Acquisition of plots of land for the Undy to Rogiet Severn Tunnel Junction (STJ) Links Active Travel Route
ApprovedExecutive3 papers
AI summaryMonmouthshire Cabinet approved buying land for a new 3m shared walking and cycling path alongside the B4245 between Undy and Rogiet, with authority delegated to the Chief Officer for Infrastructure to complete the purchases.
Written from the decision and the officer reportPDF Pro
OutcomeApproved
MoneyCost awaiting final details
What happens nextLand purchases to proceed
Who it affectsMagor with Undy and Rogiet wards
What was decided
Cabinet approved the acquisition of the land needed to deliver the active travel route between Undy and Rogiet.
Cabinet delegated authority to the Chief Officer for Infrastructure, in consultation with the Cabinet Member, to complete the land acquisition.
Why
The route addresses a lack of active travel infrastructure and severance between Undy and Rogiet, where there is no footway for 1.21km of the B4245, and responds to expected growth from Strategic Growth Areas near Caldicot and Rogiet. Report 2.1, P16
Earlier WelTAG Stage One and Two work concluded that a route parallel to the B4245 should be taken forward, and the Review Group on 19th December 2022 supported that recommendation. Report 1.1
The study objectives focus on a direct, coherent and attractive route, improved safety, more active travel trips, and better access to Severn Tunnel Junction, Caldicot Station and nearby schools. Report 2.2
What happens next
Complete the purchases of the plots needed to build the shared-use path along the southern verge of the B4245. Report 3.2, P29
Seek construction funding from the Cardiff Capital Region Regional Transport Fund in 2026 to 2028, with the Burns Delivery Unit kept under review. Report 7.3, P144, P145
Take forward Phases 2 and 3 of the Severnside route between Rogiet and Caldicot, including access to Severn Tunnel Junction, through a separate WelTAG Lite study. Report P13, 3.2
£43,630 AMAT congestion benefit, high growth scenario, 40-year appraisal Report P43
£593,690 AMAT reduced risk of premature death, low growth scenario, 40-year appraisal Report P51
£2,415,660 AMAT reduced risk of premature death, high growth scenario, 40-year appraisal Report P51
£911,890 AMAT present value of benefits, low growth scenario, 40-year appraisal (2010 prices, excludes maintenance) Report P53, P54
£3,523,100 AMAT present value of benefits, high growth scenario, 40-year appraisal (2010 prices, excludes maintenance) Report P53, P54
Options considered
Chosen: Option 1: 3m shared-use active travel path on the southern verge of the B4245 from Undy Church Road to Rogiet Station Road. Identified as preferred in WelTAG Stages One and Two and progressed to Stage Three detailed design Report 3.2, P29
Rejected: Option 3: route alignment forming the basis of Phase 2 between Rogiet and Caldicot. Being developed separately as part of Phase 2 through a WelTAG Lite study Report 3.2
Implications
Financial: Construction is expected to be funded through the Cardiff Capital Region Regional Transport Fund in 2026 to 2028, with ongoing maintenance absorbed within the existing road maintenance budget. Report 7.3, P144, P145
Legal: Cabinet approval is being sought to authorise compulsory or negotiated purchase of the plots required to build the route. Report 3.2
Equalities: An Equality Impact Assessment Screening Report found no likely adverse impacts on protected groups, so a full Equality Impact Assessment was not required. Report P105
Climate: The AMAT assessment forecasts a greenhouse gas monetary benefit of between £3.3k and £15k over 40 years through modal shift, plus air quality and noise benefits of between £200 and £1k. Report P109, P106
Risk: Ecological mitigation will be required for habitats, bats, dormice, hedgehogs, amphibians and reptiles, and consultation with MCC Planning is needed for any works affecting Tree Preservation Orders. Report P110
Other: Alternative bus stop design details have been agreed with Transport for Wales because of limited width at one stop. Report 3.2
Who and where
Residents of Undy and Rogiet who currently have no footway for 1.21km of the B4245, including at the M4 underbridge Report P16
Users of Severn Tunnel Junction and Caldicot Station seeking access by active modes Report 2.2, P64
Pupils and families travelling to Rogiet Primary School and Caldicot School Report 2.2, P65
Landowners along the B4245 whose plots are needed for the 2.08km route Report 3.2
Bus passengers using stops along the B4245 between Undy and Rogiet Report 3.2, P64
Timeline
19th December 2022: Review Group endorsed the WelTAG Stage One and Two recommendation to take forward the B4245 route Report 1.1
December 2024: WSP Integrated Well-being Appraisal and WelTAG Stage Three report dated December 2024 Report P8, P10
2025: Assumed scheme opening year used in the AMAT appraisal
2026-28: Intended construction period for the proposed scheme using Cardiff Capital Region Regional Transport Fund Report 7.3
40-year appraisal period: AMAT benefits and costs assessed over 40 years, based on 2010 prices Report P41, P42
Plain English for the jargon
WelTAG: Welsh Transport Appraisal Guidance, the Welsh Government's framework for appraising transport interventions
WelTAG Stage Three: Full Business Case stage of a WelTAG study, appraising a preferred option in detail
AMAT: Department for Transport Active Mode Appraisal Toolkit, used to estimate benefits of walking and cycling schemes
PVB: Present Value of Benefits, the total monetised benefits calculated by the AMAT over the appraisal period
B4245: The primary road connecting Rogiet and Undy, between the A48 at Parkwall Roundabout and the A48 Chepstow Road
Severn Tunnel Junction: Railway station in the Severnside area that the wider active travel route is designed to serve
Shared-use path: A path designed for use by people walking, wheeling and cycling, in this case 3m wide
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9
Resolved
To progress the delivery of an active travel route between Undy and Rogiet through land acquisition. That Cabinet approves the acquisition of the land required for the route. That Cabinet delegates authority to the Chief Officer for Infrastructure, in consultation with the Cabinet Member, to complete the land acquisition.
Word for word from the decision Monmouthshire published for this meeting.Source: democracy.monmouthshire.gov.uk
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.