Resolved
that griselinia littoralis be purchased in 4/5 foot heights, and planted along the south elevation of the new canopy, to serve as a wind break;
Margam Crematorium Joint Committee decided this item on Friday 20 January 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
that griselinia littoralis be purchased in 4/5 foot heights, and planted along the south elevation of the new canopy, to serve as a wind break;
1 To provide Members with an update on works completed and more detailed costings on proposed works.
Completed Works
2 The following works have now been completed:
Installation of canopy
Ongoing Works
3 External. An order for the new path under the canopy has be placed and the works will commence on the weekend of the 21st and 22nd of January. The works will take two weekends in total however the path will be left in a safe operational manner following the works on the first weekend. The surface and colour have been chosen following advice from CADW. The cost of this is £8800.00
4 Internal. The audio and visual works have started onsite with the physical elements being installed prior to Christmas. The installation of the control system and commissioning has been booked in for the weekend of the 28th of January Proposed Works
5 Wind break along the new canopy. Following the installation of the canopy concerns have been raised as to the amount of shelter that would be afforded by the canopy. Therefore various options have been considered ranging from trellis panels, fencing or hedging to be run along the south elevation to protect from the prevailing wind. Taking advice from the Superintendent further options regarding a hedge was sought, and the Authority’s arborist has recommended the use of griselinia littorarlis, which is a fast growing evergreen shrub. An estimate for this using established specimens ranging from 1.2m to 1.5m in height along the full length is £1,420.00
Financial Impact
10 The cost of the proposed works will need to be considered in the context of the available reserves whilst noting that, as a ‘public facing’ building that provides a cremation service, there is a requirement to ensure that it maintains the necessary standards
Equality Impact Assessment
11 A Screening Assessment has been undertaken to assist the Council in discharging its Public Sector Equality Duty under the Equality Act 2010. After completing the assessment it has been determined that this proposal does not require an Equalities Impact Assessment
Workforce Impact
12 There are no workforce impacts associated with this report
Legal Impact
13 The Council has to ensure that the premises meets all relevant legislative requirements Risk Management
14 There are no immediate risk management issues associated with this report
15 There is no requirement under the Constitution for external consultation on this item
Recommendation(s)
16 That the Committee identify the works that they wish to proceed with.
Reason for Proposed Decision(s)
17 To ensure that Margam Crematorium is able to continue to provide a high level of service
Implementation of Decision
18 For immediate implementation
List of Background Papers
19 None
Officer Contact
20 [name removed], Head of Property & Regeneration Tel: 01639 686371 or e-mail: [email protected] Appendix A Pictures of the new canopy. Example of a griselinia littoralis hedge.
Example of the finished path surface. Speakers installed for the AV system
Monitors installed for the AV system
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Building ProjectsReport | 940 KB | DownloadRead as text |
Follow Margam Crematorium Joint Committee at Neath Port Talbot and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Jun 2026 | Minutes of Previous MeetingThe minutes of the previous meeting, held on 12 January 2026, were agreed as an accurate record. Members highlighted ... | Agreed | Open |
| 24 Jun 2026 | Outturn Report and Annual Return 2025/26That the Outturn report for 2025/26, be approved. 2. That the Annual Return, prior to external audit certification, f... | Approved | Open |
| 24 Jun 2026 | Improved Memorial Keepsake ProvisionThat the report be noted. | Noted | Open |
| 12 Jan 2026 | Minutes of Previous MeetingThe minutes of the previous meeting, held on 7 October 2025, were agreed as an accurate record. | Agreed | Open |
| 12 Jan 2026 | Annual Budget Report - 2026/27Members noted a slight discrepancy within the report, and agreed to reword Resolution 3 as follows: That the precept ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.