(a) That the comments from the Overview and Scrutiny Co-ordinating Committee be received and that the Committee be thanked for its views. (b) That Members reaffirm the Cabinet decision made on 15 th June 2011 with the additional recommendations as follows: · That the Council commits to undertaking a public consultation process supported by any preferred purchaser prior to the submission of any planning application for development of the subject land. · That any marketing particulars clarify: o The Council’s expectation of compliance with the current policy regarding the provision of affordable housing and; o The potential for inclusion of a convenience store. · That the outcome of any public consultation process be reported back to Cabinet as part of any final report to dispose of the subject land.
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
To report back to Cabinet the outcome of the scrutiny review process and to seek a decision on how to proceed in this matter.
Recommendations
(a) To receive the comments from the Co-ordinating Overview and Scrutiny Committee and to thank them for their views.
(b) That members reaffirm the Cabinet decision made on 15 June 2011 with the additional recommendations as follows:
• That the Council commits to undertaking a public consultation process supported by any preferred purchaser prior to the submission of any planning application for development of the subject land.
• That any marketing particulars clarify: (i) the Council’s expectation of compliance with the current policy regarding the provision of affordable housing and; (ii) the potential for inclusion of a convenience store.
• That the outcome of any public consultation process be reported back to Cabinet as part of any final report to dispose of the subject land.
Reasons
To enable Cabinet to respond to the views arising from the Scrutiny call-in process and to make a final decision in this matter so that progress can be made to secure a comprehensive redevelopment programme for this surplus site.
Background
1.1Cabinet resolved, at its meeting on 15 June 2011 to dispose of the Knutton Recreation Centre site. In particular the following resolutions were made:-
(a) That officers be authorised to take the necessary steps, in consultation with the relevant Portfolio Holder, to dispose of the Knutton Recreation Centre site for redevelopment as soon as practically possible after the new Jubilee 2 centre is completed.
(b) That the redevelopment of this site should be primarily housing-led with provision also made for a replacement bowling green and pavilion and the potential for a small convenience store.
1 (c) That, in principle, the existing ‘3G’ football pitch should be retained and options for its future local/community-led management arrangements be explored (including the bowling green), the outcome of which would be reported to Members.
(d) That consideration be given to the inclusion of adjoining land in the Council’s ownership in order to optimise the prospects of securing a comprehensive redevelopment scheme.
(e) That officers be authorised to engage suitably qualified specialist advisors to prepare both marketing particulars for sale of the subject land and a planning brief (reflecting the Council’s ambitions for comprehensive redevelopment of the site).
1.2The above decision was called in for review by the Council’s scrutiny process on the following two grounds:-
(a) The local residents are unhappy with a decision to remove the recreation centre without consultation following Renews demise, the regeneration programme for Knutton is in doubt.
(b) The revenue budgets, contrary to the report, are not needed for running Jubilee 2.
1.3The Co-ordinating Overview and Scrutiny Committee scoped the call-in at its meeting on 26 July 2011 and identified the following by lines of enquiry:-
(a) What is the current position regarding the regeneration programme for Knutton following the demise of RENEW?
(b) How have local residents been consulted over the decision to remove the recreation centre?
(c) What impact does the disposal of the site have on the council’s revenue budget, specifically in relation to the running of Jubilee 2?
(d) What will be the impact on Knutton and its residents e.g. What facilities are and will be available for residents at the college and the fire station
(e) Is executive housing what is really needed in this area?
1.4The Co-ordinating Overview and Scrutiny Committee reviewed the call-in at its meeting on 19 September 2011 and resolved:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Local government reorganisation update(i) That the content of the letter from the Minister for Devolution received on 7 th September 2026, reviewing decisi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.