Traffic Order/s: St Pauls Road and Sunnybank Road, Port Talbot (Prohibition of Waiting, Loading and Unloading at any time)
DecidedExecutive4 papers
Streetscene and Engineering Cabinet Board decided this item on Friday 22 January 2021. Below is the council's own wording, with the papers it was decided on.
That the objection is upheld in part to the St Paul’s Road and Sunnybank Road, Port Talbot (Prohibition of Waiting, Loading and Unloading at Any time) traffic regulation order 2020 (as detailed in Appendix A of the circulated report) and the revised scheme (as detailed in Appendix B of the circulated report) be implemented on site and the objector informed accordingly. That the objection is upheld in part to the St Paul’s Road and Sunnybank Road, Port Talbot (Prohibition of Waiting, Loading and Unloading at Any time) traffic regulation order 2020 (as detailed in Appendix A of the circulated report) and the revised scheme (as detailed in Appendix B of the circulated report) be implemented on site and the objector informed accordingly. Reason for To prevent indiscriminate parking in the interest of highway safety. Implementation of The decision will be implemented after the three day call in period. Consultation: This item has been subject to external consultation.
Word for word from the decision Neath Port Talbot published for this meeting.Source: democracy.npt.gov.uk
Report to Streetscene and Engineering Cabinet Board
NEATH PORT-TALBOT COUNTY BOROUGH COUNCIL STREETSCENE AND ENGINEERING CABINET BOARD 22th JANUARY 2021
Report of Head of Engineering & Transport – D.W.Griffiths
Matter for Decision
Wards affected: Sandfields East
ST PAULS ROAD AND SUNNYBANK ROAD, PORT TALBOT (PROHIBITION OF WAITING, LOADING AND UNLOADING AT ANY TIME) traffic regulation order 2020.
Purpose of Report To consider the objections and comments received following the advertisement of the above scheme, as indicated in Appendix A.
Executive Summary The report outlines the comments received and the recommendations for the scheme.
Background The proposed scheme is required to prevent indiscriminate parking on the junction of St Paul’s Road and Sunnybank Road in the interest of road safety and to protect school children attending the adjacent Tywyn Primary School.
Financial Impact The work will be funded by the Capital Works Programme. Integrated Impact Assessment A first stage impact assessment has been undertaken to assist the Council in discharging its legislative duties (under the Equality Act 2010, the Welsh Language Standards (No.1) Regulations 2015, the Well-being of Future Generations (Wales) Act 2015 and the Environment (Wales) Act 2016. The first stage assessment, attached at Appendix C, has indicated that a more in-depth assessment is not required. A summary is included below:- A full impact assessment is not required as the proposed traffic regulation order will provide a safe environment for motorists, pedestrians, cyclists, school children and residents.
Valleys Community Impacts There are ‘No implications’ associated with this report.
Workforce Impacts There are ‘No Implications’ associated with this report.
Legal Impacts The scheme was advertised for a 21-day period as part of the statutory process.
Risk Management Impacts There are no risk management impacts associated with this report.
Consultation A consultation exercise was undertaken in December 2020 with approximately 30 properties receiving hand delivered letters with a plan. Only one objection was received. The objection has been discussed with the local Councillors whom support reducing the length of the proposed traffic regulation order adjacent to Nos 57 and 59 Sunnybank Road. The revised scheme is as indicated in Appendix B.
Recommendations It is recommended that the objection is upheld in part to the St Paul’s Road and Sunnybank Road, Port Talbot (Prohibition of Waiting, Loading and Unloading at Any time) traffic regulation order 2020 (as detailed in Appendix A to the circulated report ) and the revised scheme ( as detailed in Appendix B to the circulated report ) be implemented on site. The objector to be informed of the decision accordingly.
Reason for Proposed Decision To prevent indiscriminate parking in the interest of highway safety.
Implementation of Decision: The decision is proposed for implementation after the three day call in period.
Appendices Appendix A – Original Plan – Sunnybank Road – St Paul’s Road, Sandfields, Port Talbot Appendix B – Revised Plan – Sunnybank Road – St Paul’s Road, Sandfields, Port Talbot Appendix C – Integrated Impact Assessment.
Follow Streetscene and Engineering Cabinet Board at Neath Port Talbot and we tell you when its next papers are published, before the meeting rather than after it.
Traffic Regulation Orders - GlynneathHaving had due regard to the integrated impact assessment, approval be granted to advertise the B4242 Pontneathvaugha...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.