Resolved
- That the report be received.
Public Protection Committee decided this item on Monday 23 January 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
- That the report be received.
The purpose of this report is to disseminate the results of the environmental site investigation carried out at Chorlton Moss Tip, Staffordshire during September 2010 under Part IIa of the Environmental Protection Act 1990. The work forms part of an ongoing programme of investigations which are taking place on former landfills sites within the Borough of Newcastle under Lyme. All Local Authorities have a responsibility to investigate sites in their area and further information, including the contaminated land inspection strategy and the approach to investigating potentially contaminated sites, can be found on the Newcastle under Lyme Borough Council website: (www.newcastle-staffs.gov.uk/contaminatedland).
To advise that the risks posed to human health, livestock, controlled waters and buildings/services are considered to be within acceptable limits and further investigative or remedial works will not be required.
That the report be received and that the information is disseminated to the Parish Council (site owner).
1.1The Borough Council has a statutory duty placed upon it under Part IIA the Environmental Protection Act 1990 to identify whether any land in its area is contaminated. The Council has undertaken a strategic approach to the identification of land which merits detailed individual attention and has formulated a Contaminated Land Strategy to help fulfil its statutory duty. This looks at past land uses, the current land uses and geology and considers the contamination present on in or under the land and its impacts upon receptors.
1.2Chorlton Moss Tip was identified as being located within the top ten sites requiring further investigation by the Borough Council to allow quantification of the nature of risk to receptors. This site was operated by Newcastle Urban District Council between 1967 and 1974 when ownership transferred to Newcastle-under-Lyme Borough Council who operated the site from 1974 until the surrender of the site licence in 1981.
1.3The phase 1 desk study completed by the Borough Council detailed the known site history, the nature of the materials deposited in the former landfill, the pollutant linkages which may exist and ultimately how sensitive receptors might be affected. A visual walkover also identified that the clay cap which overlies the landfill had been breached by cattle grazing on the site and that this had caused household waste materials to be present at the surface. It was also considered that the damaged cap may also be allowing water to enter the site. There was also evidence that potentially contaminated soils have been moved around the site or may extend beyond the boundaries of the former land filled quarry.
1.4At this stage, it was not possible to be precise about the risks posed by this site in respect of the following:- • its impact on the underlying aquifer caused by leachate generated by the ingress of water and decomposition of waste and any liquid wastes which may be present within the site, • risk posed to buildings, structures, voids and persons therein both on and off the site by landfill gases generated by the natural decomposition of the deposited wastes • mobilisation of contaminants into the surface soils where they may be ingested by animals, or find there way into the food chain.
1.5These issues required further detailed investigation by the Borough Council to help inform how the site was impacting its surroundings. As such, Newcastle under Lyme Borough Council successfully bid for DEFRA (the Department for Environment, Food and Rural Affairs) Capital Funding to investigate the potential environmental risks posed by the site and invited a number of reputable environmental consultancies to quote to undertake the works on our behalf as an independent third party. The contract was subsequently awarded to Mouchel who undertook the investigative works during September 2010.
2. Findings
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Chorlton Moss Landfill Site WorksReport | 45 KB | DownloadRead as text |
Follow Public Protection Committee at Newcastle-under-Lyme and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Apr 2018 | Minutes of Previous MeetingThat the minutes of the meeting held on 13 March, 2018 be agreed as a correct record. | Agreed | Open |
| 23 Apr 2018 | Disclosure of Exempt InformationResolved :- That the public be excluded from the meeting during consideration if the following matter because it is l... | Decided | Open |
| 23 Apr 2018 | Resolved:APPEAL OUTCOME MR ABDUL HAKIM BAIGThat the report be received. | Decided | Open |
| 23 Apr 2018 | Appeal outcome mr mohammed sajjad miahThat the report be received. | Decided | Open |
| 13 Mar 2018 | Disclosure of Exempt InformationResolved :- That the public be excluded from the meeting during consideration of the following matters because it is ... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.