Cabinet, Wednesday 16 September 2026 at 5.00pm

Local Flood Risk Management Strategy

Noted Executive 6 papers

AI summaryMonmouthshire Cabinet adopts revised Local Flood Risk Management Strategy to manage local flood risk from surface water, groundwater and ordinary watercourses across the county, pending Welsh Government Ministerial approval.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedCabinet adopted the Local Flood Risk Management Strategy and approved its submission to Welsh Government for Ministerial approval
MoneyVarious cost bands71 actions in Strategic Flood Risk Areas categorised from £1k to over £1M, plus 38 county-wide actions delivered through existing budgets, all funded by Revenue Support Grant and Welsh Government capital grants
What happens nextMinisterial approvalThe adopted Local Strategy will be submitted to Welsh Government for Ministerial approval
Who it affectsAll Monmouthshire residents and businessesThe strategy covers flood risk from surface water, groundwater and ordinary watercourses across nine Strategic Flood Risk Areas

What was decided

Cabinet considered the results and review of the statutory public consultation on the draft Local Strategy, which was presented to Place Scrutiny Committee on 30th July 2026.

Cabinet noted the feedback from Place Scrutiny Committee.

Cabinet adopted the Local Strategy and approved its submission to Welsh Government for Ministerial approval.

Why

Under Section 10 of the Flood and Water Management Act 2010, the Lead Local Flood Authority must develop, maintain, apply and monitor a strategy for local flood risk management. Report 3.1, 3.7

The revised Local Strategy ensures compliance with Welsh Government's National Strategy for Flood and Coastal Erosion Risk Management in Wales, published in October 2020. Report 3.5, 3.6

The previous Local Strategy (2013) and Flood Risk Management Plan (2016) required updating to reflect changes in legislation, policies and funding arrangements. Report 3.4, 3.6

What happens next

Following Cabinet approval, the amendments highlighted in red text will be inserted correctly in the final version before submission to Welsh Government. Report 6.14

The Local Strategy will be submitted to Welsh Government for Ministerial approval. Report 2.4

The Local Strategy will be reviewed within 2 years of the next National Strategy publication, approximately every 6 years. The Flood Action Plan will be reviewed every 3 years or as required. Report 3.14

The money

  • £1k, £20k Low Cost band for 26 actions in Strategic Flood Risk Areas Report 6.21
  • £20k, £250k Medium Cost band for 42 actions in Strategic Flood Risk Areas Report 6.21
  • £250k - £1M High Cost band for 2 actions in Strategic Flood Risk Areas Report 6.21
  • £1M+ Very High Cost band for 1 action in Strategic Flood Risk Areas Report 6.21
  • Various 38 county-wide actions delivered through existing internal staff resources funded by existing revenue budgets Report 6.20
  • Various Development, consultation and monitoring costs supported by Welsh Government revenue grant funding Report 8.2

Options considered

  • Rejected: Do Nothing: Do not update the Local Flood Risk Management Strategy (2013) or Flood Risk Management Plan (2016). This is not considered to be a feasible option given the requirements of the Flood and Water Management Act 2010. By not updating the Local Strategy, MCC will not be compliant with its statutory duty, nor will there be a Strategy in place that takes account of the current National Strategy and related legislation. Report P39
  • Chosen: Do Something: Update the existing Local Flood Risk Management Strategy and Flood Risk Management Plan. This will ensure MCC's Local Flood Risk Management Strategy is compliant with Section 10 of the FWMA and that local sources of flood risk are effectively managed by MCC as the Lead Local Flood Authority. The updated Strategy will give clear strategic direction and a valuable source of information on who is responsible for managing different sources of flood risk. Report P41

Implications

  • Legal: The revised Local Strategy ensures that MCC fulfils its statutory duty under the Flood and Water Management Act 2010 to produce, develop, maintain, apply, and monitor a Local Flood Risk Management Strategy. Report 4.1
  • Financial: Costs associated with delivery of each measure and action will be met through Revenue Support Grant supplemented by Welsh Government grant funding, or through Welsh Government capital grants including Flood and Coastal Erosion Risk Management capital grants and Small Scale Works Grant (for schemes under £300k). Report 8.4
  • Other: The revised Local Strategy integrates the previous Local Strategy (2013) and Flood Risk Management Plan (2016) into one document, reducing complexity and enabling MCC to communicate and manage local flood risk more effectively. Report 3.8

Who and where

  • All residents, elected members, community groups, other Risk Management Authorities, external organisations and the general public in Monmouthshire Report 4.2
  • Welsh Government, Natural Resources Wales, other Risk Management Authorities, town and community councils and neighbouring Local Authorities Report 6.5

Timeline

  • July to August 2023: Non-statutory public engagement exercise (online survey with 90 responses) Report 6.1, 6.2
  • 10th July 2025: Draft Local Strategy presented to Place Scrutiny Committee prior to statutory consultation Report 6.3
  • 1st August to 26th September 2025: Eight-week statutory public consultation period with drop-in sessions across five towns and 80 responses received Report 6.5, 6.7, 6.8
  • 30th July 2026: Final Local Strategy presented to Place Scrutiny Committee Report 6.17
  • 16th September 2026: Cabinet meeting to consider adoption of the Local Strategy
  • Short Term (1-3 years): Delivery timescale for some Flood Action Plan actions Report 6.20
  • Medium Term (3-6 years): Delivery timescale for some Flood Action Plan actions Report 6.20
  • Long Term (6+ years): Delivery timescale for some Flood Action Plan actions Report 6.20
  • Approximately every 6 years: Review of the Local Strategy following publication of the next National Strategy Report 3.7
  • Every 3 years or as required: Review and update of the Flood Action Plan Report 3.7, 3.14

Plain English for the jargon

  • Lead Local Flood Authority (LLFA): The local authority designated under the Flood and Water Management Act 2010 responsible for developing, maintaining, applying and monitoring a local flood risk management strategy. In Monmouthshire this is Monmouthshire County Council.
  • Local flood risk: Risk from surface water runoff, groundwater and ordinary watercourses (usually smaller watercourses not designated main rivers).
  • Strategic Flood Risk Areas (SFRAs): Catchment-based areas used to assess and manage flood risk holistically across Monmouthshire. The county is divided into nine SFRAs.
  • Flood Action Plan: A focused plan within the Local Strategy detailing specific deliverable actions to address flood risks, formerly known as the Flood Risk Management Plan.
  • Risk Management Authorities: Organisations with responsibilities for managing different sources of flood risk, including Lead Local Flood Authorities, Natural Resources Wales and water companies.
  • Small Scale Works Grant: Welsh Government capital grant funding for flood risk management schemes with a construction value of less than £300k.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5

Resolved

That Cabinet considered the results and the review of the statutory public consultation on the draft Local Strategy, which was presented to Place Scrutiny Committee on 30th July 2026. To note the feedback from Place Scrutiny Committee. To adopt the Local Strategy. To submit the Local Strategy to the Welsh Government for Ministerial approval.
Word for word from the decision Monmouthshire published for this meeting. Source: democracy.monmouthshire.gov.uk

Follow this further

Built from Monmouthshire's papers

What the report saysPro

Report to Cabinet

Recommendations

2.1To consider the results and the review of the statutory public consultation on the draft Local Strategy, which was presented to Place Scrutiny Committee on 30th July 2026.

2.2To note the feedback from Place Scrutiny Committee.

2.3To adopt the Local Strategy.

2.4To submit the Local Strategy to the Welsh Government for Ministerial approval.

3. KEY ISSUES:

3.1Under the Flood and Water Management Act 2010 (FWMA)1, Monmouthshire County Council (MCC) is the Lead Local Flood Authority (LLFA) for its administrative area. Under this legislation, MCC is required to develop, maintain, apply and monitor a strategy for local flood risk management, known as the Local Strategy.

3.2Local flood risk is defined as the risk from: • Surface water runoff • Groundwater • Ordinary watercourses (usually smaller watercourses, not designated main rivers).

1 Flood and Water Management Act 2010

1 3.3 The draft revised Local Strategy focuses on these local sources of flood risk within Monmouthshire, but also acknowledges and considers other sources of flood risk (including main rivers, sea, and sewers) and associated responsible Risk Management Authorities. The responsibility for different sources of flood risk is detailed in the Local Strategy and outlined in the following table.

3.4MCC published its first Local Strategy in 2013, setting out their overarching approach to managing local flood risk. Alongside their Local Strategy, MCC published a Flood Risk Management Plan (FRMP) in 2016. The FRMP developed the objectives and high-level measures outlined in the Local Strategy into a more detailed plan for managing flooding in our communities.

3.5Following the publication of Welsh Government’s new National Strategy for Flood and Coastal Erosion Risk Management in Wales (National Strategy)2 in October 2020, LLFA’s in Wales are required to revise their Local Strategy to ensure compliance with the National Strategy.

3.6The revised Local Strategy has been developed to ensure compliance with the National Strategy. It also takes into account changes to relative key legislation, policies and funding arrangements for local flood risk management, since the publication of the previous LFRMS 2013 and FRMP 2016.

3.7The revised Local Strategy sets out how flooding from local sources will be managed across Monmouthshire, ensuring consistency with the objectives, measures and related policies and legislation, set out in the National Strategy. The Local Strategy

2 National Strategy for Flood and Coastal Erosion Risk Management in Wales | GOV.WALES

2 will be reviewed within 2 years of the publication of the next National Strategy, approximately every 6 years. The Flood Action Plan will be reviewed and updated every 3 years or as required. The revised draft Local Strategy is included in Appendix 1 of this report.

3.8Whilst MCC previously published their Local Strategy and FRMP separately, the revised Local Strategy integrates the two documents into one. This reduces complexity and enables MCC to communicate and manage local flood risk more effectively. The FRMP is referred to as the Flood Action Plan within the revised Local Strategy.

3.9The structure of the revised Local Strategy is as follows:

Chapter 1 Introduction Introduces the background, need and purpose of the Local Strategy.

Chapter 2 Coordination of Flood Risk Management Summarises how this Local Strategy aligns with other Council strategic plans, national policies and coordination with other stakeholders and their plans.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
4a. Appendix 1: Local Flood Risk Management Strategy 2026 (Post Consultation Amendments: Marked Up Copy) CabinetAppendix 3.3 MB Download
PDF
4b. Appendix 2: Flood Action Plan 2026: Appendix A (Post Consultation Amendments: Marked Up Copy) CabinetAppendix 15 MB Download
PDF
4d. Appendix 4: Strategic Environmental AssessmentAppendix 8.4 MB Download
PDF
4e. Appendix 5: Habitats Regulations AssessmentAppendix 1.8 MB Download
PDF
Local Flood Risk Management Strategy 2026: Summary (Post Consultation Amendments: Marked Up Copy) CabinetAppendix 3 1.5 MB Download
PDF
Local Flood Risk Management StrategyReport 521 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 30 attended
CC
County Councillor Mary Ann BrocklesbyCommittee Member, present
CC
County Councillor Paul GriffithsCommittee Member, present
CC
County Councillor Angela SandlesCommittee Member, present
CC
County Councillor Catrin MabyCommittee Member, present
CC
County Councillor Ben CallardCommittee Member, present
CC
County Councillor Ian ChandlerCommittee Member, present
CC
County Councillor Sara BurchCommittee Member, present
CC
County Councillor Laura WrightCommittee Member, present
CC
County Councillor Richard JohnGuest, present
CC
County Councillor Frances TaylorGuest, present
NP
Nicola PerryOfficer, expected
JW
James WilliamsOfficer, expected

All 30 on the meeting page

More from Monmouthshire Cabinet

All decisions
MeetingDecisionOutcome
11 Nov 2026 Local Growth Fund Year 2 and 3 2027- 2029That the Cabinet considered the draft Local Growth Fund proposals for Years 2 and 3. That Cabinet approves the portfo... Approved Open
11 Nov 2026 Future of Former Tudor Street Day Centre, AbergavennyTo terminate the existing Tenancy at Will agreement with The Gathering Community CIO. To Approve the commencement of ... Agreed Open
11 Nov 2026 Medium Term Financial Plan Update - October 2026That Cabinet notes the refreshed MTFP update at Appendix 1, including the current scenario based planning range for 2... Decided Open
14 Oct 2026 Performance and Overview Scrutiny Committee - Feedback to Cabinet of Meeting held on 29th September 2026Noted. Noted Open
14 Oct 2026 Place Committee - Feedback to Cabinet of Meeting held on 1st October 2026Noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies