Resolved
AGREED (unanimously) that: (a) the project update be noted.
Homes & Communities Committee agreed this item on Monday 13 September 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
AGREED (unanimously) that: (a) the project update be noted.
1.1To provide Members with an update on the progress of the Midlands Energy Hub (MEH) Local Authority Delivery 2 (LAD 2) Grant Funding Project to provide major energy efficiency improvement measures to 73 homes on low incomes.
2.0Background Information
2.1The Council confirmed its participation and acceptance of the government grant of £724,850 on 15 April 2021, to enable approximately 73 (20 social homes owned by the Council and 53 private sector homes) low income households in poorly insulated homes to benefit from either solid wall insulation or installation of solar photovoltaic panels.
2.2Prior to accepting the grant allocation for this project verbal approval for the scheme was given by the following Councillors in principle:
• David Lloyd (Leader – Conservative) • Paul Peacock (Labour – Leader of the opposition) • Tim Wendels (Conservative – Chair Homes & Communities) • Kathleen Arnold (Labour).
2.3Approval for contract procedure rules exemption was verbally approved by the Section 151 Officer first and then the SLT on 19 May 2021 due to the tight deadlines for acceptance of the grant.
2.4Initially NCDS were not going to bid for grant as we did not have the resources to deliver the programme. However, discussions with two neighbouring authorities (Gedling and Rushcliffe) raised the prospect of working in partnership with EON to deliver our programme. Following initial discussions with EON a proposal was drawn up and submitted for approval by SLT before being lodged with the MEH on 24 May 2021.
2.5Two target areas have been established for the measure as the Council's top ranking wards in terms of % of households living in fuel poverty. These are Bilsthorpe and Boughton.
3.0Update
3.1On 25 June 2021 approval was received from MEH that our proposal had been accepted and the first grant element of £2,750 was released.
3.2The Council also received £72,485 on 23 July 2021 for administration and mobilisation of the project.
3.3So far, the Council has identified 35 homes, 20 Council-owned homes and 15 privately owned homes. The 20 Council-owned homes will receive the solar panel measures, subject to receiving the tenant’s agreement. A letter is being sent to these tenants as the first communication, explaining the scheme and encouraging participation. In addition the first flyer has gone out to owner-occupiers and we have already received interest from 7 residents. An income assessment will then be made to ensure applicants’ incomes are below the threshold of £30,000 per household required under the grant funding.
3.4On 20 August 2021, we received confirmation from MEH that the Department for Business, Energy & Industrial Strategy have extended the deadline for completion of works from 31 December 2021 to 31 March 2022. This is most welcome given the initial delay in realising funds for administration and mobilisation.
4.1There are no direct equalities implications arising from this report. Any proposed changes to operations and any consequential impact upon tenants and staff will need to be considered in terms of any possible negative impacts upon people with protected characteristics, but none are envisaged at present.
5.0Digital Implications
5.1None
6.0Financial Implications (FIN21-22/1879)
6.1The urgency item approved in April 2021 included approvals to changes to the budget as follows: • £84,148.28 of the grant be initially added to the HRA Capital Investment Programme to support the current budget of £150,000 making £234,148.28 available for the works to the 20 Council Dwellings. • A general fund Capital budget be set up for £578,175.57 for the works to the privately owned properties via EON (which would be passed to EON under the contractual arrangement for this scheme). • The remaining part of the £724,850 grant (of £62,526.15) as it stands £5,073.99 is unlikely to be required, and £57,452.16 be set up in revenue for managing and administering the programme.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MEH LAD 2 Grant Funding Project: UpdateReport | 260 KB | DownloadRead as text |
Follow Homes & Communities Committee at Newark and Sherwood and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Jan 2022 | Minutes of meeting held on 22 November 2021AGREED (unanimously) that the Minutes of the meeting held on 22 November 2021 be approved as a correct record and sig... | Agreed | Open |
| 24 Jan 2022 | Update on Antisocial Behaviour and Interventions and EnforcementAGREED (unanimously) that the Committee noted the data relating to Anti-Social Behaviour and the range of activities,... | Agreed | Open |
| 24 Jan 2022 | Housing Ombudsman Complaint Handling - Self AssessmentAGREED (unanimously) that: a) Members noted the progress and continued compliance against the self-assessment. b) Mem... | Agreed | Open |
| 24 Jan 2022 | Reasonable Adjustment Policy for Customers ReportAGREED (unanimously) that Members of the Committee supported the Reasonable Adjustment for Customers Policy and recom... | Agreed | Open |
| 24 Jan 2022 | Dealing with Unreasonable Behaviour and Vexatious Complaints PolicyAGREED (unanimously) that Members of the Committee supported the revised Dealing with Unreasonable Behaviour and Vexa... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.