CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Newark and Sherwood District Council
Policy & Finance Committee, Thursday 2 April 2020 at 2.00pm

Footpath and Access Realignment and Levelling at Epperstone Manor

Agreed Finance 1 paper

Policy & Finance Committee agreed this item on Thursday 2 April 2020. Below is the council's own wording, with the papers it was decided on.

Item99

Resolved

AGREED (unanimously) to recommend to the Chief Executive that: (a) the Business Manager - Legal Services ask Epperstone Developments Limited’s solicitor to enter into a land swap in respect of the land detailed at paragraph 2.4 of the report [shown with red marker/red hatched area in Figure 2] and that completion be concluded as soon as is practicable; (b) delegated authority be given to Director – Growth & Regeneration to commission contractors to install a fence along an appropriate route, having regard to ownership issues as set out in the report presented to the Committee and confirmation from the Business Manager - Legal Services that such issues have been legally resolved to mitigate risk to the Council; (c) a budget of up to £12,212 + VAT be set up in 2020/21 to cover the cost of the works to implement (b) above; and (d) authorisation be granted to the Business Manager - Legal Services to recover all such reasonable costs from the developer. Reason for Decision To enable the future transfer of the land and footpath to Epperstone Parish Council and to ensure that the community can continue to use the footpath and recreational land.
Word for word from the decision Newark and Sherwood published for this meeting. Source: democracy.newark-sherwooddc.gov.uk

Follow this further

Built from Newark and Sherwood's papers

What the report saysPro

Report to Policy & Finance Committee

Purpose of report

1.1To update Members on progress in securing the transfer of ‘Recreational’ land and a footpath from a developer to the Council (and in turn to Epperstone Parish Council) following a previous breach of a legal planning obligation under S106 of the Town and Country Planning Act 1990.

1.2To seek approval of additional funds to relocate fencing erected by the developer erroneously on land outside of their control.

2.0Background Information

2.1In December 2008, planning permission (application no 08/01841/FULM) was approved for the construction of twelve new dwellings with access road on land South West of Epperstone Manor. This development is complete and known as West Manor Park. The site was subject of a S106 Agreement dated 23 December 2008 and included the following obligations:

 an obligation to transfer an area of Recreational Land of 1.913 hectares to the Council (including a post and rail fence along the north boundary of the field);  an obligation to the construct a footpath in a location and to a specification agreed by the Council (including a maintenance strip), and to transfer the footpath to the Council.  an obligation to maintain a right of access adjacent to the footpath

2.2The transfer (as amended through a Deed of Partial Release under Sections 106 and 106A of the Town and Country Planning Act 1990) of the Recreational Land and footpath to the District Council was completed and registered on 3 August 2018. The only matter which appeared to be outstanding at this time related to the provision of the post and rail fence along the northern boundary of the Recreational Land. The area of Recreational Land including location of the post and rail fence and footpath route (including maintenance strip) are illustrated in Figure 1 below. Post and rail fence

Figure 1: Extract of plan in transfer Deed which shows existing route of path on the OS Base, the proposed route in red and the maintenance strip in blue.

2.3It was soon realised that the metal estate fencing erected to demarcate the footpath (shown red above) was 1) on land which did not match the land registry ownership boundary for the developer and 2) did not match exactly the approved line of the footpath. The correct route was pegged out in May 2019 by the Council. The ownership position is demonstrated below: Figure 2: Extract from Land Registry Plan showing current Council ownership in green, land in neighbours ownership in yellow and EDL land subject of land swap in red hatched area.

2.4The red hatched area above has very recently been registered as within the ownership of the developer (EDL). The developer will be advised that it is in their interests for this land to be transferred to the Council under the terms of the S106 and land transfer agreements previously signed. This will be requested on the basis that there are no physical works for the developer to do. The footpath and fencing is already installed and this is simply a matter of a land transfer.

2.5There remains an issue with respect to the yellow land in that this is technically within the registered ownership of a neighbouring dwelling. The owner has made clear that they wish the fence and footpath to be relocated.

2.6The Council has sought to pursue the developer to relocate the footpath in order to match 1) the approved position and 2) the ownership. This has included an offer by the Council to instruct contractors to do the works, with the developer then covering the costs. Despite attempts there remains no progress.

2.7The Council have been informed of an unresolved legal ownership dispute between the neighbouring owner and EDL in relation to a triangular section of land marked by a star in Figure 3. Despite this, legal advice on this matter states that the Council is entitled to erect a fence on the land within its ownership, and could do that at any time.

3.0Proposals

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Footpath and Access Realignment and Levelling at Epperstone ManorReport 578 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 12 attended
DL
Councillor David LloydChairman, present
KG
Councillor Keith GirlingVice-Chair, present
BC
Councillor Brendan Clarke-SmithCommittee Member, present
RJ
Councillor Roger JacksonCommittee Member, present
PP
Councillor Paul PeacockCommittee Member, present
TW
Councillor Timothy WendelsCommittee Member, present
MR
Councillor Miss Ronnie WhiteCommittee Member, present
JR
John RobinsonCouncil Staff, expected
NH
Nigel HillOfficer, expected
MF
Matt FinchOfficer, expected
SK
Sanjiv KohliOfficer, expected
KW
Karen WhiteOfficer, expected

More from Newark and Sherwood Policy & Finance Committee

All decisions
MeetingDecisionOutcome
21 Feb 2022 Pay Policy Statement 2022/23AGREED (unanimously) that the Pay Policy Statement 2022/2023 be recommended for approval by the Full Council at their... Agreed Open
21 Feb 2022 2022/23 Proposed General Fund Revenue BudgetAGREED (unanimously) that the Committee recommends to Full Council at its meeting on 8 March 2022 that: (a) the follo... Agreed Open
21 Feb 2022 2022/23 to 2025/26 Medium Term Financial PlanAGREED (unanimously) that the Committee recommends the 2022/23 to 2025/26 Medium Term Financial Plan (MTFP) for appro... Agreed Open
21 Feb 2022 Capital Programme 2022/23 to 2025/26AGREED (unanimously) that the General Fund schemes set out at Appendix A to the report, and the Housing Services sche... Agreed Open
21 Feb 2022 Newark Castle - Condition SurveyAGREED (unanimously) that: (a) the inclusion of this work in the 2022/23 Capital Programme for £570,000 be approved, ... Agreed Open