Resolved
That the Capital Strategy be approved.
Council approved this item on Wednesday 27 February 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Capital Strategy be approved.
That the Capital Strategy be approved.
Reason
The Capital Strategy sets out how the Council proposes to deploy its capital resources in order to assist it to achieve its corporate and service objectives.
1.1The previous Capital Strategy was approved by the Council on 22 February 2012. It covered the period 2012 to 2015. When Full Council considered revised Financial Regulations on 25 February 2009 it resolved that following discussion by the Cabinet the Capital Strategy be approved by Full Council.
1.2The purpose of the Capital Strategy is to set out how the Council proposes to deploy its capital resources in order to assist it to achieve its corporate and service objectives. It takes into account other relevant Council strategies, policies and plans and the views of partners and stakeholders with whom the Council is involved. It also takes account of the resources which are likely to be available to the Council to fund capital investment and the effect of that investment on the Council’s revenue budget. It covers the period 2013 to 2016. It will serve as a useful point of reference when determining or reviewing the Council’s Capital Programme.
2. Issues
2.1The 2013 to 2016 Capital Strategy is appended to this report at Appendix A.
2.2The principles set out in the Capital Strategy 2013 to 2016 are largely unchanged from the previous Strategy. However, some changes have been made to Section 5 (resources available to finance capital investment) and Section 11 (future capital programme). These are to reflect the current financial situation at the Council, which has seen a decline in resources available for capital investment since the previous Strategy was produced, although it should be noted that the previous Strategy predicted that this would occur. There are also changes to Section 1 (Introduction) and Section 4 (external influences, partners and consultation with stakeholders).
2.3The main changes are summarised below, referenced to the paragraph number concerned:
1.2The current Capital Programme amounts have been included. The approved Capital Programme over two years is £18,480,800 with £4,457,200 programmed for 2012/13. The revised 2012/13 Programme is £5,418,300. The corresponding amounts in the previous Strategy were: £21,638,800, £10,374,500 (2011/12) and £16,783,300 (revised 2011/12).
5.3The amount of usable capital receipts in hand at 1 April 2012 is £2.4m compared to £6.0m at 1 April 2011
5.5The balance on the ICT Development Fund at 1 April 2012 is £0.7m compared to £0.8m at 1 April 2011. The balance on the New Initiatives Fund at 1 April 2012 is £0.1m compared to £0.2m at 1 April 2011. The LSVT Capital Fund is exhausted with a nil balance at 1 April 2012 compared to a balance of £2.3m at 1 April 2011.
A number of additional items have been included, as follows:
4.7Reference to the establishment of a Town Centre Partnership.
5.7A 50/50 split between capital and revenue in respect of New Homes Bonus grant, as approved by Council.
5.10The establishment of a business rates pool and a consequent capital investment fund, which is a new development
5.11Proposals to pool income arising from the implementation of council tax reforms and a consequent capital investment fund, which is a new development.
11.2The appendices setting out assets available or potentially available for disposal contained in the Asset Management Strategy 2013 – 2016.
11.6An additional paragraph, which refers to an indicated shortfall in resources to finance projects to ensure continued service delivery and the possible need to borrow to finance such projects pending asset sales receipts being received.
2.4The Strategy was considered by Cabinet on 16 January 2013 and is recommended to you for approval. The Transformation and Resources Scrutiny Committee had earlier scrutinised the strategy, on 10 December 2012, and raised no comments.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
08(b): Appendix A: Capital Strategy 2013-2016Appendix | 351 KB | Download |
PDF |
Capital Strategy 2013-16Report | 23 KB | DownloadRead as text |
Follow Council at Newcastle-under-Lyme and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Jul 2026 | Appointment of honorary aldermen for the borough of newcastle-under-lymeThat the following be appointed as Honorary Aldermen for the Borough of Newcastle under Lyme. David Allport Gillian B... | Decided | Open |
| 8 Jul 2026 | Minutes of a previous meetingThat the minutes of the meeting held on 20 May, 2026 be agreed as a correct record. | Agreed | Open |
| 8 Jul 2026 | Reports of the chairs of the scrutiny committeesResolved : That the reports be received. | Decided | Open |
| 8 Jul 2026 | Reports of the chairs of the regulatory committeesResolved : That the reports be received. | Decided | Open |
| 20 May 2026 | Minutes of a previous meetingThat the minutes of the meeting held on 11 th February 2026 be agreed as a correct record. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.