Audit Wales Work Programme: Council Progress Update

Noted Finance 1 paper

AI summaryMonmouthshire's Governance and Audit Committee noted the council's progress update on Audit Wales recommendations, with open proposals on financial sustainability, performance data, counter-fraud and commissioning.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNo further action required from committee
MoneyNo specific sum stated
What happens nextCommissioning framework reviewProvisionally scheduled for October 2026
Who it affectsCouncil-wide servicesIncluding performance, finance, counter-fraud, commissioning

What was decided

The committee noted the report setting out progress against open and closed Audit Wales proposals for improvement. Report 3.2

Why

The committee is responsible for scrutinising the council's response to Audit Wales findings and seeking assurance that adequate progress is being made. Report 2.1, 3.1

Audit Wales reviews focus on value for money and the sustainable development principle in how the council meets its well-being objectives. Report 3.1

What happens next

Officers are developing a Change and Improvement Plan to close the council's forecast funding gap, with an update to Performance and Overview Scrutiny Committee in September. Report P26, P27

An authority-wide commissioning framework is being developed with Ardal partners, with monitoring arrangements due by March 2027. Report P42, P43

Performance management training and a data maturity assessment are being progressed during Q2 2026/27. Report P22, P23, P31

Implications

  • Financial: The council has low reserves and is yet to identify how it will close its future funding gap, requiring pace on its financial strategy. Report P25, P26
  • Risk: Counter-fraud arrangements are improving but further work is needed on data analytics and intelligence sharing, with rolling out of App Check across service areas. Report P33, P35, P38
  • Risk: Weaknesses in data quality and accuracy of service user and outcomes information are restricting senior leaders' ability to manage performance effectively. Report P21
  • Legal: The committee may refer national study findings to other scrutiny committees, including Democratic Services Committee, where further consideration is needed. Report 2.2, 3.4
  • Equalities: A national review of the Additional Learning Needs system found public bodies lack a complete picture of demand, costs, workforce and outcomes for vulnerable learners. Report P46, P48, P49

Who and where

  • Service users across council services, particularly those with Additional Learning Needs Report P21, P48
  • Senior leaders and service managers responsible for performance and commissioning Report P21, P42
  • Internal Audit team, with new AI tools being introduced Report P39
  • Members of Governance and Audit Committee, who receive quarterly counter-fraud updates Report P35

Timeline

  • November 2025: F-POP change programme launched to staff and senior leaders Report P26
  • February 2026: Internal Audit Strategy updated; service business plan quality assurance completed Report P31, P35
  • Q2 2026/27: Performance management training and updated service business plan guidance to be rolled out Report P22, P31
  • October 2026: Provisional date for Governance and Audit Committee to review the new commissioning framework Report P42
  • March 2027: Target for commissioning monitoring arrangements to be set out Report P43

Plain English for the jargon

  • ALN: Additional Learning Needs, covered by the Additional Learning Needs and Education Tribunal (Wales) Act 2018
  • F-POP: For Purpose, On Purpose, the council's change and improvement programme
  • GAC: Governance and Audit Committee
  • Ardal: Regional collaboration partnership the council is working with on commissioning
  • Audit Wales proposals for improvement: Recommendations made by Audit Wales following a review, which can be open or closed depending on assessed progress
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

To note the report.
Word for word from the decision Monmouthshire published for this meeting. Source: democracy.monmouthshire.gov.uk

Follow this further

Built from Monmouthshire's papers

What the report saysPro

Report to Governance and Audit Committee

Recommendations

2.1That members scrutinise the council’s response to the Audit Wales work programme, seeking assurance that adequate progress is being made.

2.2That members refer any issues contained within Audit Wales national studies to other committees for consideration where they identify there are findings of particular relevance to the council that need further scrutiny.

3. KEY ISSUES

3.1Each year, Audit Wales produces an Audit Plan, which sets out the work they intend to undertake to discharge their duties, and this is presented to Governance and Audit Committee upon publication. The performance audit work programme set by Audit Wales focusses on discharging duties in relation to value for money and sustainable development:  Value for money - The Council has to put in place arrangements to get value for money for the resources it uses.  Sustainable development principle - The Council needs to comply with the sustainable development principle when setting and taking steps to meet its well-being objectives.

3.2This report provides an update on the progress being made by the council in implementing the findings of Audit Wales reviews. This includes an update on progress against existing recommendations, followed by the latest local audit work carried out since the last review, with an accompanying management response. Recommendations that require further attention are marked as ‘open’ – these can be found in appendix 1. Where a recommendation has been assessed as being adequately addressed, it is ‘closed’ and explanation why included. Some of the forward-looking actions committed to by the authority are likely to be reflected within other council strategic documents such as the Community and Corporate Plan, enabling strategies, the Whole Authority Strategic Risk Assessment and the Medium-Term Financial Plan.

3.3As well as local work at each council, Audit Wales carries out national studies across the local government sector to make recommendations for improving value for money, and all of these reports are published on www.audit.wales/publications. Whilst the findings of these studies are not necessarily specific to Monmouthshire County Council, those of greatest relevance are shared with the most appropriate service area to consider their findings and recommendations and to respond accordingly. Appendix 2 identifies the studies most applicable to the council since the last iteration of this report. This includes a review of the Additional Learning Needs system; the recommendations provided by Audit Wales as part 1 of this report are directed to Welsh Government, and so a management response to these recommendations has not been provided. An overview of the report and Audit Wales’s findings has been provided for the committee’s awareness.

3.4Governance and Audit Committee has a role in ensuring the council is responding to the findings from national studies and can also refer them to another scrutiny committee if they feel the report requires further in-depth consideration beyond the response already provided by the service area. The committee may also refer issues to Democratic Services Committee.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Audit Wales Work Programme: Council Progress UpdateReport 563 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 30 attended
AB
Andrew BlackmoreCommittee Member, present
CP
Colin ProsserCommittee Member, present
RG
Rhodri GuestCommittee Member, present
MT
Michael ThomasCommittee Member, expected
CC
County Councillor Sara BurchCommittee Member, present
CC
County Councillor Tony EassonCommittee Member, present
CC
County Councillor David JonesCommittee Member, present
CC
County Councillor Malcolm LaneCommittee Member, expected
CC
County Councillor Phil MurphyCommittee Member, present
CC
County Councillor Peter StrongCommittee Member, present
CC
County Councillor Ann WebbCommittee Member, apologies, sent representative
CC
County Councillor Rachel GarrickCommittee Member, present

All 30 on the meeting page

On this subject at Monmouthshire

Search all
  1. Audit Wales Work Programme: Council Progress UpdateThis decision
  2. Audit Wales: Review of Housing AdaptationsNoted
  3. Audit Wales: Recruitment and Retention ChallengesNoted
  4. Audit Wales - Monmouthshire County Council’s Statutory Accounts: Delivery Plan and Next StepsNoted
  5. Audit Wales Audit Plan 2026-27Noted
  6. Implementing Audit Wales recommendations to improve the Council's digital approachNoted

More from Monmouthshire Governance and Audit Committee

All decisions
MeetingDecisionOutcome
19 Nov 2026 To note the Action List from the previous meeting.Resolved that Action 1 be closed and progress against Action 2 be noted. Noted Open
19 Nov 2026 26/27 Q2 Treasury reportResolved that the report be noted. Officers to review arrangements for providing members with access to relevant exem... Noted Open
19 Nov 2026 Whole Authority Annual Complaints ReportResolved that the report be noted. Noted Open
19 Nov 2026 The Ombudsmans's Annual LetterResolved that the report be noted. Officers to consider providing further assurance regarding how complaint informati... Noted Open
19 Nov 2026 Annual Audit Plan Welsh Church FundsResolved that the report be noted. Noted Open