Application to upgrade Footpaths No's 1 and 2 to a Public Bridleway, Community of Blaenhonddan

Refused Executive 5 papers

Regeneration and Sustainable Development Cabinet Board refused this item on Friday 12 April 2019. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

That no modification order be made as stated in Paragraph 4.2 of the circulated report, and the application to upgrade the public footpaths shown on Plan No. 1 to a public bridleway, be refused. That a No Modification Order be made as stated in Paragraph 4.2 of the circulated report, and the application be refused. Reasons for 1. At the previous public inquiry held in 1999 the appointed Inspector concluded there had been no dedication of a public bridleway by that date. 2. None of the evidence submitted in support of the current and outstanding 2017 application has established otherwise. 3. There has been no 20 years uninterrupted use since 1999 to satisfy the provisions of Section 31 of the Highways Act 1980. 4. No dedication under common law can be shown to have occurred since 1999. Implementation of Decision : The decision will be implemented after the three day call in period. Consultation: The item has been subject to extensive consultation.
Word for word from the decision Neath Port Talbot published for this meeting. Source: democracy.npt.gov.uk

Follow this further

Built from Neath Port Talbot's papers

What the report saysPro

Report to Regeneration and Sustainable Development Cabinet Board

Purpose of the report

To determine the application that has been made to upgrade the public footpaths shown on Plan No. 1 to a public bridleway.

Background

1.1The application being considered in this report is to upgrade footpath No’s 1 and 2 to a public bridleway. This application submitted by a local resident was made in 2017 is supported by 11 people who claim to have ridden this route for an average of 30 years. These supporters are therefore referred to as “claimants” in the report. It is the second time such an application has been made, the first having been reported to this Council’s predecessor Council, West Glamorgan County Council on the 26th October 1995.

1.2The earlier application was rejected but the applicant successfully appealed against that Council’s decision, which resulted in this Council being directed to make a Modification Order. As required, notice of that order was published and as a consequence, thirteen objections were made, which resulted in a public inquiry being held on 24th August 1999. On the 21st September 1999 the Inquiry’s Inspector refused to confirm the order, thus agreeing with that Council’s original conclusion. 1.3 There remains however, a continual duty on this Council under the Wildlife & Countryside Act 1981, to review the entries in the Definitive Map and Statement and to take account of any new evidence together with any considered previously. The relevant provisions of the Act are contained in Appendix 1. Therefore, this second application must be assessed in the light of the previous information submitted in respect of the first application and the reasons for the previous Inspector’s decision in 1999.

The Twenty Year Relevant Period

2.1As the evidence in support of this application is based on long term use, the provisions of Section 31 of the Highways Act 1980 also apply in determining the application and these can be found in Appendix 2. Consequently, the applicant must either establish (a) there has been a minimum period of 20 years uninterrupted use counting retrospectively from the date the alleged existence of the public bridleway was called into question or (b) 20 years use retrospectively from the date of the application, but in either case whichever is the earlier.

2.2In addition such a presumed dedication can only be inferred in the absence of any evidence that refutes the existence of such a right.

2.3The date of the application is 2017, but the evidence from the previous conclusions reached by the Inspector was that the existence of the alleged public bridleway was challenged by a former occupier of one of the nearby properties, No. 3 Cwm Cottage in 1993, some 25 years previously.

2.4The public inquiry was held in 1999 and so this earlier challenge and objection was sustained throughout this 6 year period (1993 – 1999).Consequently any use between these dates could not count toward the previous nor current application.

2.5No statutory declaration denying the existence of a public bridleway has been received since 1999 from any of the owners or occupiers of the land containing footpath No’s 1 and 2. Nonetheless the current five objectors who have a legal interest in the path would contend that no one has been able to ride along this path “uninterrupted nor as of right” from 1999. Background to the Earlier Application

3.1In order to properly assess the current application it should be viewed within the context of those facts that were established from the previous public inquiry.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Application to upgrade Footpaths No's 1 and 2 to a Public Bridleway, Community of BlaenhonddanReport 114 KB DownloadRead as text
PDF
Plan No. 3 for the reportReport 14 KB Download
PDF
Plan No. 4 for reportReport 429 KB Download
PDF
Plan No.1 for Draft ReportReport 42 KB Download
PDF
Plan No.2 for Draft ReportReport 208 KB Download

More from Neath Port Talbot Regeneration and Sustainable Development Cabinet Board

All decisions
MeetingDecisionOutcome
25 Feb 2022 Appointment of ChairpersonAgreed that Councillor A.Wingrave be appointed Chairperson for the meeting. Agreed Open
25 Feb 2022 Forward Work Programme 2021/22That the Forward Work Programme be noted. Noted Open
25 Feb 2022 Economic Recovery PlansHaving had due regard to the first stage of the Integrated Impact Assessment, adoption of the following documents, as... Approved Open
25 Feb 2022 South West Wales Regional Energy StrategyThe decision will be implemented after the three day call in period, which ends on Tuesday, 1 March 2022 at 9.00am. T... Decided Open
25 Feb 2022 Waterfall Country Park and Ride EvaluationHaving had due regard to the first stage Integrated Impact Assessment, Option 2, as detailed within the circulated re... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies