(1) That progress on the delivery of the projects in the Carbon Management Delivery Plan for 2012/13 be note and the projects for the 2013/14 plan be approved in principle; and (2) That officers be authorised to seek external funding opportunities to support delivery of the remaining projects and to seek consideration of appropriate projects as part of the Invest to Save allocation process funded from the Budget Support Fund.
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
1.1The Council has a Carbon Management Programme to deliver a reduction in carbon emissions from it’s estate and operations by 30% from a baseline established in 2009/10. The Carbon Management Plan includes a Delivery Plan which outlines which projects should be completed subject to securing funding.
1.2A Carbon Board was formed to provide strategic direction and provide a link between the programme, the Executive Management Team and Cabinet. A key role of the Board is to report overall progress and seek executive approval for continuing delivery of the plan. Whilst the Board leads on delivery of the plan, previous Cleaner Greener and Safer Communities Overview and Scrutiny Committees have requested updates on progress as part of the Scrutiny process. Accordingly a report was presented to the Committee at it’s meeting in February 2013 and the projects were approved in principle.
2. Issues
2.1To date, projects in the plan have been funded using existing council resources and where possible external funds. The Council was successful in bidding to the Improvement and
1 Efficiency West Midlands (IEWM) for Low Carbon funding with £35,000 awarded in 2012. This funding was awarded on submission of satisfactory returns, evidence of financial expenditure and confirmation of compliance of funding conditions. The fundamental condition of this grant funding was that 10% of the subsequently generated annual revenue savings had to be paid to IEWM for 3 years following the first year of implementation. The updated Carbon Management Delivery Plan attached outlines the completion of the 2012/13 projects which were funded though the IEWM and council funding. as well as projects completed in previous years.
2.2As highlighted above the delivery of the Carbon Management Plan is monitored through the Carbon Board. A corporate Carbon Management Officers Team is responsible for implementing the plan seeking new projects as well as monitoring the progress of projects. The draft updated Carbon Management Delivery Plan attached includes projects that have been considered by these groups as appropriate. The projects which require funding and involve works to the council’s building have been ranked in order of priority based on costs and payback savings.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Local government reorganisation update(i) That the content of the letter from the Minister for Devolution received on 7 th September 2026, reviewing decisi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.