Resolved
AGREED (unanimously) that: a) the Audit and Accounts Committee considered and commented upon the latest Internal Audit Progress report and approved the extensions to the implementation dates.
Audit & Accounts Committee Previous agreed this item on Wednesday 30 September 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
AGREED (unanimously) that: a) the Audit and Accounts Committee considered and commented upon the latest Internal Audit Progress report and approved the extensions to the implementation dates.
Internal Audit Progress Report
Image Courtesy of the Official UK Puzzle Club
Newark and Sherwood District Council September 2020
For all your assurance needs Contents Key Messages Page 2 Introduction Summary Assurances
Internal Audit work completed Page 3 Overview of Assurances Audit Reports at Draft Work in Progress Performance
Other Matters of Interest Page 9
Cabinet Office Public Sector risk update
Appendices Page 10 1 Assurance Definitions & recommendation ranking 2 Details of Overdue Actions 3 Outstanding Actions for Limited Reports 4 Internal Audit Plan 2020/21 – Progress to Date 5 Audits with Limited or Low Assurance
Lucy Pledge - Head of Internal Audit & Emma Bee – Audit Team Leader Risk Management [email protected] [email protected]
Amanda Hunt – Principal [email protected]
This report has been prepared solely for the use of Members and Management of Newark and Sherwood District Council. Details may be made available to specified external organisations, including external auditors, but otherwise the report should not be used or referred to in whole or in part without prior consent. No responsibility to any third party is accepted as the report has not been prepared, and is not intended for any other purpose.
The matters raised in this report are only those that came to our attention during the course of our work – there may be weaknesses in governance, risk management and the system of internal control that we are not aware of because they did not form part of our work programme, were excluded from the scope of individual audit engagements or were not bought to our attention. The opinion is based solely the work undertaken as part of the agreed internal audit plan. Introduction The purpose of this report is to:
• Provide details of the audit work during the period 1st April 2020 to 30 June 2020 • Advise on progress of the 2020/21 plan • Raise any other matters that may be relevant to the Audit Committee role
Key Messages The onset of Covid-19 and subsequent lockdown has had a significant impact on all areas of the public sector. Operationally, the Council has had to react quickly to rapidly 1 HIGH changing circumstances. This has had an impact on the pace ASSURANCE of progression for some of our audits, however we continue to work closely with the Council in order to finalise audit work.
Given the current situation, we have worked closely with management to ascertain what work could be completed during Quarter 1 and rescheduling of those audits postponed 8 SUBSTANTIAL at the end of 2019/20. We are currently in the process of ASSURANCE reviewing our resources and the logistics around the delivery of the remainder of the plan.
During the period we have completed 12 assurance audits and have 10 audits currently in progress with 3 of these at draft report stage. 3 LIMITED Those which have been completed are:- ASSURANCE • Follow-ups 2019/20 – High • Project and Programme Management - Substantial • • • Procurement - Substantial NNDR – Substantial Land Charges – Substantial 0 • Performance – Substantial LOW • Enforcement - Substantial ASSURANCE • ICT Patch Management and Change Control – Substantial • Key Controls – • Financial Regulations, Bank, Tax & VAT, Absence Management and Equality & Diversity – Substantial • Health and Safety - Limited 2 • Building Control - Limited OTHER • ICT Incident Management - Limited
Note: The assurance expressed is at the time of issue of the report but before the full 2 implementation of the agreed management action plan. The definitions for each level are shown in Appendix 1. Introduction We have also completed the review of the Mansfield Crematorium Accounts and the Newark Livestock market Rent calculation.
Further details of our progress can be found within the body of the report and in Appendix 4.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
07A 0AA: Audit and Accounts 30-09-20: Internal Audit Progress ReportReport | 1.2 MB | DownloadRead as text |
PDF |
Internal Audit Progress ReportReport | 236 KB | Download |
Follow Audit & Accounts Committee Previous at Newark and Sherwood and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Apr 2022 | Minutes of the meeting held on 2 February 2022AGREED that the Minutes of the meeting held on 2 February 2022 be approved as a correct record and signed by the Chai... | Agreed | Open |
| 27 Apr 2022 | Update on the Strategic Risk Management Process and RegisterAGREED (unanimously) that: a) the Committee noted the amendments to the Strategic Risk Register; and b) the Committee... | Agreed | Open |
| 27 Apr 2022 | Internal Audit Progress ReportAGREED (unanimously) that: a) the Committee considered the latest internal audit progress report; and b) the Committe... | Agreed | Open |
| 27 Apr 2022 | Combined Assurance ReportAGREED (unanimously) that the Committee considered the Combined Assurance report. | Agreed | Open |
| 27 Apr 2022 | Annual Internal Audit PlanAGREED (unanimously) that the Audit & Accounts Committee approved the Internal Audit Plan. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.