DEVELOPMENT OF A SUPPORTED ACCOMMODATION PROVISION
ApprovedExecutive3 papers
AI summaryMonmouthshire Cabinet approves acquisition and refurbishment of a Monmouth property to provide 3-bed supported accommodation for care experienced young people aged 16-24, funded by a £675,450 Housing with Care Fund grant with £3m borrowing as fallback.
Written from the decision and the officer reportPDF Pro
OutcomeApproved3-bed supported accommodation in Monmouth, third-party support contract
Money£675,450 HCF grant requestedwith £3m borrowing headroom fallback over 10 years
What happens nextComplete purchase by 31 March 2026Property works tender April to June 2026, operational September 2026
Who it affectsCare experienced young people 16-24in Monmouthshire, plus external provider via tender
What was decided
Cabinet approved acquiring and refurbishing a property in Monmouth to create supported accommodation for 3 care experienced young people aged 16-24, with support delivered by an external provider. Report P7, P10, P13, P17
Cabinet approved using a Housing with Care Fund capital grant for the whole capital cost, with any shortfall met from the £3m borrowing headroom agreed by Full Council on 18 April 2024 over a 10-year term. Report P14, P16, P156
Cabinet approved entering a contract with a suitable external provider to deliver the housing-based support element. Report P17, P53
Why
Monmouthshire has a national and local shortage of supported accommodation for 16-plus care leavers, leaving the council reliant on costly spot-purchased placements and forcing young people away from their communities. Report P8, P23, P24, P26, P29
An in-house owned property managed by a third-party provider fits Welsh Government policy to remove profit from children's care and gives the council greater control of matching, quality and placement decisions. Report P7, P18, P44, P66
Modelling shows potential annual revenue savings of £178,201 at 100% occupancy with grant funding, against current spend of £446,000 a year on external placements for an equivalent cohort. Report P137, P162, P170, P173
What happens next
Complete property purchase by 31 March 2026, then run a mini-tender with framework contractors in April 2026, appoint a contractor in May 2026 and start works in June 2026. Report P183, P184
Procure a third-party support provider through an open Sell2Wales process, with the contract in place by September 2026 when the provision becomes operational. Report P53, P120, P152, P154, P183
If the HCF grant is not approved in full, draw on the £3m borrowing headroom already factored into the medium-term treasury budget. Report P16, P127, P160
The money
£675,450 Housing with Care Fund capital grant application for purchase and refurbishment Report P156
£3m Borrowing headroom agreed at Full Council 18 April 2024 over 10 years, as fallback if grant not secured in full Report P16
£1,652.56 Weekly external provider cost per bed Report P146, P164
£257,799.36 Annual revenue cost of external support provider contract Report P146, P164, P170
£446,000 Current annual spend on external placements for an illustrative 3-child cohort Report P137, P162, P172
£178,201 Potential annual revenue saving at 100% occupancy with grant funding Report P173
£95,913 Potential annual revenue saving at 100% occupancy funded by borrowing Report P173
£82,288.00 Annual borrowing repayment cost over 10 years at rates on 29/01/26 Report P170, P175
Options considered
Rejected: Option 1: Do nothing, continue spot-purchasing from external market. Leaves council dependent on external market and loses grant funding opportunity Report P137, P138, P139, P140, P141
Rejected: Option 2: Do minimal, do not proceed with this property and seek alternatives. Suitable properties are rare and delay could be lengthy Report P142, P143, P144, P145, P146
Chosen: Option 3: Purchase and redevelop property with 3rd party support delivery. Shares risk with an experienced provider, supports mixed delivery model, lowest net cost Report P146, P147, P148
Rejected: Option 4: Purchase and redevelop property with in-house support team. Loses resilience of mixed market; recruitment prioritised for residential rather than accommodation-based support Report P149, P150
Implications
Financial: Potential annual revenue savings of £178,201 against £446,000 current external placement cost, at 100% occupancy with grant funding; £95,913 if borrowing used. Report P173
Legal: Ten-year restriction on title in favour of Welsh Government as a condition of the HCF grant, with claw back risk if conditions are breached. Report P130
Legal: A Certificate of Lawful Use is required to confirm change of use from C3 dwelling houses to C3(b). Report P113
Staffing: Support will be delivered by an external provider commissioned via Sell2Wales, with quarterly contract monitoring by council officers. Report P53, P120, P187
Risk: Key risks include: delays in ministerial grant approval, refurbishment cost overruns, failure to secure a provider, and inability to identify suitable young people. Report P104, P120, P124, P125, P128
Climate: Property has EPC rating 85 B with potential to reach 94 A; solar PV and optional air source heat pump (additional £30k) under consideration. Report P58, P59, P102
Other: Contingency options if the project fails include re-tendering, in-house support, selling placements to other councils, change of use with the regional partnership board, or re-purposing the property. Report P188, P189, P190, P191
Who and where
Care experienced young people aged 16-24 in Monmouthshire, including unaccompanied asylum-seeking children Report P7, P10, P46, P73
Monmouthshire County Council Children's Services, as future placement commissioner and asset owner Report P13, P17, P66
A yet-to-be-procured third-party support provider, via open tender Report P17, P53, P120, P152
Social workers and personal advisors, whose travel time should reduce as more placements are local Report P66, P99
Timeline
18 April 2024: Full Council agreed £3m borrowing headroom and ambitions for in-house children's residential and 16+ supported accommodation placements Report P19, P32
27 November 2025: 73 children and young people aged 14+ were in care placements in or out of county; 43 of these were already 16 or over Report P74, P83, P84
21 January 2026: Welsh Government approved HCF grant application for the property purchase, subject to ministerial sign-off Report P14, P103
31 March 2026: Deadline to complete property purchase, required by grant funding conditions Report P135, P183, P184
April 2026: Framework contractors mini-tender for refurbishment works and service specification drafting Report P183, P184
May 2026: Appoint refurbishment contractor Report P183, P184
June 2026: Commencement of refurbishment works Report P183
August 2026: Completion of refurbishment works (as stated in the report's milestone list) Report P183
September 2026: Provision becomes operational; first cohort of young people matched and in place Report P135, P183, P184
Plain English for the jargon
Care experienced young people: Children and young people aged 16-24 who are or have been Looked After by the local authority
Housing with Care Fund (HCF): Welsh Government capital grant programme supporting accommodation-based services, including for looked-after children
Looked After Children: Children in the care of the local authority under the Social Services and Well-being (Wales) Act 2014
Spot-purchased placements: Care placements bought from independent providers on a one-off basis, often at higher cost
Pathway plan: A plan for care leavers from age 14 setting out support, accommodation and education or employment goals after age 16
C3 / C3(b) use class: Planning use classes for dwelling houses, with C3(b) covering up to six residents living as a single household such as supported accommodation
CIW (Care Inspectorate Wales): Welsh regulator of care services, which would not register this supported accommodation as it is not covered by RISCA
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6
Resolved
To acquire and refurbish a property in Monmouth for the purposes of developing a supported accommodation provision for care experienced young people. To utilise a Housing with Care Fund grant for the entirety of the capital expenditure associated with the acquisition and subsequent redevelopment of the property (subject to ministerial approval). To the extent that Housing with Care Fund grant is not secured for the full amount requested, that any sum remaining to be funded is met from the £3m borrowing headroom agreed at Full Council meeting 18th April 2024 under a 10-year term. To enter into a contract with a suitable external provider to provide the housing-based support for young people residing at the property.
Word for word from the decision Monmouthshire published for this meeting.Source: democracy.monmouthshire.gov.uk
ACQUISITION PROPERTY IN MONMOUTH TO PROVIDE A REGISTERED SUPPORTED LIVING ACCOMODATION SINGLE-STAGE BUSINESS CASE - MEDIUM VALUE AND RISK - (£250K TO £2 MILLION VALUE OF PROCUREMENT)
Author: Jane Rodgers Chief Officer, Social Care and Health
Date (26.01.2026)
Consultees: Councillor Ian Chandler, Cabinet Member for Social Care, Safeguarding and Accessible Health Services (TBC) Nicholas Keyes, Head of Landlord Services. Ben Thorpe, Estates Development Surveyor Tyrone Stokes, Finance Manager Diane Corrister, Head of Children’s Services Scott Hereford, Residential and Resource Service Manager Kevin Fortey, Housing with Care Fund Project Manager, Regional Partnership Board
Page 1 of 15 $ge4eyh5o.docxMonmouth Property
1 INTRODUCTION Children’s Services seek approval to acquire the property in Monmouth, to provide a supported lodgings (accommodation) provision for 3 Monmouthshire care experienced young people aged 16-24. This provision will be available to consider supporting all our 16+ Looked After children and in the future will specifically complement our existing children’s Residential Home in Monmouth. The provision will create a structured step-down pathway to independence and ensure that children can move from residential care to semi-independent living within the same local area, maintaining friendships, support networks, and community. Additionally, the resource would support the Council’s commitment to work towards the eradication of profit from the care of Children Looked After, in accordance with the Health and Social Care (Wales) Act.
Monmouthshire currently has two Local Authority owned supported accommodation properties and requires one further facility to provide suitable placements for young people and reduce our reliance on third party providers.
The subject property has sufficient space for 3 bedrooms together with adequate provision for sleeping- in arrangements for support staff. There is sufficient space for communal areas for recreational activity and there is accessible outdoor space with a rear garden for the young people to utilize.
The proposed use of the property would be to accommodate 3 young people aged between 16-24 for a transitional period to assist in their step-down from care and support. The provision will provide a medium-to-high level of support, in a homely setting, to assist and equip the young people with the skills required to live more independently. In this sense the provision will support a young person’s pathway to independence.
This approach ensures that the individual needs of children are consistently and appropriately met, while providing greater opportunities for placements closer to their homes and communities. Expanding the number of placements managed by the Local Authority will promote stability and certainty in broader care planning for children and young people. It will also strengthen integrated working practices and enhance the quality oversight of the care provided.
This business case therefore seeks approval:
To acquire and refurbish the property for the purposes of developing a supported accommodation provision for care experienced young people.
To utilise a Housing with Care Fund grant for the entirety of the capital expenditure associated with the acquisition and subsequent refurbishment of the property. [Welsh Government approved the grant application on 21st January, confirming Part 1 of the funding to cover 100% of the capital required for the acquisition of the property, subject to final ministerial sign-off. Part 2 of the grant application, which will relate to the refurbishment and redevelopment works, will be prepared and submitted in the new financial year.]
Page 2 of 15 $ge4eyh5o.docxMonmouth Property
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.