Resolved
That the report be noted.
Environment, Regeneration and Streetscene Services Cabinet Board noted this item on Friday 12 January 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted.
To provide Members with an update on the progress of work relating to the Regional Transport Plan (RTP), with a focus on the Implementation Plan that has recently been submitted to Welsh Government by the Corporate Joint Committee (CJC).
This report is for information only in order to provide Members with an overview of the duties of the Corporate Joint Committee in developing a Regional Transport Plan for South West Wales. The initial stage of producing the RTP required the CJC to submit a RTP – Implementation Plan to the Welsh Government, by 31st October 2023. A copy of the Implementation Plan is shown in Appendix 1.
The Corporate Joint Committee (CJC) for South West Wales has been mandated to produce a Regional Transport Plan (RTP) for the region by Welsh Government, in conformity with the Transport (Wales) Act (2006) and to complement Llwybr Newydd: Wales Transport Strategy (2022).
The region was tasked with producing an Implementation Plan setting out how the Regional Transport Plan (RTP) will be developed and adopted. This implementation plan was submitted to Welsh Government by their deadline of the 31st October 2023. The Implementation Plan is shown in Appendix 1.
Prior to submitting the Implementation Plan to Welsh Government, the Plan was considered and endorsed by the CJC Regional Transport Sub Committee at its meeting on the 9th October 2023. The overarching aims of the Regional Transport Sub Committee is to drive an accessible, sustainable and efficient transport system across the region; and they have the function to make recommendations to the Corporate Joint Committee on the development and delivery of the Regional Transport Plan.
In addition to endorsing the Implementation Pan, the Sub Committee agreed that a covering letter be sent to the Minister to deal with the risks highlighted in the plan. The letter is shown in Appendix 2.
Following the meeting of the CJC Regional Transport Sub Committee, the Implementation Plan and covering letter was presented and approved by the CJC on 24th October 2023, and have subsequently been submitted to the Welsh Government by the deadline of 31st October 2023. The RTP Guidance issued by Welsh Government set out the key requirements in order to develop the South West Wales RTP, these are listed below. Each requirement has a number of actions and work packages that need to be undertaken, further details on these can be found in the Implementation Plan attached as Appendix 1 of the circulated report.
Development of the RTP Implementation Plan
Development of the Case for Change
Development of the Initial Draft of the Regional Transport Plan, Integrated Well-Being Assessment (IWBA) and Regional Transport Delivery Plan (RTDP)Development of the Final Draft of the Regional Transport Plan, Integrated Well-Being Assessment (IWBA) and Regional Transport Delivery Plan (RTDP)
Development of the Final Regional Transport Plan, Integrated Well-Being Assessment (IWBA) and Regional Transport Delivery Plan (RTDP)
Public and Stakeholder Consultation Monitoring and Evaluation Plan
Equalities Impact Assessment
Environmental Impact Assessment and Habitats Regulation Assessment.
The RTP Guidance issued by Welsh Government also set out the key dates in producing the RTP, these are shown in the table below. These dates are extremely ambitious given the volume of work required to produce the RTP, and there is a lack of funding and resources available; this was recognised by the CJC Regional Transport Sub Committee and the Corporate Joint Committee. Key dates in producing the RTP
13th July 2023 Guidance issued to CJC's
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
DWG Appendix 1: RTP Implementation Plan: SW WalesAppendix | 1.3 MB | Download |
PDF |
DWG Appendix 2: Letter to Deputy Minister RTP: October 2023Appendix | 640 KB | Download |
PDF |
Regional Transport Plan: Update from South West Wales Corporate Joint CommitteeReport | 346 KB | DownloadRead as text |
Follow Environment, Regeneration and Streetscene Services Cabinet Board at Neath Port Talbot and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Apr 2024 | Appointment of ChairpersonAgreed that Councillor S.Jones be appointed as Chairperson for the meeting. | Agreed | Open |
| 19 Apr 2024 | Shared Prosperity Funded (SPF) Business Anchor Project - Enhance Business Support for Growth and Innovation - UpdateThat the report be noted. | Noted | Open |
| 19 Apr 2024 | South West Wales Corporate Joint Committee - Regional Transport Plan - Case for Change - UpdateThat the report be noted. | Noted | Open |
| 19 Apr 2024 | Neath Port Talbot Local Area Energy PlanThat the report be noted. | Noted | Open |
| 19 Apr 2024 | Traffic Regulation Order - B4603 Ynysmeudwy Road and Clos Nant Ddu Pontardawe (Prohibition of Waiting, Loading or Unloading at any time) and (Speed Cushions) Order 2024That having had due regard to the integrated impact assessment: · That the objections be upheld in part to the B4603 ... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.