(a) That the progress in delivery of the ‘Jubilee 2’ centre be noted, including the public opening event on 7 January 2012. (b) That Enger -G be commissioned to undertake the maintenance of the combined heat and power unit installed at the Jubilee 2 centre initially for a 1 year period at a fee of £5,658 without seeking alternative quotations and that the Council’s Standing orders and Financial Regulations (as per Section 2a( i ) and 2b(vii) be waived for the reasons identified in section 2.5 of this report.
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
To provide Members with information about progress relating to the Jubilee 2 since your last meeting.
Recommendations
(a) That the progress in delivery of the ‘Jubilee 2’ centre is noted, including the public opening event on 7 January 2012.
(b) To commission Enger-G to undertake the maintenance of the Combined Heat and Power unit installed at the Jubilee 2 centre initially for a 1 year period at a fee of £5,658 without seeking alternative quotations and waive the Council’s Standing orders and financial regulations (as per Section 2a(i) and 2b(vii) for the reasons identified in section 2.5 of this report.
Reasons
To facilitate the decision-making and delivery processes regarding the provision of the Jubilee 2 centre for the residents of the Borough and achieve the Council’s aspirations of delivering the project before the end of 2011.
Background
1.1On 11 October 2011 Cabinet noted the progress made on Jubilee 2. Given the significance of the project Members requested that a monthly update report should be provided to Cabinet and this is the latest of such reports.
2. Issues/Progress Update
2.1The capital build of Jubilee 2 is now over ninety percent complete, with the contractor entering into their fifty eighth week on site out a contractual period of sixty two weeks.
2.2The programme for completion of the building remains in line with the Council’s aspirations of opening Jubilee 2 to the general public in January 2012, with the anticipated capital cost of the project remaining within the budget envelope of £10.5 million.
2.3As part of Morgan Sindall’s obligations to the Council, they continue to monitor the use of local labour on site. In this regard your Officers are pleased to report that in the last month, 58 percent of labour has come from within a thirty minute drive time of the site.
2.4By the time of your meeting the building should have been substantially completed. Since your last meeting the following items of significant work have been undertaken as part of the construction process: • The dimensions of the main pool have been verified by the ASA as being in compliance with current guidelines. This will enable officers to register the pool as a short course competition venue. • The installations of the climbing wall, boulder area and traverse climbing wall have now been completed. • The pool filtration system has been installed. • The Technogym Fitness Equipment and Wellness system will have been installed by the time of your meeting. • The installation of the public art work on the Brunswick Street facade has commenced. • A number of tenders have been received for the maintenance of the Mechanical and Electrical plant. It is envisaged that an appointment will be made by the middle of December 2011. • The commissioning of the mechanical and electrical equipment and pool filtration system has commenced and should be complete by the time of your meeting. • The highways works are now completed on Brunswick Street and Hanover Street, and work has now commenced on School Street.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Local government reorganisation update(i) That the content of the letter from the Minister for Devolution received on 7 th September 2026, reviewing decisi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.