1.1To provide an update to members on the status of the Council’s 2021/22 Strategic Risk Register.
2.0Background Information - Risk Management
2.1Risk management is the management of business risk in a manner consistent with the virtues of economy, efficiency and effectiveness. In essence it is about making the most of opportunities, making the right decisions and about achieving objectives once those decisions are made. This is achieved through:
Identifying risk Controlling and managing risks Transferring risks (including insurance) Living with risks
2.2A certain amount of risk taking is both inevitable and essential if the council is to achieve its objectives. The council recognises that the way it manages the many risks facing it contributes towards the successful implementation and achievement of its objectives/priorities.
3.0Risk Management Performance
3.1The strategic risk register is reviewed annually to ensure it remains relevant and effective.
An annual strategic risk workshop was held with SLT in late November 2020 with formal approval achieved in February 2021. During this workshop the following actions were undertaken:
Annual review of the strategic risk register Full overview of the last audit report actions Evaluation of the risk review process Evaluation and determination regarding management of project risks Evaluation and determination of corporate risk maturity and appetite
3.2Following approval a draft strategic risk register was produced, subsequently adopted and commenced operation in April 2021.
3.3Performance of all strategic risks continue to be reported to the Senior Leadership Team (SLT) quarterly via the Transformation team’s assurance reporting system. This includes identification of failing or “red” risks. 3.4 The corporate Risk Management Group also continues to meet on a quarterly basis to review risk management performance. Members of this group are provided with an overview of the current status and performance of strategic and operational risks. In addition members of the group raise and discuss new and/or emerging risks.
3.5A full review of the risk management policy, associated guidance document and processes has been completed. These documents have been shared with members of the Risk Management Group. After consultation with the Risk Management Group the updated documents will be shared and approved by SLT prior to implementation.
4.0Strategic Risks
4.1Strategic risks are those that have the potential to halt or interfere with the Council’s ability to achieve its priorities and/or deliver its statutory duties.
4.2As detailed in 3.1 a risk workshop, involving members of SLT, was undertaken to agree risks that are strategic in nature for the forthcoming year. When reviewing strategic risks, consideration is given to how the whole organisation is positioned to deliver its objectives having regard to internal/external factors, some of which are out of the Council’s control e.g. economic downturn.
4.3The current risk register has 14 strategic risks. These are listed in the table below.
Strategic Risk Register – 2021/22 Title Description Owner(s) SR101 Ensuring financial sustainability of the general fund Sanjiv Kohli Financial to allow the council to undertake its core functions, sustainability – deliver services, meet its corporate priorities and General Fund objectives
SR102 Financial sustainability of the HRA to ensure the Sanjiv Kohli Financial council is able to provide, maintain and develop its Suzanne Shead sustainability - housing stock. HRA SR103 Maintaining corporate safeguarding arrangements Matthew Finch Safeguarding to ensure suitable and appropriate management of the councils safeguarding duties.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Risk ManagementReport | 1 MB | DownloadRead as text |
Follow Audit & Accounts Committee Previous at Newark and Sherwood and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Apr 2022 | Minutes of the meeting held on 2 February 2022AGREED that the Minutes of the meeting held on 2 February 2022 be approved as a correct record and signed by the Chai... | Agreed | Open |
| 27 Apr 2022 | Update on the Strategic Risk Management Process and RegisterAGREED (unanimously) that: a) the Committee noted the amendments to the Strategic Risk Register; and b) the Committee... | Agreed | Open |
| 27 Apr 2022 | Internal Audit Progress ReportAGREED (unanimously) that: a) the Committee considered the latest internal audit progress report; and b) the Committe... | Agreed | Open |
| 27 Apr 2022 | Combined Assurance ReportAGREED (unanimously) that the Committee considered the Combined Assurance report. | Agreed | Open |
| 27 Apr 2022 | Annual Internal Audit PlanAGREED (unanimously) that the Audit & Accounts Committee approved the Internal Audit Plan. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.