That approval be granted for a Modification Order made under Section 53 of the Wildlife and Countryside Act 1981 to register the path shown A – B on plan No. 1 and of no objections are received to confirm the same as an unopposed order. That approval be granted for a Modification Order made under Section 53 of the Wildlife and Countryside Act 1981 to register the path shown A – B on plan No. 1 and of no objections are received to confirm the same as an unopposed order. Reason for There is sufficient evidence that the footbridge has been subject to a period of uninterrupted use for a minimum period of 20 years. This satisfies the provisions of section 31 of the Highways Act 1980 which presumes the way has been dedicated as a highway to the public. Implementation of The decisions will be implemented after the three day call in period.
Word for word from the decision Neath Port Talbot published for this meeting.Source: democracy.npt.gov.uk
Report to Regeneration and Sustainable Development Cabinet Board
Purpose of the report
1.1To determine an application for a footpath Modification Order to recognise the public’s right to use a footbridge over the railway in the centre of Seven Sisters marked A – B on the attached plan No. 1.
Executive summary
2.1The Board is under a duty to make a decision by the impartial analysis of the evidence before it. The report considers the legal tests that have to be applied before looking at the evidence in support of the claim, as well as any other contrary evidence. Additional information is provided as to why the public say they use the footbridge in the appendices and reasons given as to why it is recommended a modification order should be made.
Background
3.1The application has been supported by 23 people who allege an average of 48 yeas use of the bridge, 16 of whom claim to have used this bridge for a minimum of 30 years.
3.2The footbridge is owned by Network Rail who have temporarily closed the bridge due to safety concerns for the public. Network Rail have stated they ‘understand this to be a private crossing without rights to the public but with the obligation to the railway as its provision under the deed’. The deed referred to was made in 1986 between the Neath and Brecon Railway Company and Neath Rural District Council and Others.
3.3Network Rail have indicated that they intend to refurbish the bridge rather than remove it, although there is no indication as to when this would occur.
3.4The bridge has been included in the Schedule of Buildings of Local Importance dated April 2019, as part of the Local Development Plan 2011 – 2026. It is listed under the section on the Dulais Valley but this in itself does not afford the bridge any legal status or protection for the purposes of the application.
The Law:
4.1An application is based on the provision of Section 31 of the Highways Act 1980, which presumes the owner of the land or in this case; the structure, has been dedicated to the public due for a minimum of 20 years uninterrupted use. In addition, it is alleged that there is no evidence of any contrary intention during that period to dedicate the way as a public one. The relevant extract of Section 31 is shown in Appendix 1.
4.2The twenty year period referred to above is calculated by either:
(a) Establishing the date when the path was first obstructed which has the effect of calling into question the existence of the alleged public right or:-
(b) The date of the application itself.
Of the two possible dates, it will be the earlier which is taken to represent the end of the twenty year period.
In this example, the application was made on the 19th July 2019, and the closure of the bridge occurred earlier the same year, consequently, the relevant twenty year period is 1999 – 2019.
4.3Under common law, it is possible to infer a public path has been dedicated whether that use is more or less than a period of twenty years. However, there needs to be evidence of a positive expression by the owners that they have dedicated the way, rather than a lack of any contrary evidence.
4.4Section 53 of the Wildlife and Countryside Act 1981, places an obligation on this Council to consider any evidence that shows a public path exists. Section 53 is shown in Appendix 2. The Council needs to be satisfied that the evidence is sufficient and if so, should make a modification order which has the effect of amending the Council’s record of its public paths, namely the Definitive Map and Statement.
4.5The basis for making a modification order is established by the application of the following tests: (a) That this Council is satisfied that a public right of way exists on the balance of probabilities.
(b) Or that this Council can be satisfied that it is reasonable to allege a public right of way exists
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Regeneration and Sustainable Development Cabinet Board at Neath Port Talbot and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.