AGREED (unanimously) that: a) the Committee noted the General Fund projected favourable outturn variance of £ 0m; b) the Committee noted the Housing Revenue Account projected favourable outturn variance of £0.117m to the Major Repairs Reserve; c) the Committee note the Capital Programme revised budget and financing of £53.759m; and d) the Committee noted the Prudential indicators at Appendix A.
Word for word from the decision Newark and Sherwood published for this meeting.Source: democracy.newark-sherwooddc.gov.uk
Report to: Audit & Accounts Committee Meeting 22 April 2026 Director Lead: Sanjiv Kohli Deputy Chief Executive / Director – Resources - Section 151 Officer Lead Officer: Nick Wilson, Business Manager Financial Services on ext 5317
Report Summary Projected General Fund and Housing Revenue Account Report Title Revenue and Capital Outturn Report to 31 March 2026 as at 31 December 2025 To update Members with the forecast outturn position for the 2025/26 financial year for the Council’s General Fund and Housing Revenue Account revenue and capital budgets. Purpose of Report To show performance against the approved estimates of revenue expenditure and income. That Committee: (a) note the General Fund projected favourable outturn variance of £0m; (b) note the Housing Revenue Account projected favourable Recommendations outturn variance of £0.117m to the Major Repairs Reserve;
(c) note the Capital Programme revised budget and financing of £53.759m; and
(d) note the Prudential indicators at Appendix A.
Alternative Options Not applicable. Considered
To consider the forecast outturn position for the 2025/26 financial year for the Council’s General Fund and Housing Reason for Revenue Account revenue and capital budgets. Recommendations Ensure the Council has overall financial sustainability for the current financial year compared to the budgeted position. 1.0 Background
Overview of General Fund Revenue Projected Outturn for 2025/26
1.1Table 1 shows a projected favourable variance against the revised budget of £0.385m on Service budgets, with an overall favourable variance of £0m that would need to be transferred to the General Fund reserve. This is based on meetings which took place with Business Managers during January, whereby they have analysed actual income and expenditure to 31 December 2025 and forecasted forward to the end of March 2026 the additional income and expenditure currently expected to be incurred.
Table 1: General Fund revenue outturn for 2025/26 financial year as at 31 December 2025
Original Revised Projected Variance Budget Budget Outturn £'m £’m £'m £'m Net Cost of Services 20.722 21.341 20.956 (0.385) Other Operating Expenditure 5.120 5.063 5.062 (0.001) Finance & Investment Income/Expenditure (1.572) (1.572) (1.728) (0.156) Taxation & Non-Specific Grant Income (25.230) (25.251) (25.775) (0.524) Net Cost of Non-Service (21.682) (21.760) (22.441) (0.681) Net Cost of Council Expenditure (0.960) (0.419) (1.485) (1.066) Transfer to/(from) Usable Reserves 0.316 (1.110) 0.001 1.111 Transfer to/(from) Unusable Reserves 0.644 1.529 1.484 (0.045) Transfer to/(from) General Reserves 0 0 0 0
1.2While the current overall favourable variance of £0m is a non-impact for the Councils resources, it is only a forecast, therefore the Outturn Report in June 2026 will finalise the variance and the allocation of that variance into the Councils General Reserves.
Overview of Projected Housing Revenue Account (HRA) Outturn for 2025/26
1.3With reference to the ‘Variance’ column in Table 2, the HRA accounts show a projected unfavourable variance on the Net Cost of HRA Services against the revised budget of £0.237m and an increased transfer to the Major Repairs Reserve of £0.117m: Table 2: HRA revenue outturn for 2025/26 financial year as at 31 December 2025
Original Revised Projected Variance Budget Budget Outturn £'m £’m £'m £'m Net Cost of HRA Services (6.366) (5.667) (5.430) 0.237 Other Operating Expenditure 0.013 0.013 0.011 (0.002) Finance & Investment Income/Expenditure 4.243 4.243 3.891 (0.352) Taxation & Non-Specific Grant Income 0 0 0 0 (Surplus)/Deficit on HRA Services (2.109) (1.411) (1.528) (0.117) Movements in Reserves Transfer to/(from) Usable Reserves (0.263) (0.961) (0.961) 0 Transfer to/(from) Unusable Reserves (6.245) (6.245) (6.245) 0 Transfer to/(from) Major Repairs Reserve 8.617 8.617 8.734 0.117 Total 0 0 0 0
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.