Resolved
AGREED approval of the Combined Assurance report.
Audit & Accounts Committee Previous agreed this item on Wednesday 5 February 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
AGREED approval of the Combined Assurance report.
Combined Assurance Status Report 2019/20
Newark and Sherwood District Council February 2020 Contents Overview of Assurance Page 1
Chief Executive's Summary Page 2
Link to Community Plan Page 3
Strategic Risk Page 4
Director's Key Messages Page 6 Communities and Environment Growth and Regeneration Governance and Organisational Development Resources and Deputy Chief Executive ICT Key Projects
The contacts at Assurance Lincolnshire are: Lucy Pledge CMIIA, QIAL
Audit and Risk Manager (Head of Internal Audit)
01522 553692
Emma Bee CMIIA
Audit Manager
[email protected] Overview of Assurance
Combined assurance is a structured means of identifying and mapping the main sources and types of assurance in the council and coordinating them to best effect.
It enhances risk management by providing an effective and efficient framework of sufficient, regular and reliable evidence of assurance on organisational stewardship and management of major risks to the Council’s success.
We do this using the 3 lines of defence model.
Overall Assurance Direction of travel
Red Amber Green No Down from Change Up from 32% 56% to 51% 0% 44%
High impact on resources, Medium or short term impact Monitor and be aware, activity significant costs likely, high on resources, costs covered to mitigate risk within existing impact on service delivery. within existing financial plans, service delivery plans. low impact on service delivery.
1 Combined Assurance Status Report 2019/20 Chief Executive's Summary
Newark and Sherwood District Council has an ambitious agenda to improve the quality of life for its local community.
The new Community Plan sets out a clear direction of travel and contains a significant number of high profile and in some cases, highly complex initiatives. The ‘insourcing’ of housing management, the Joint Venture development of a new Travel Lodge, major capital investment at the Dukeries Leisure Centre and the comprehensive regeneration of the Yorke Drive estate are just a selection of examples of priority schemes that not only reflect the Council’s ambition but also entail significant risks that need to be effectively managed.
While the Council’s overall assurance status remains positive, I consider that the increase in the ‘amber rating’ is appropriate, having regard to not only the Council’s forward plan of action but also the increasing variety and complexity in our operating and governance arrangements. I am, nevertheless, satisfied that we are not only aware of our key risks but have measures are in place to mitigate and manage these.
2 Combined Assurance Status Report 2019/20 Link to Community Plan Objectives The Council updated their Community Plan in February 2019. As part of the assurance process the activities and projects have been mapped against each of the 11 Objective for 2019 – 2023.
0% 20% 40% 60% 80% 100% Red Amber Green Unknown
3 Combined Assurance Status Report 2019/20 Strategic Risks Good risk management is part of the way we work. It is about taking the right risks when making decisions or where we need to encourage innovation in times of major change – balancing risk, quality, cost and affordability.
This put us in a stronger position to deliver our goals and provide excellent services.
Our Strategic Risk Register is regularly reviewed and our risks are being effectively managed.
Level of Risk Risk rating management Management Assurance
Currently approved MTFP through Council. Budget SR101 Financial monitoring reported to SLT and Committee quarterly. sustainability - Amber Controlled External influences mean this risk is difficult to mitigate General Fund fully. Current HRA FBP shows this is currently sustainable, SR102 Financial which has been updated for changes in CPI rate and Control sustainability - HRA Amber future development schemes. The HRA BP is due to be Pending updated, which will be completed post the transfer of NSH
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Combined Assurance Report: FinalReport | 1.3 MB | DownloadRead as text |
PDF |
Combined Assurance ReportReport | 220 KB | Download |
Follow Audit & Accounts Committee Previous at Newark and Sherwood and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Apr 2022 | Minutes of the meeting held on 2 February 2022AGREED that the Minutes of the meeting held on 2 February 2022 be approved as a correct record and signed by the Chai... | Agreed | Open |
| 27 Apr 2022 | Update on the Strategic Risk Management Process and RegisterAGREED (unanimously) that: a) the Committee noted the amendments to the Strategic Risk Register; and b) the Committee... | Agreed | Open |
| 27 Apr 2022 | Internal Audit Progress ReportAGREED (unanimously) that: a) the Committee considered the latest internal audit progress report; and b) the Committe... | Agreed | Open |
| 27 Apr 2022 | Combined Assurance ReportAGREED (unanimously) that the Committee considered the Combined Assurance report. | Agreed | Open |
| 27 Apr 2022 | Annual Internal Audit PlanAGREED (unanimously) that the Audit & Accounts Committee approved the Internal Audit Plan. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.