Resolved
AGREED (unanimously) that the report be noted.
Homes & Communities Committee agreed this item on Monday 10 June 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
AGREED (unanimously) that the report be noted.
1.1To update Members on the outcome of a Warm Homes Fund (WHF) bid and revised project delivery arrangements following the Committees support for the scheme.
2.0Background Information
2.1Further to Committees approval of a report presented on 14 January 2019, a Warm Homes Fund bid was submitted to Affordable Warmth Solutions in February 2019 to attract funding from Cadent’s Affordable Warmth programme in addition to Energy Company Obligation (ECO) grant funding to support new gas connections and first time central heating systems to approximately 100 fuel poor private sector dwellings on Vera Crescent and Bevan Close, Rainworth. The vast majority of these homes are currently electrically heated via old storage/panel heaters which are notoriously inflexible and expensive to run when compared to gas central heating.
2.2Affordable Warmth Solutions (AWS) is an independent Community Interest Company (CIC) that works in partnership with Cadent (Gas Network Operator) to meet the challenges of fuel poverty and energy efficient homes. Working with Local Authorities and Energy Companies they are committed to funding new gas connections to some of the most deprived communities in England.
2.3The Energy Company Obligation (ECO) is a Government energy efficiency scheme in England that aims to help tackle fuel poverty and reduce carbon emissions and is delivered through energy suppliers and their agents. The current phase (ECO 3) runs from 2018-2022.
3.0Bid Outcome
3.1Whilst the grant funding provider (AWS) was very impressed by the Council’s bid and keen to support it, the required grant funding per installation was too high for them to be able to support the project.
3.2AWS suggested that, as an alternative route to delivering the same outcome for residents, the Council get in touch with AgilityEco. AgilityEco is managing a large Warm Homes Fund scheme across a number of council areas in England, on behalf of the lead council partner, Portsmouth City Council (PCC). The outcome of these conversations is that PCC have agreed for part of their funding to be used for the project.
3.3The attached Memo (APPENDIX A) from Agility Eco outlines the outcome of this bid and the revised delivery arrangements. The offer to residents/tenants will remain fully- funded (valued at circa £6K per property). 4.0 Anticipated Benefits/Risks
4.1The primary driver behind the new delivery model is to reduce costs to the WHF by removing/reducing duplication of effort and creating greater economies of scale. However, this model also significantly reduces the risks to the Council (e.g. by negating the need for a legally-binding contract with AWS) and lowers our costs as, for example, it will no longer be necessary to procure a heating contractor. In addition, quarterly reports/financial claims will no longer be the responsibility of NSDC as this task will be undertaken by Agility Eco, together with the end of project evaluation report.
4.2The Council’s involvement reduces to more of a communication/co-ordination role which can be fulfilled using existing staff and resources.
5.0Next Steps
5.1Following approval to proceed by the Council’s Senior Leadership Team on 30 April 2019, a data sharing agreement and Memorandum of understanding is being put in place. The existing risk register is being revised to reflect the changes in delivery and a communications and project plan is being developed.
5.2Residents have been informed of the good news by letter (attached at APPENDIX B)
6.1The scheme outlined in this report targets residents living in, or at risk of, fuel poverty. A full Equalities Impact Assessment will now be carried out for this scheme in order to consider the relevant protected characteristics.
7.0Financial Services Business Manager Comments – FIN18-19/4209
7.1The proposed scheme outlined in this report will be delivered within existing budgets.
That the Committee note the contents of this report.
Nil
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Warm Homes Fund: Successful BidReport | 753 KB | DownloadRead as text |
Follow Homes & Communities Committee at Newark and Sherwood and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Jan 2022 | Minutes of meeting held on 22 November 2021AGREED (unanimously) that the Minutes of the meeting held on 22 November 2021 be approved as a correct record and sig... | Agreed | Open |
| 24 Jan 2022 | Update on Antisocial Behaviour and Interventions and EnforcementAGREED (unanimously) that the Committee noted the data relating to Anti-Social Behaviour and the range of activities,... | Agreed | Open |
| 24 Jan 2022 | Housing Ombudsman Complaint Handling - Self AssessmentAGREED (unanimously) that: a) Members noted the progress and continued compliance against the self-assessment. b) Mem... | Agreed | Open |
| 24 Jan 2022 | Reasonable Adjustment Policy for Customers ReportAGREED (unanimously) that Members of the Committee supported the Reasonable Adjustment for Customers Policy and recom... | Agreed | Open |
| 24 Jan 2022 | Dealing with Unreasonable Behaviour and Vexatious Complaints PolicyAGREED (unanimously) that Members of the Committee supported the revised Dealing with Unreasonable Behaviour and Vexa... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.