot Castle Country Park, 3) the Caldicot Regeneration Scheme, 4) Cornfield Project.

The agreement stipulated that the contribution should be paid prior to completion or occupation (whichever was the soonest) of 50% of the dwellings. This sum is index- linked and ring-fenced for the specified projects, ensuring that the funding is used to deliver tangible benefits for the local community.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
DM_2018_00880-S106_AGREEMENT_Church RdAppendix 1 4.9 MB Download
PDF
DM 2018 00696 Section 106 Agreement Crick RdAppendix 2 6.7 MB Download
PDF
S106 Cabinet Decision 5th May 2024 Church RdAppendix 3 323 KB Download
PDF
Map and Photos S106Appendix 4 779 KB Download
PDF
MUR Stakeholder HighlightsAppendix 5 294 KB Download
PDF
S106 CHURCH ROAD AND CRICK ROAD ALLOCATION OF S106 OFFSITE RECREATION FUNDINGReport 418 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

22 of 34 attended
JD
Jonathan DaviesOfficer, present
CC
County Councillor Mary Ann BrocklesbyCommittee Member, present
CC
County Councillor Paul GriffithsCommittee Member, present
CC
County Councillor Catrin MabyCommittee Member, present
RM
Robert McGowanOfficer, expected
PD
Peter DaviesOfficer, expected
HI
Hazel IlettOfficer, expected
PM
Paul MatthewsOfficer, present
WM
Will McLeanOfficer, present
JR
Jane RodgersOfficer, present
JP
John PearsonOfficer, expected
WB
Wendy BarnardOfficer, expected

All 34 on the meeting page

On this subject at Monmouthshire

Search all
  1. S106 CHURCH ROAD AND CRICK ROAD ALLOCATION OF S106 OFFSITE RECREATION FUNDINGThis decision
  2. Church Road Caldicot S106 FundingAgreed

More from Monmouthshire Cabinet

All decisions
MeetingDecisionOutcome
11 Nov 2026 Local Growth Fund Year 2 and 3 2027- 2029That the Cabinet considered the draft Local Growth Fund proposals for Years 2 and 3. That Cabinet approves the portfo... Approved Open
11 Nov 2026 Future of Former Tudor Street Day Centre, AbergavennyTo terminate the existing Tenancy at Will agreement with The Gathering Community CIO. To Approve the commencement of ... Agreed Open
11 Nov 2026 Medium Term Financial Plan Update - October 2026That Cabinet notes the refreshed MTFP update at Appendix 1, including the current scenario based planning range for 2... Decided Open
14 Oct 2026 Performance and Overview Scrutiny Committee - Feedback to Cabinet of Meeting held on 29th September 2026Noted. Noted Open
14 Oct 2026 Place Committee - Feedback to Cabinet of Meeting held on 1st October 2026Noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies