CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Monmouthshire County Council
Cabinet, Wednesday 4 March 2026 at 4.30pm

CASTLEWOOD - LOW COST HOME OWNERSHIP FUTURE USE

Agreed Executive 3 papers

AI summaryMonmouthshire Cabinet agrees to repurchase a Low Cost Home Ownership home at Castlewood, Usk, remarket it in 2026 and use it as temporary accommodation if no buyer is found.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedTemporary accommodation fallback if no LCHO buyer found
Money£125,000 purchase, £15,000 worksFunded from £321,731.92 LCHO capital budget
What happens nextComplete repurchase, remarket in Spring/Summer 2026Use as temporary accommodation if no suitable buyer
Who it affectsUsk and adjoining areasHouseholds in housing need in Usk, Llanbadoc, Gwehelog Fawr, Llantrissant Fawr

What was decided

To repurchase the property using available LCHO capital funds and retain it in council ownership on a temporary basis before remarketing for sale in 2026. Report P6

If a suitable purchaser cannot be identified in Spring/Summer 2026, the property will be used as temporary accommodation in the interim before later sale. Report P6, P7

To carry out improvement works to the property and to use a proportion of the sale proceeds from 21 Castlewood to reimburse £3,050 of essential works. Report P6, P7

Why

The property is part of a 1989/90 Build for Sale LCHO scheme in Usk, and the council has a pre-emption requiring it to act within two months of the owner notifying intent to sell. Report P7, P13

Three marketing rounds on Monmouthshire Homesearch have not secured a suitable purchaser meeting local connection and affordability criteria, so repurchase is a contingency measure. Report P7

The proposal supports delivery of affordable accommodation and provides a self-contained unit for families at risk of homelessness if used as temporary accommodation. Report P7, P13

What happens next

Complete the repurchase and improvement works, then remarket the property in Spring/Summer 2026 through Monmouthshire Homesearch. Report P6, P7

If no suitable buyer is identified, the Accommodation Team will manage the property as temporary accommodation until a future sale. Report P7, P14

Reimburse the £3,050 boiler replacement cost for 21 Castlewood from the proceeds of that sale. Report P7

The money

  • £125,000.00 Owners' 50% equity share in the property Report P7, P23
  • £250,000 Council Estates department valuation of the property Report P7
  • £15,000.00 Indicative cost of minor improvement works Report P7, P23
  • £321,731.92 Available balance within LCHO and Home Finder Loan budgets Report P7, P23
  • £3,050 Reimbursement from 21 Castlewood sale proceeds for boiler replacement Report P7
  • 5,000 Estimated annual holding costs (utilities, council tax, management) Report P7, P14, P25
  • £6,250.00 Land Transaction Tax on repurchase Report P23
  • £1,150.00 Purchase costs including surveys and land registry Report P23
  • -£174,331.92 Net cost shown in the cost model after LCHO budget offset Report P23

Options considered

  • Chosen: Repurchase the property and remarket for sale in 2026, with temporary accommodation as a fallback. Retains an affordable home in council control, meets LCHO policy and addresses homelessness demand Report P6, P11
  • Rejected: Allow the owner to sell on the open market. Does not meet the LCHO Policy and Procedure and would lose council control of the property Report P12

Implications

  • Financial: Initial capital outlay for repurchase, surveys, land registry, land transaction tax and refurbishment, funded from the existing LCHO capital budget. Report P7, P14, P23
  • Financial: Estimated annual holding costs of 5,000 if the property remains empty, with management by the Accommodation Team if used as temporary accommodation. Report P14, P25
  • Legal: The council must follow the Castlewood Policy and Procedure May 2013, including the pre-emption requirement to act within two months of the seller's notice. Report P7, P13
  • Equalities: The evaluation identifies positive impacts on health and wellbeing and a more equal Wales, supporting households in housing need within Usk and adjoining communities. Report P7, P8
  • Staffing: There will be an impact on staff resources required to manage the property, including repairs, maintenance and any anti-social behaviour issues if used as temporary accommodation. Report P11
  • Other: PV panels with battery storage and an air source heat pump were ruled out due to substantial cost, leaving a smaller package of insulation and ventilation works. Report P7

Who and where

  • Households in housing need in Usk and the adjoining communities of Llanbadoc, Gwehelog Fawr and Llantrissant Fawr who qualify for the LCHO scheme Report P7
  • Families at risk of homelessness who could be placed in the property as temporary accommodation Report P7, P14
  • The current owner of the property who gave notice of intent to sell in February 2025 Report P7
  • The Council's Accommodation Team, which would manage the property if used as temporary accommodation Report P7, P14

Timeline

  • 1989/90: Eleven properties constructed in Usk under the Build for Sale 'Monmouthshire Model' scheme Report P7
  • 7th March 1990: Welsh Office consent granted for the Monmouthshire Model scheme Report P7
  • May 2013: Castlewood LCHO Policy and Procedure document updated Report P7, P16
  • 2017: Council repurchased a property at the same scheme, setting a precedent Report P7
  • 2023: Council repurchased another property at the same scheme Report P7
  • 2024: Council repurchased another property at the same scheme Report P7
  • February 2025: Owner gave notice of intent to sell; property first marketed on Monmouthshire Homesearch and a suitable purchaser identified Report P7
  • April 2025 onwards: Three other Castlewood properties sold as LCHO with suitable purchasers Report P7
  • Spring/Summer 2026: Proposed remarketing of the property for sale Report P6, P7
  • September 2025: The prospective purchaser withdrew from the conveyancing process Report P7
  • October 2025: Property remarketed; eight expressions of interest but none met local connection or affordability criteria Report P7
  • December 2025: Property advertised again; a potential purchaser identified but sale subject to a legal process Report P7
  • March 2026: Cabinet decision taken on the future use of the property Report P3, P6

Plain English for the jargon

  • LCHO: Low Cost Home Ownership, a scheme where the council provides an equity loan (usually 30%, up to 50%) toward the purchase price
  • Monmouthshire Model: The Build for Sale LCHO scheme at Castlewood, Usk, agreed by the Welsh Office in 1990
  • Homesearch: Monmouthshire's housing application system used to advertise LCHO properties to eligible households
  • Temporary Accommodation (TA): Self-contained housing provided to households at risk of homelessness, managed by the Council's Accommodation Team
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4

Resolved

To agree to repurchase the property using the available LCHO capital funds. To retain the property in the council’s ownership on a temporary basis before marketing the property for sale again in 2026. If a purchaser cannot be identified in Spring/Summer 2026, it is proposed that the property is used as temporary accommodation in the interim before selling at a later date. To agree to improvement works. To agree to utilise a proportion of the sale proceeds from 21 Castlewood for essential works.
Word for word from the decision Monmouthshire published for this meeting. Source: democracy.monmouthshire.gov.uk

Follow this further

Built from Monmouthshire's papers

What the report saysPro

Report to Cabinet

SUBJECT: CASTLEWOOD – LOW COST HOME OWNERSHIP FUTURE USE

MEETING: CABINET

DATE: MARCH 2026

DIVISION/WARDS AFFECTED: USK AND ADJOINING AREAS

1. PURPOSE 1.1 To approve the purchase of a Low Cost Home Ownership (LCHO) property at Castlewood, Usk, NP15 1SR following receipt of the owner’s intent to sell. 1.2 To approve utilising a proportion of the sale proceeds from 21 Castlewood to cover essential works that were directly attributable to the sale of 21 Castlewood.

2. RECOMMENDATIONS: 2.1 To agree to repurchase the property using the available LCHO capital funds. 2.2 To retain the property in the council’s ownership on a temporary basis before marketing the property for sale again in 2026. If a purchaser cannot be identified in Spring/Summer 2026, it is proposed that the property is used as temporary accommodation in the interim before selling at a later date. 2.3 To agree to improvement works. 2.4 To agree to utilise a proportion of the sale proceeds from 21 Castlewood for essential works.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2a. Appendix 1: Castlewood, Usk Policy and ProcedureAppendix 137 KB Download
PDF
2b. Appendix 3: EQIAAppendix 362 KB Download
PDF
CASTLEWOOD: LOW COST HOME OWNERSHIP FUTURE USEReport 352 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

17 of 28 attended
JD
Jonathan DaviesOfficer, present
CC
County Councillor Mary Ann BrocklesbyCommittee Member, present
CC
County Councillor Paul GriffithsCommittee Member, present
CC
County Councillor Catrin MabyCommittee Member, present
RM
Robert McGowanOfficer, expected
PD
Peter DaviesOfficer, present
HI
Hazel IlettOfficer, expected
PM
Paul MatthewsOfficer, present
WM
Will McLeanOfficer, present
JR
Jane RodgersOfficer, expected
JP
John PearsonOfficer, expected
NP
Nicola PerryOfficer, present

All 28 on the meeting page

More from Monmouthshire Cabinet

All decisions
MeetingDecisionOutcome
11 Nov 2026 Local Growth Fund Year 2 and 3 2027- 2029That the Cabinet considered the draft Local Growth Fund proposals for Years 2 and 3. That Cabinet approves the portfo... Approved Open
11 Nov 2026 Future of Former Tudor Street Day Centre, AbergavennyTo terminate the existing Tenancy at Will agreement with The Gathering Community CIO. To Approve the commencement of ... Agreed Open
11 Nov 2026 Medium Term Financial Plan Update - October 2026That Cabinet notes the refreshed MTFP update at Appendix 1, including the current scenario based planning range for 2... Decided Open
14 Oct 2026 Performance and Overview Scrutiny Committee - Feedback to Cabinet of Meeting held on 29th September 2026Noted. Noted Open
14 Oct 2026 Place Committee - Feedback to Cabinet of Meeting held on 1st October 2026Noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies