That members note: i. the decision taken by officers to offer an option on a parcel of council-owned land, consistent with the council’s scheme of delegation, and; ii. the work being undertaken by officers to enable the efficient movement of vehicles to/from the site whilst minimising nuisance to local residents.
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
To review the process which led to JCB’s decision to invest in the Blue Planet building and in particular to enable members to review the Officers’ decision to offer an option to develop Council-owned land at a later date.
Recommendations
That members note: (a) the decision taken by officers to offer an option on a parcel of council- owned land, consistent with the council’s scheme of delegation, and; (b) the work being undertaken by officers to enable the efficient movement of vehicles to/from the site whilst minimising nuisance to local residents.
Reasons
The main reason for making this decision was to facilitate economic growth for the long term economic well-being of the borough.
1. Introduction
1.1In July, JCB agreed to take a long lease of the prestigious Blue Planet building in the Chatterley Valley and take an option to acquire the adjoining Borough Council owned land to allow for later expansion. This is a major coup for the Borough and particularly welcome in a time of recession. The investment is expected to realise around 600 jobs of which around 350 would be here in the Chatterley Valley and around 250 at JCB HQ in Rocester. Additionally there is the potential for expanding the firm’s presence at Chatterley Valley which could create another 200-300 local jobs. This report considers how the investment came about and lessons for future working to see what went well and what might have gone better so that future inward investment efforts might be better managed.
Background
2.1The Borough Council have been the owner of this 20 hectare site, known as Ravensdale, in the Chatterley Valley for a number of years following its acquisition from two local businesses. The site was derelict, having been mined previously and having also a long history of former contaminative industrial processes based here. It was acquired by the Council with funding from the, then, Department of the Environment (DoE) to reclaim for industrial development. A condition of the agreement with the two companies was that two plots of developable land (comprising some 5.5 ha of the site) would then be offered back to them within a certain timescale or the Council would incur significant financial penalties reflecting the agreed value of the land.
. 2.2 The land was largely reclaimed but government funding ran out (or was switched to other priorities) before the necessary on-site and off-site infrastructure could be made. With still low land values prevailing in the area and with the need to invest further in the land, the Council faced the prospect of having to pay the financial penalties referred to above.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Local government reorganisation update(i) That the content of the letter from the Minister for Devolution received on 7 th September 2026, reviewing decisi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.