Vehicle and Heavy Plant Fleet Procurement Programme 2019/20

Approved Executive 1 paper

Streetscene and Engineering Cabinet Board approved this item on Friday 22 February 2019. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

That the proposed Fleet Procurement Programme for 2019/20, as detailed in Appendix A of the circulated report, be approved. That the Fleet Procurement Programme for 2019/20, as detailed in Appendix A of the circulated report, be approved. Reason for The replacement vehicles and plant will have a higher euro standard which will enable the fleet to be more fuel efficient by producing better MPGs and reducing the carbon footprint of the Council by lower emissions. Integrated Transport has also undertaken a vehicle efficiency exercise to establish vehicle/plant usage within sections with the possibility of introducing full electric and Ultra Low Emission vehicles (ULEV) and plant into the fleet to further reduce carbon emissions emitted from Authority Fleet vehicles. This will be done in conjunction with future infrastructure improvements within the Authority and through partnership working with other Local Authorities and companies. The specifications are developed to accommodate the Authority’s Health and Safety requirements and will be discussed with user sections, manufacturers and health and safety section to ensure the correct vehicles are procured. Implementation of The decision will be implemented after the three day call in period.
Word for word from the decision Neath Port Talbot published for this meeting. Source: democracy.npt.gov.uk

Follow this further

Built from Neath Port Talbot's papers

What the report saysPro

Report to Streetscene and Engineering Cabinet Board

Purpose of report

1. To seek approval to procure new and replacement vehicles and heavy plant in 2019/20 as per the attached programme.

Executive summary

2. A replacement report has been prepared to replace vehicles/plant which has reached the end of their economic life cycle in line with the Authority’s renewals policy.

3. If agreed, vehicles/plant will be procured either by outright purchase or prudential loans and repaid by departments over the life of the vehicles/plant.

Background

4. The preparation of the Vehicle/Plant Fleet Replacement Programme for 2019/20 has been undertaken by the Council’s Fleet section in consultation with user Directorates/Sections, including a review of current vehicle condition, serviceability and environmental position.

5. Vehicles acquired by contract hire such as certain pool vehicles, are dealt with separately and are not included in this report.

6. The proposed programme is shown on the attached Appendix A. It is noted, however, that the Fleet Manager, in conjunction with the user Directorates, may opt to extend the working life of individual vehicles/plant once tenders are received where there are economic- advantages to be gained however careful consideration will be given to the environmental impact of high emitting carbon vehicles.

7. The means of financing the acquisition of each of the items listed will be either by outright purchase or prudential loan.

8. Outright purchase – Can be used to acquire new or preowned vehicles or items of plant. Items acquired by this means will involve monthly contributions to the Renewals Fund for a predetermined period of time prior to the section purchasing the required items.

9. Vehicles purchased from Grant funding will need to be budgeted for by the service area when a replacement vehicle is required.

10. Prudential loan – Can be used to acquire new or preowned vehicles or items of plant. Items required by this means will involve loan repayments for a predetermined period of time.

11. The financing costs of the vehicle acquisitions will be a charge on the relevant Directorate’s Operating account and the means of acquisition will be agreed between the Fleet Manager and user Directorate in each case.

12. Any vehicles purchased out of the Renewals Fund will get the residual value deducted from the total cost of the vehicle. The Fleet Manager will seek an estimated residual value which he expects to achieve at the end of the vehicles economical life or term. This has been agreed with finance and committed to achieve savings towards the FFP. The Fleet Manager will expect the vehicles to be returned at the end of the term in a reasonable condition to ensure the vehicle recovers the committed up front residual values. Any additional monies achieved at sale will help off-set any uplift costs of new vehicle purchases out of the renewals fund.

13. Vehicles Purchased via Prudential loans do not follow the above commitment for the residual values. Any monies achieved at auction will be given back to sections minus a disposal arrangement fee.

Financial Impact

14. As all of the vehicles are replacements to existing vehicles, a budget will already be in place to fund the costs of vehicles/plant purchased over the vehicles’ life, so there are no financial implications apart from natural vehicle price increase. Equality Impact Assessment

15. A Screening Assessment has been undertaken to assist the Council in discharging its Public Sector Equality Duty under the Equality Act 2010. After completing the assessment it has been determined that this proposal does not require an Equalities Impact Assessment

Workforce Impacts

16. There will be no workforce impacts.

Legal Impacts

17. There is no legal risk to the Authority.

Risk management

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Vehicle and Heavy Plant Fleet Procurement Programme 2019/20Report 361 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Neath Port Talbot

Search all
  1. Vehicle and Heavy Plant Fleet Procurement Programme 2019/20This decision
  2. Vehicle and Heavy Plant Fleet Procurement Programme 2024/25Approved
  3. Vehicle and Heavy Plant Fleet Procurement Programme 2023/24Approved
  4. Vehicle and Heavy Plant Fleet Procurement Programme 2021/2022Approved
  5. Vehicle and Heavy Plant Fleet Procurement Programme 2020-2021Approved

More from Neath Port Talbot Streetscene and Engineering Cabinet Board

All decisions
MeetingDecisionOutcome
28 Jan 2022 Appointment of ChairpersonAgreed that Councillor M.Harvey be appointed Chairperson for the meeting . Agreed Open
28 Jan 2022 Minutes of Previous MeetingThat the Minutes of 17 December 2021, be approved. Approved Open
28 Jan 2022 Traffic Regulation Orders - GlynneathHaving had due regard to the integrated impact assessment, approval be granted to advertise the B4242 Pontneathvaugha... Approved Open
28 Jan 2022 Traffic Regulation Orders – Tonna and AberdulaisHaving had due regard to the integrated impact assessment, the objections to the B4434 Dulais Fach Road, Station Road... Decided Open
28 Jan 2022 New Post Code for Bro Nantfer in Gwaun Cae GurwenHaving due regard to the first stage integrated impact assessment, residents of Bro Nantfer be consulted on whether t... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies