Resolved
That the progress and programming of the extension, chapel air conditioning, and ventilation to the chapel and cremation area, be noted.
Margam Crematorium Joint Committee noted this item on Friday 22 March 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
That the progress and programming of the extension, chapel air conditioning, and ventilation to the chapel and cremation area, be noted.
MARGAM CREMATORIUM - rev A - 12th March 2019 ID Task Task Name Duration Start Finish Predecessors Jul '18 Aug '18 Sep '18 Oct '18 Nov '18 Dec '18 Jan '19 Feb '19 Mar '19 Apr '19 May '19 Jun '19 Jul '19 Aug '19 Sep '19 Oct '19 Mode 250209162330061320270310172401081522290512192603101724310714212804111825041118250108152229061320270310172401081522290512192602091623300714 1 2018/2019 Margam Crem extension52 days Mon 24/09/18Tue 04/12/18 2018/2019 Margam Crem extension
2 RIBA 0 - Strategic Definition 1 wk Mon 24/09/18Fri 28/09/18 RIBA 0 - Strategic Definition
3 RIBA 1 - Preparation and Brief 1 wk Mon 01/10/18Fri 05/10/18 2 RIBA 1 - Preparation and Brief
4 RIBA 2 - Concept Design 2 wks Mon 08/10/18Fri 19/10/18 3 RIBA 2 - Concept Design
5 RIBA 3 - Developed Design 4 wks Mon 22/10/18Fri 16/11/18 4 RIBA 3 - Developed Design
6 CADW 13 wks Mon 07/01/19Fri 05/04/19 CADW
7 RIBA 4 - Detailed Design- Arch 52 days Mon 19/11/18Fri 08/02/19 5 RIBA 4 - Detailed Design- Arch
8 RIBA 4 - Detailed Design - M+E 35 days Mon 14/01/19Fri 01/03/19 7SS RIBA 4 - Detailed Design - M+E
9 RIBA 4 - QS Tender prep 4 wks Mon 11/02/19Fri 08/03/19 8SS+3 wks RIBA 4 - QS Tender prep
10 RIBA 4 - Tender period 5 wks Mon 11/03/19Fri 12/04/19 9 RIBA 4 - Tender period
11 RIBA 4 - Tender evaluation 2 wks Mon 15/04/19Fri 26/04/19 10 RIBA 4 - Tender evaluation
12 RIBA 5 - Mobilisation & (D+B 2 wks Mon Fri 10/05/19 11,6 RIBA 5 - Mobilisation & (D+B early design if applicable) early design if applicable) 29/04/19
13 RIBA 5 - Construction phase 20 wks Mon 13/05/19Fri 27/09/19 12 RIBA 5 - Construction phase
14 RIBA 6 - Handover and PC issued 0 days Fri 27/09/19 Fri 27/09/19 13 RIBA 6 - Handover and PC issued 27/09
16 M+E Ventilation - Option 2A 175 daysMon 07/01/19Fri 06/09/19 M+E Ventilation - Option 2A
17 Design 9 wks Mon 07/01/19Fri 08/03/19 Design
18 Tender negotiation and award 4 wks Mon Fri 05/04/19 17 Tender negotiation and award 11/03/19
19 Lead in 12 wks Mon 08/04/19Fri 28/06/19 18,6 Lead in
20 Construction 10 wks Mon 01/07/19Fri 06/09/19 19 Construction
Task Project Summary Inactive Milestone Manual Summary Rollup Deadline
Project: Margam Crem Programm Split External Tasks Inactive Summary Manual Summary Progress Date: Thu 14/03/19 Milestone External Milestone Manual Task Start-only Summary Inactive Task Duration-only Finish-only
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Architects ReportReport | 104 KB | DownloadRead as text |
PDF |
Building Improvements and MaintenanceReport | 54 KB | Download |
Follow Margam Crematorium Joint Committee at Neath Port Talbot and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Jun 2026 | Minutes of Previous MeetingThe minutes of the previous meeting, held on 12 January 2026, were agreed as an accurate record. Members highlighted ... | Agreed | Open |
| 24 Jun 2026 | Outturn Report and Annual Return 2025/26That the Outturn report for 2025/26, be approved. 2. That the Annual Return, prior to external audit certification, f... | Approved | Open |
| 24 Jun 2026 | Improved Memorial Keepsake ProvisionThat the report be noted. | Noted | Open |
| 12 Jan 2026 | Minutes of Previous MeetingThe minutes of the previous meeting, held on 7 October 2025, were agreed as an accurate record. | Agreed | Open |
| 12 Jan 2026 | Annual Budget Report - 2026/27Members noted a slight discrepancy within the report, and agreed to reword Resolution 3 as follows: That the precept ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.