a) That members accept the outcome of the bidding process and the offer from Company B for a new 25 year full repairing and insuring lease containing options to break with rent based upon a percentage of turnover . b) That officers be authorised to complete a new lease with Company B on the terms summarised both within the report and at Appendix 3 (the appendix is not for publication as it contains exempt information as defined in paragraph 3 of Schedule 12A of Part I of the Local Government Act 1972). C) That the decision to extend the interim management and maintenance arrangements be noted.
Word for word from the decision Newcastle-under-Lyme published for this meeting.Source: moderngov.newcastle-staffs.gov.uk
To obtain Cabinet’s decision on the selection of a new operator and approval to the grant of a new lease of the golf centre at Keele on the terms outlined in this report.
Recommendation(s)
1. That members accept the outcome of the bidding process and the offer from Company B for a new 25 year full repairing and insuring lease containing options to break with rent based upon a percentage of turnover.
2. That officers be authorised to complete a new lease with Company B on the terms summarised both within the report and at Appendix 3 (the appendix is not for publication as it contains exempt information as defined in paragraph 3 of Schedule 12A of Part I of the Local Government Act 1972).
3. That the decision to extend the interim management and maintenance arrangements be noted.
Decision required
Taking account of both the officers’ recommendations and the views of the various Overview and Scrutiny Committees, are members satisfied with the overall process and content to accept the officers’ recommendations?
Reasons
Following a competitive bidding process, Company B submitted the best overall offer to justify the Council offering a lease on the terms described in the report. Additionally the offer from Company B is considered to represent market rental value and will provide necessary and appropriate investment in improvements to the golf course and premises.
The leasehold disposal is in accordance with both the Council’s Asset Management Strategy and Capital Strategy.
1.1The Council managed and operated a municipal golf activity at Keele until 2003 after which time it was considered appropriate to do so by way of a lease to a specialist commercial golf operator. Keele Golf Centre Limited (K.G.C.Ltd ), was subsequently selected as the tenant operator and on 1st April 2003 was granted a 25 year lease of the property.
1.2Following several years of difficult trading conditions K.G.C.Ltd. was placed into creditors’ voluntary liquidation on 21 March 2013. The Liquidator, in discharging his responsibilities, took steps to formally disclaim the commercial lease in relation to the golf centre with effect from 1st May 2013.
1.3In view of the above, Members instructed that interim course maintenance and management arrangements were established to enable ongoing pay-as-you-play municipal golf whilst a new tenant operator was sought. The need for interim arrangements was at that time envisaged to be a period of up to six months, to the end of October 2013. In order to meet the various stages of the process to establish a new operator for the course a timetable was established with the aim to install the new operator at the earliest possible time. That date is currently 3rd December 2013 and allows for the completion of legal formalities and operational gearing up following a decision being made at your meeting.
1.4Therefore the need for an extension to the temporary arrangements was identified, and in order to provide service continuity and ensure the facilities remains available for the public to use up to the point of handover, the current arrangement management and maintenance was extended, following consultation with the relevant Portfolio Holders, by one month.
2. Issues
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Local government reorganisation update(i) That the content of the letter from the Minister for Devolution received on 7 th September 2026, reviewing decisi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.