AGREED (unanimously) that (a) Fernwood Village Hall be transferred to Fernwood Parish Council under asset transfer powers as detailed in the Council’s Asset Transfer - Corporate Principles Policy; and (b) the Director – Communities & Environment be given delegated authority to progress the transfer. Reason for Decision To ensure that corporate principles are followed to guide the consideration of the transfer of community assets.
Word for word from the decision Newark and Sherwood published for this meeting.Source: democracy.newark-sherwooddc.gov.uk
1.1To seek Policy & Finance Committee’s approval to transfer Fernwood Village Hall to Fernwood Parish Council under Asset Transfer Powers as detailed in the Council’s Asset Transfer - Corporate Principles Policy.
2.0Background Information
2.1Cabinet considered and approved an Asset Transfer Policy – Corporate Principles in December 2008 in order to guide any future considerations regarding the transfer of community assets. This Policy ensures that the Council is able to consistently consider requests or recommendations for the transfer of assets whilst also being able to treat each case individually so that the Council was able to fulfil its strategic priorities.
2.2Since the adoption of the Policy the Council has exercised its powers and successfully transferred Edwinstowe Village Hall and Coddington Community Centre to respective Parish Councils and Millgate Community Centre to the Newark and Sherwood Play Support Group, a registered charity, for a nominal consideration in each case. However, each transfer has appropriate provisions within the legal documentation to protect the Council’s interest in terms of capital assets.
2.3Fernwood Parish Council was granted a 40 year lease by the District Council in 2008 and has managed the village hall as per the terms of the lease exceptionally well throughout its tenure. In the last 12 months the Parish Council has improved the sustainability of the hall by improving the heating system and introducing photo-voltaic cells to the roof to reduce energy consumption and improve the buildings green credentials.
2.4The hall is an important part of the Fernwood community and serves as a focal point and hub facility for a wide range of community-focussed activities, which meet the needs of the local community.
2.5Accordingly Fernwood Parish Council has now formally approached the District Council to request the transfer of the freehold interest in the building following resolution at its Full Council meeting on 16th September 2019.
3.0Proposals
3.1That Fernwood Village Hall be transferred to Fernwood Parish Council under Asset Transfer Powers as detailed in the Council’s Asset Transfer - Corporate Principles Policy.
Equalities implications
4.1Fernwood Parish Council is governed by the same equality law as the District Council therefore will be required to ensure compliance with the regulatory obligations. This would include the production of an Equality Policy Statement as a pre requisite of the transfer.
4.2Under the transfer the Parish Council will covenant with the District Council as deemed necessary and appropriate to ensure that the asset continues to serve the community of Fernwood and its environs as is currently the practice in accordance with the Equality Act.
4.3The village hall is currently deemed to be compliant with Equality Act’s disability requirements and will be maintained as such by the Parish Council.
5.0Financial Implications (FIN19-20/4081)
5.1There is no provision in the revenue budget for works to Fernwood Village Hall, therefore there are no direct revenue implications to transferring this asset to the Parish Council.
5.2The asset is held on the Council’s asset register with a 2019/20 brought forward balance of £752,518, the valuation basis is depreciated replacement cost which therefore does not necessarily represent a transactional market value. The asset is subject to depreciation up to the date of transfer and would then need to be disposed, off the Council’s asset register.
6.0Community Plan – Alignment to Objectives
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Programme 2022/23 to 2025/26AGREED (unanimously) that the General Fund schemes set out at Appendix A to the report, and the Housing Services sche...
Newark Castle - Condition SurveyAGREED (unanimously) that: (a) the inclusion of this work in the 2022/23 Capital Programme for £570,000 be approved, ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.