AGREED (unanimously) that: (a) the contents of the report be noted; (b) the Policy & Finance Committee be recommended to give delegated authority to the Director – Planning & Growth (in consultation with the Assistant Director – Legal & Democratic Services) to enter into a Grant Agreement with Urban&Civic for up to £20m of LUF Grant and up to £5.019m of NSDC grant (inclusive of any grant already committed), subject to: a) any requirements of the LUF grant being met and b) full delivery of the Newark Southern Link Road.
Word for word from the decision Newark and Sherwood published for this meeting.Source: democracy.newark-sherwooddc.gov.uk
1.1To provide Members with an update on progress of funding and delivery of major highways schemes across the district, including:
Newark Southern Link Road A1 Overbridge at Fernwood Major Road Network Fund – A614 junctions/Ollerton Roundabout A46 Newark Northern Bypass
2.0Background Information
2.1Members will be aware that addressing issues of: congestion; connectivity; sustainable transport and an ability of employers and residents to access sites; services and move more freely across the highway network is one of the key priorities linked to achieving our Community Plan and Sustainable Growth aspirations.
Newark Southern Link Road (SLR)
2.2Delivery of the SLR is critical to the Place Making ambitions around the Middlebeck Sustainable Urban Extension. Full SLR delivery will further reduce congestion, accelerate housing delivery, unlock employment land, and advance the delivery of the county parks, sports facilities, and associated community uses. It will also, if delivered in a timely manner, provide a part traffic management solution for Newark as part of the A46 Newark Northern Bypass scheme, which it is hoped will commence in March 2025.
2.3At the Policy & Finance Committee on 25 June 2020, Members agreed unanimously to commit an overall capital contribution from this Council of £5,000,000 towards the delivery of the SLR, with delegated authority given to the Director – Planning & Growth, in consultation with the Business Manager – Legal Services, to enter into an agreement with master developer Urban & Civic.
2.4The rationale for doing so was to demonstrate further commitment towards the delivery of the full SLR, offering additional match funding which could be leverage alongside a Newark Levelling Up Fund (LUF) bid to close the remaining funding gap to allow accelerated construction of the road. The LUF bid was submitted jointly with colleagues from Nottinghamshire County Council and Urban & Civic on 18 June 2021.
2.5In the Autumn Budget on 27 October 2021 we received confirmation that the LUF bid was successful for the full £20m ask. It is now necessary to move at pace to accelerate the final design and delivery of the whole road given the LUF requirement for defrayal of grant to commence in 2022/22 and be fully spent by March 2024. This will involve working closely with National Highways (formerly Highways England), D2N2 (a grant funder alongside NSDC), Homes England (a loan funder), and Nottinghamshire County Council. In the case of the latter additional support and contributions will be sought. It remains the expectation that the SLR will be delivered in c2 years from now. 2.6 The table below updates funding sources for the SLR, as set out in the LUF bid (exc. adoption costs and fees):
2.7In accordance with the resolutions detailed at the June 2021 meeting the Council and Urban & Civic will shortly conclude a grant agreement to complete the remaining technical approval update works for the A1 and A46 junctions.
A1 Overbridge, Fernwood
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Economic Development Committee at Newark and Sherwood and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.