Resolved
AGREED that the report be noted.
Audit & Accounts Committee Previous agreed this item on Wednesday 24 April 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
AGREED that the report be noted.
1.1To provide an update to members on the Council’s Risk Management arrangements and status of the Council’s Strategic Risks.
2.0Background Information - Risk Management
2.1The Risk Management Group continues to meet on a quarterly basis. Members of this group are provided with an overview of the current situation/performance of strategic and operational risks. Emerging/ongoing risks are also discussed.
2.2The Risk Management Policy is currently under review. It is envisaged that this policy will be submitted to SLT for approval in April 2019.
2.3An audit of the Council’s Risk Management arrangements, undertaken last year by Assurance Lincolnshire, has identified a substantial level of confidence in service delivery, management of risks and operation of controls and/or performance.
2.4A small number of improvements were noted as part of this audit and it is envisaged that all outstanding actions will be completed by July 2019.
2.5Operational risks identified as red are monitored and reported to SLT as part of the wider assurance arrangements.
2.6Following the restructure, meetings are being held with new business units and existing units with new operations, to identify and develop their operational risks.
2.7Further assistance will be provided to Business Managers in reviewing and developing their operational risks once business plans have been approved.
2.8Projects have the potential to expose the Council to numerous risks. It is therefore essential that they are managed by competent project leads that have a good understanding of how to manage risk. A series of sessions have recently been delivered around Project Management which includes a section on risk covering identification, management, mitigation and control.
3.0Strategic Risks
3.1Strategic risks are those that have the potential to halt or interfere with the Council’s ability to achieve its priorities and/or deliver its statutory duties.
3.2A workshop involving members of SLT is held annually to agree risks that are strategic in nature for the forthcoming year. When reviewing risks consideration is
1 given to how the whole organisation is positioned to deliver its objectives having regard to internal/external factors, some of which are out of the Council’s control e.g. economic downturn.
3.3Individual action plans are produced for all strategic risks as a means of controlling/mitigating the risk to a level that is acceptable (i.e. target risk) from SLT’s perspective. Action plans are reviewed quarterly and recorded/managed within pentana.
3.4The next annual strategic risk review workshop will be undertaken during the summer of 2019. Existing strategic risks will be reviewed by SLT at this workshop to determine if they remain appropriate and, if so, agree new risk scores. In circumstances where risks are no longer deemed appropriate from a strategic perspective they will either be closed (if appropriate) or re-classified as operational (if appropriate). Consideration will also be given to the addition of new/emerging risks arising as a result of internal/external factors e.g. adoption of the Council’s Community Plan.
3.5A quarterly assurance report regarding risk management is provided to SLT for their consideration/information. This report provides an overview of the risks, outstanding actions and areas of concern.
3.6Ownership of each risk is assigned to a relevant director(s) who have, with the assistance of Business Managers, developed action plans to manage, mitigate or reduce the risk accordingly. However, as the very nature of strategic risks are complex and influenced by many outside factors/controls, some actions can be very long term and the ability to reduce the risk level may be limited. Having risks that are either shown as high risk or above target risk level does not necessarily mean that the Council is not actively managing the risk.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
A&A RM report mar 19 Appendix 1Appendix | 463 KB | Download |
PDF |
Risk Management reportReport | 359 KB | DownloadRead as text |
Follow Audit & Accounts Committee Previous at Newark and Sherwood and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Apr 2022 | Minutes of the meeting held on 2 February 2022AGREED that the Minutes of the meeting held on 2 February 2022 be approved as a correct record and signed by the Chai... | Agreed | Open |
| 27 Apr 2022 | Update on the Strategic Risk Management Process and RegisterAGREED (unanimously) that: a) the Committee noted the amendments to the Strategic Risk Register; and b) the Committee... | Agreed | Open |
| 27 Apr 2022 | Internal Audit Progress ReportAGREED (unanimously) that: a) the Committee considered the latest internal audit progress report; and b) the Committe... | Agreed | Open |
| 27 Apr 2022 | Combined Assurance ReportAGREED (unanimously) that the Committee considered the Combined Assurance report. | Agreed | Open |
| 27 Apr 2022 | Annual Internal Audit PlanAGREED (unanimously) that the Audit & Accounts Committee approved the Internal Audit Plan. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.