(a) That the information contained within the report be received. (b) That Cabinet convey its thanks to all partners involved in delivering this project, particularly those who contributed funding. Members specifically wished to thank North Staffs NHS Trust, Sport England, the Amateur Swimming Association, The Contractors, Robert Foster and Andy Arnott.
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
To provide Members with information about progress relating to the capital build of the Jubilee 2 centre since you considered a report at your December meeting.
Recommendations
(a)_ That Cabinet receive the information contained within this report.
(b) That Cabinet conveys its thanks to all partners involved in delivering this project, particularly those who contributed funding.
Reasons:
(i) To facilitate the decision-making and delivery processes regarding the provision of the Jubilee 2 health and wellbeing centre for the residents of the Borough. (ii) To ensure that the good practices adopted throughout the delivery of Jubilee 2 and the lessons learned are taken into account for the future projects that the Council may wish to undertake.
Background
1.1In the spring/summer of 2008 Cabinet authorised officers to develop the brief for a new Health and Wellbeing Centre (now known as Jubilee 2) to meet the healthy and active lifestyle needs of the Borough’s residents. At that stage the “preferred facility mix” included a 25m eight lane swimming pool, a training pool, eighty station fitness suite, two dance studios, health suite (including sauna and steam room), cafeteria, and other ancillary space including changing rooms, plant rooms; no specific requirement was made for sustainable energy solutions in the building.
1.2Your officers sought specialist advice to determine the likely footprint of the building and the broad cost envelope for the project which was determined to be 4,000sqm and £14 million respectively. It should be noted that Cabinet acknowledged the potential requirement for additional “desirable facilities” including a moveable floor in the competition pool & training pool, an additional 20 stations in the fitness suite, and a climbing wall. None of the latter facilities were factored into either the original footprint for the building or the broad cost envelope for the project.
1.3The brief for Jubilee 2 was developed throughout 2009 in consultation with key stakeholders including NHS North Staffordshire, Sport England, and the Amateur Swimming Association, the Carbon Trust, the users of Jubilee Pool & Knutton Recreation Centre and the wider community. As a result of this ongoing consultation Officers worked closely with the design team and professional advisors to incorporate the above-mentioned desirable facilities into the design for Jubilee 2, resulting in an increase in the footprint of the building to 4,300sqm. 1.4 Given the Council’s strategic responsibility to reduce its carbon footprint a robust options appraisal of the available sustainable energy solutions was undertaken by the Council’s professional advisors. This resulted in the following items being incorporated into the design for Jubilee 2: a combined heat a power unit; L.E.D lighting; photovoltaic cells; waterless urinals; heat recovery systems and; automated (PIR) lighting systems.
1.5Throughout the design phase the cost plan for Jubilee 2 was continually refreshed to take account of the fluctuating market conditions, the availability of external funding and the design requirements of the building. This resulted in a revised broad cost envelope being established for the Jubilee 2 of £12.2million prior to freezing the main elements of the building design in the autumn of 2009 and submitting a Planning Application for the Council’s consideration.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Local government reorganisation update(i) That the content of the letter from the Minister for Devolution received on 7 th September 2026, reviewing decisi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.