AGREED (unanimously) that the progress made in the development of Environmental Services be noted. Reason for Decision To ensure Members are informed on the progress made to deliver the improvement required to ensure delivery of the Community Plans’ objectives.
Word for word from the decision Newark and Sherwood published for this meeting.Source: democracy.newark-sherwooddc.gov.uk
1.1To update Members in respect of the project to realign and invest in Environmental Services. This project commenced in September 2019 and the project aimed to realign and refocus the service towards effective delivery of the Community Plan.
2.0Background Information
2.1Environmental Services within the scope of the development outlined in this report include: Street Cleansing; Refuse & Recycling; Transport; and Parks & Grounds Maintenance. These services now sit within one unit enabling synergies across the functions however these services report into different Committees – namely: cleansing, waste and transport to Leisure & Environment and parks and grounds maintenance to Economic Development. This report will provide an overview of the work done within the project.
2.2The Environment Strategy was due to be presented to Committee alongside this report however due to the dramatic impact of the pandemic this strategy needs to be reviewed and realigned. This Strategy will cover the period 2020-2023 and summarise the strategic direction for refuse, recycling and green spaces. The standard lifespan for a strategy is five years however this strategy has a shorter lifespan in reflection of the currently altering national picture. The purpose of this three year strategy is to deliver the Community Plan objectives and prepare the service for the changes coming so that the service will be on a solid foundation in 2023 ready to grow and to deliver nationally mandated change.
2.3The project was expected to close in May 2020 however Environmental Services have had to redirect their primary focus to keeping essential services running through the Covid-19 crisis. This has meant that some project work streams have been scaled back and others paused in recognition of the changing local and national picture.
2.4This report summarises the work done and that planned, for the development of this service and highlights where Covid-19 has impacted project outputs. This report will set the scene for the service area and lays the foundation for the Environmental Services Strategy, which will set the vision for the service that is due to be presented to Committee later this year.
3.0Proposals
3.1The project’s aim was to develop the services within Environmental Services to a secure foundation through realignment and investment to enable the service to be ready to deliver the objectives outlined in the Community Plan. The project is still ongoing however the majority of the activity undertaken to develop and improve the services has been completed. These activities have been undertaken across the service and this report will review the work undertaken underneath each of the five ‘delivery arms’ within the newly formed environmental services; Restructure
3.2Firstly, the project undertook a service wide restructure to create the five delivery arms within Environmental Services. The aim of the restructure was to realign resource to strengthen street scene functions, improve succession planning and separate commercial services and service delivery to increase income generation and provide a better service for our residents and customers. The restructure was approved at JCC on 18 October 2019, consultation took place and the restructure commenced November 2019. The Environmental Services Business Manager is in place as are the Waste & Transport and Street Scene Managers. At the time of this report, it is expected the complete structure will be in place by September 2020.
Refuse & Recycling
3.3The main focus for the refuse and recycling delivery arm has been creating efficiencies and realigning services to reflect best practice. This included;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Programme 2022/23 to 2025/26AGREED (unanimously) that the General Fund schemes set out at Appendix A to the report, and the Housing Services sche...
Newark Castle - Condition SurveyAGREED (unanimously) that: (a) the inclusion of this work in the 2022/23 Capital Programme for £570,000 be approved, ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.